Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 12]

Bombay High Court

M/S. Ashoka Buildcon Limited,Thr. Its ... vs Maharashtra State Elecytricity ... on 26 June, 2019

Author: G.S.Kulkarni

Bench: G.S. Kulkarni

  pvr                                         1               13carpst15933-19.doc


                IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                               CIVIL APPELLATE JURISDICTION

                ARBITRATION PETITION (lodg)NO.15933 of 2019


 M/s.Ashoka Buildcon Ltd.                          ...Petitioner
       Versus
 Maharashtra State Electricity Distribution Co.Ltd
 through its Chief Engineer (Infra)                ...Respondent
                                      ---

 Mr.R.S.Apte, Senior Advocate I/b. Mr.A.A.Garge, for the Petitioner.

 Ms.Prerna Gandhi I/b. DSK Legal, for the Respondent.

                                          -----
                                   CORAM : G.S. KULKARNI, J.

                                   DATE   :     26 June 2019
                                              ---
 P.C.

 1.       Heard the learned Counsel for the petitioner and the learned

 Counsel for the respondent.

 2.       This is a petition filed under Section 11 of the Arbitration and

 Conciliation Act,1996 (for short 'the Act') whereby the petitioner has

 prayed for an arbitral tribunal to be appointed to adjudicate the disputes

 and differences between the parties which are stated to have arisen under

 the Letter of Award No.CE/DSPC/GFSS/T-7/48/587 dated 6 January

 2011 titled as "Turnkey Contract for Gaonthan Feeder Separation Scheme




::: Uploaded on - 06/07/2019                        ::: Downloaded on - 15/07/2019 06:07:54 :::
   pvr                                        2                  13carpst15933-19.doc


 for left-out village/wadies and balance feeders in Jalgaon and Nashik

 zone. The parties under the tender conditions of the contract, which is

 part of the contract agreement dated 21 January 2011, have agreed for

 the disputes and differences between the parties be referred to arbitration.

 The arbitration agreement is contained in clause 17 of the said agreement

 which reads thus:-

                  "17.    Arbitration
                  (a)     All disputes and differences between the parties under or in
                  connection with this Agreement or any breach thereof shall be
                  sought to be referred to the Chief Engineer (Distribution Special
                  Project Cell).

                  (b)     If such differences or disputes as between the parties
                  cannot be settled through Chief Engineer (Distribution Special
                  Project Cell) within stipulated time period as mentioned in tender
                  documents, they shall be settled by Arbitration. The Arbitration
                  shall be conducted in accordance with the provisions of the
                  Arbitration and Conciliation Act,1996 and any statutory
                  modification thereof from time to time.

                  (c)     The language of the arbitration shall be English and the
                  place of Arbitration shall be Mumbai.

                  (d)     Notwithstanding the existence of any disputes referred to
                  Arbitration, the parties shall continue to perform their obligations
                  under this agreement."



 3.       There is no dispute on the existence of an arbitration agreement

 between the parties. The petitioner by its letter dated 20 March 2019

 ('Exhibit I' page 33 of the paperbook) invoked the arbitration agreement

 and called upon the respondent to refer the disputes to be adjudicated by

 appointing an arbitral tribunal. As there was no response to the said notice




::: Uploaded on - 06/07/2019                          ::: Downloaded on - 15/07/2019 06:07:54 :::
   pvr                                    3                 13carpst15933-19.doc


 within the prescribed period of thirty days, the petitioner is before the

 Court making prayer for appointment of arbitral tribunal.



 4.       Learned Counsel for the respondent would also not dispute the

 existence of the arbitration agreement. Learned Counsel for the

 respondent fairly and on instructions, states that his client has no

 objection for appointing an arbitral tribunal.



 5.       In view of the consensus between the parties, the petition is

 required to be allowed. Hence, the following order:-

                                       ORDER

(i) Mr.Justice J.H.Bhatia, Former Judge of this Court, is appointed as a sole Arbitrator to arbitrate the disputes and differences between the parties under the Letter of Award No.CE/DSPC/GFSS/T-7/48/587 dated 6 January 2011 titled as "Turnkey Contract for Gaonthan Feeder Separation Scheme for left-out village/wadies and balance feeders in Jalgaon and Nashik Zone;

(ii) The learned prospective Sole Arbitrator, fifteen days before entering the arbitration reference, shall forward a statement of disclosure as per the requirement of Section 11(8) read with Section 12(1) of the Arbitration and Conciliation Act,1996, to the Prothonotary & Senior ::: Uploaded on - 06/07/2019 ::: Downloaded on - 15/07/2019 06:07:54 ::: pvr 4 13carpst15933-19.doc Master of this Court, to be placed on record of this petition with a copy to be forwarded to both the parties;

(iii) The fees payable to the arbitral tribunal shall be governed in accordance with the fees prescribed under the Bombay High Court (Fees Payable to Arbitrators) Rules, 2018;

(iv) At the first instance, the parties shall appear before the prospective arbitrator within 10 days from today on a date which may be mutually fixed by the prospective sole arbitrator;

(v) All contentions of the parties are expressly kept open.;

(vi) The petition is disposed of in the above terms. No costs.

(vii) Office to forward a copy of this order to the learned Arbitrator on the following address:

1302/1303, C-Wing, Ashok Garden, Dr.T.J.Road, Sewree, Mumbai-4400 015.
Tel.: 022-66306620 Mobile: 9969400001 Office: Natwar Chamber, 104, 1st floor, Nagindas Master, Road, Fort, Mumbai-400 001.
Tel: 022-22617436 E-mail: [email protected] (G.S.Kulkarni, J.) ::: Uploaded on - 06/07/2019 ::: Downloaded on - 15/07/2019 06:07:54 :::