Section 7(4) in The Delhi Electricity Regulatory Commission (Levy and Collection of Fee and Charges by State Load Despatch centre) Regulations, 2007

(4)Disputes arising out of billing of SLDC charges shall be, as far as possible, settled by mutual negotiations. If the disputes are not resolved through mutual negotiations within sixty (60) days of the receipt of the bills, the matter shall be referred to the Commission through a petition by either of the parties. The decision of the Commission shall be final and binding on all the parties.