Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 0]

Orissa High Court

Forum Projects Private Limited vs Berhampur Development Authority on 2 December, 2020

Equivalent citations: AIRONLINE 2020 ORI 221

Author: K.R.Mohapatra

Bench: K.R. Mohapatra

                            HIGH COURT OF ORISSA: CUTTACK

                                       ARBA NO.38 OF 2019

             In the matter of an Appeal under Section 37 of the Arbitration and
             Conciliation Act, 1996.
                                          ------------
             Forum Projects Private Limited,                    ........       Appellant
             Kolkata

                                           -Versus-

             Berhampur Development Authority,                    .......     Respondent
             Berhampur, Ganjam



                          For Appellant        : M/s. A.P.Bose, V.Kar, D.J.Sahoo,
                                                  S.K.Hota & A.Pattnaik

                          For Respondent        : Mr.S.P. Mishra, Sr. Advocate
                                                   M/s Bhabani Shankar Panigrahi

                                       ------------------------------------
                              Date of Hearing by Virtual Mode on 17.11.2020
                            Judgment delivered by Virtual Mode on 02.12.2020
                                       ------------------------------------
      P R E S E N T:

                 THE HONOURABLE SHRI JUSTICE K.R. MOHAPATRA
        ----------------------------------------------------------------------------------
K.R. Mohapatra, J          This appeal under Section 37 of the Arbitration

           Conciliation Act, 1996 (for short, the Arbitration Act') has been filed

           assailing the order dated 18.10.2019 (Annexure-1) passed by

           learned District Judge, Ganjam, Berhampur in Arbitration Petition

           No.4 of 2018, whereby he dismissed a petition filed by the present
                                       2

Appellant-Company under Section 9 of the Arbitration Act holding

it to be not maintainable.

2.          Short    narration   of       facts   necessary   for   proper

adjudication of this appeal are that pursuant to a 'Request for

Proposal' (RFP) by the Respondent - Berhampur Development

Authority (BDA) for development of Integrated Commercial - cum -

Residential Complex in Berhampur, the Appellant had participated

in the bid and became the highest bidder having quoted an amount

of Rs.9.40 crore. The project was decided to be undertaken on a

Public Private Partnership (PPP) basis. Upon compliance of initial

formalities and deposit of 25% of the bid amount, i.e., Rs.2.35

crore, the Respondent-BDA issued Letter of Intent (LOI) on

16.06.2008 in favour of the Appellant-Company requesting the

Appellant to deposit the balance contractual bid amount within a

period of 180 days and to execute the agreement. But, the

Appellant could not deposit the balance contractual bid amount of

Rs.7.05 crore within a stipulated period of 180 days. Hence, the

LOI issued in favour of the Appellant was cancelled vide Order

No.250/BeDA Berhampur dated 03.03.2015. Assailing the same,

the Appellant filed W.P.(C) No.8653 of 2015 before this Court. This

Court by order dated 11.05.2015, while issuing notice in the

matter, passed the following interim order.
                                     3

            "The opposite parties shall not issue (sic) any work
            order to anybody until further orders, subject to the
            petitioners depositing of Rs.2.75 crores before the
            Registrar (Judicial) of this Court in shape of A/C payee
            bank draft within a period of two weeks hence. In the
            event, the petitioners will not pay the same within the
            time stipulated, this interim order will stand vacated."

However, the Appellant could not deposit the said amount.

Subsequently,   the   Appellant   moved     learned   District   Judge,

Berhampur in Arbitration Case No.04 of 2018 under Section 9 of

the Arbitration Act with the following prayer:-

                  "It is therefore prayed that your honour may
            graciously be pleased
            a. To preserve the entire premises and necessary
               order in this regard be passed for its interim
               custody;
            b. Injunct the opp. party from creating any third
               party interest over the schedule property and
               obstructing the entry of the petitioner or his
               representatives to the schedule premises;
            c. Cost of the proceeding be awarded in favour of
               the petitioner;
            d. Any other relief as deem fit and proper be
               awarded in favour of the petitioner."

2.1         Along with the petition under Section 9 of the

Arbitration Act, the Appellant had also filed an interim application

praying inter alia to direct the parties to maintain status quo in

respect of the property in question. Upon receipt of notice, the

Respondent (opp. party therein) appeared and filed a petition on

18.09.2018 raising an issue with regard to maintainability of the

petition under Section 9 of the Arbitration Act. Both the petitions,

namely, petition with regard to         maintainability    as well as
                                     4

injunction were heard and disposed of on 18.10.2019 by a common

order under Annexure-1, which is under challenge in this appeal.

3.          Mr. Bose, learned counsel for the Appellant submitted

that the impugned order is an outcome of non-application of

judicial mind. The Respondent, accepting the initial deposit of

Rs.2.35 crore paid by the Appellant, issued the LOI as well as draft

Lease-cum-Development Agreement to the             Appellant. It was

returned to BDA being signed by the authorized signatory of the

Appellant, which was accepted in a joint meeting held on

08.09.2009 as a token of acceptance of the proposal made by the

Respondent. Clause 32.2 of Part-II of the draft agreement contains

the Arbitration Clause, which reads as follows:

            "32.2    Arbitration
                  In the event of Dispute arising out of or in
            connection with this Agreement not being resolved
            in accordance with the provisions of Article 32.1
            above, either Party shall be entitled to, by notice in
            writing ("Arbitration Notice") to the other Party,
            refer such Dispute for final resolution by binding
            arbitration in accordance with the Arbitration &
            Conciliation Act, 1996:
                   xxx          xxx              xxx"

3.1         It   his   submission   that   since   the   project     was

undertaken on Public Private Partnership (PPP) basis, signing of

the draft agreement by the Contractor, namely, the Appellant

makes it a concluded contract. He further submitted that the

Respondent, in paragraph 19 of their counter affidavit filed in
                                     5

W.P.(C) No.8653 of 2015 have categorically admitted that there is

an arbitration clause to resolve the dispute between the parties

arising out of the contract in question. Thus, there should be no

confusion with regard to existence of an arbitration clause in the

agreement. Accordingly, the petitioner in order to protect the lis

had filed the petition under Section 9 of the Arbitration Act.

3.2          The Respondent, after accepting the draft agreement

signed by the Appellant and issuance of LOI, is precluded from

raising an objection with regard to non-execution of the agreement.

3.3          The draft agreement was filed before learned District

Judge along with the petition under Section 9 of the Arbitration

Act. But, learned District Judge failed to take notice of the same

and made an erroneous observation to the effect that no written

argument was filed, which is an error apparent on the face of the

record.

4.           W.P.(C) No.8653 of 2015 has been filed assailing the

action of the Respondent in cancelling the LOI unilaterally. Thus,

pendency of the writ petition does not affect in anyway the

maintainability of the petition under Section 9 of the Arbitration

Act, as the cause of action for filing of both the petitions is

completely   different.   Thus,   learned District Judge    failed to

appreciate the scope of petition filed under Section 9 of the
                                    6

Arbitration Act. As      such, the impugned order being not

sustainable is liable to be set aside and a direction may be made to

adjudicate the petition filed under Section 9 of the Arbitration Act

afresh on merit by issuing necessary interim direction.

5.          Mr.   Mishra,    learned   Senior   Advocate       for    the

Respondent refuting the submissions made by learned counsel for

the Appellant, submitted that after issuance of LOI, the Appellant

did not come forward to deposit the balance bid amount of Rs.7.05

crore within the stipulated period and also to execute the Lease-

cum-Development Agreement (LCDA). As such, there is no

concluded contract between the parties in the eyes of law. Due to

non-cooperation of the Appellant neither any agreement could be

executed between the parties nor could it be registered as required

under Section 17 of the Registration Act, 1908 in order to make the

draft agreement a concluded contract between the parties. As such,

the Clause- 32.2 of the Part-II of the draft agreement cannot confer

any right on the Appellant to invoke the arbitration clause.

6.          Learned    District   Judge    considering     the       rival

contentions of the parties as well as materials available on record,

has rightly come to a conclusion that the Appellant has not filed

any written agreement. The averments made by Respondent-BDA

at paragraph-19 of the counter affidavit filed in W.P.(C) No.8653 of
                                    7

2015 cannot confer any right on the parties to invoke the arbitral

clause in absence of any concluded contract to that effect. In

support of his case, he relied upon a decision in the case of M/s.

National      Highways     and     Infrastructure      Development

Corporation     -v-   BSPL Infrastructure Limited, reported in

(2019) 15 SCC 25.

7.          Mr. Mishra, with reference to Section 7 of the Contract

Act, 1872 further submitted that in order to transform a proposal

into promise, the acceptance must be absolute. In absence of any

concluded contract between the parties the arbitration clause in

the draft agreement cannot be made operational. In support of his

contention, he relied upon the case of M/s P.S.A. Mumbai

Investments PTE. Limited -v- Jawaharlal Nehru Port Trust,

reported in (2018) 10 SCC 525.

8.          Mr. Mishra, learned counsel for the petitioner further

submitted that although an interim protection was granted to the

Appellant, it did not comply with the same. As such, the interim

order becomes ineffective after lapse of the stipulated period of two

weeks within which the Appellant was required to deposit a sum of

Rs.2.75 crore before the Registrar (Judicial) of this Court in shape

of A/c payee bank draft.
                                     8

9.           The object of Section 9 is to make interim arrangement

to protect the lis before or during arbitral proceeding or at any time

after making of the arbitral award. Since an interim protection has

already been granted by this Court on 11.05.2015 in W.P.(C)

No.8653 of 2015, a proceeding under Section 9 of the Arbitration

Act is not maintainable. It is a different issue that the Appellant did

not respect the interim protection granted by this Court, by

complying with the condition to make it operative. Even otherwise,

the demeanor of the Appellant does not entitle it to a protection

under Section 9 of the Arbitration Act.     The Appellant instead of

complying with the condition imposed in the interim order passed

by this Court, waited for three years and filed the instant

proceeding under Section 9 of the Arbitration Act in the year 2019.

Thus, the intention of the Appellant is apparent to delay the matter

and drag the litigation. In view of the above, the impugned order

warrants no interference and the appeal is liable to be dismissed.

10.          Upon hearing learned counsel for the parties and on

perusal of the record, it appears that the Appellant was the highest

bidder in the RFP by quoting the bid amount of Rs.9.40 crore. The

Appellant also made an initial deposit of 25% of the bid amounting

to Rs.2.35 crore and he was required to deposit the balance

amount of Rs.7.05 crore within a period of 180 days from the date
                                   9

of issuance of   LOI dated 16.06.2008 in its favour. It did not

deposit the said amount for which the LOI was cancelled vide order

dated 03.03.2015 and the initial bid amount deposited by the

Appellant was forfeited as well. Assailing the same, W.P.(C)

No.8653 of 2015 was filed by the Appellant, which is sub-judice.

This Court also passed a conditional interim order on 24.01.2020

in Misc. Case No.78 of 2019 (supra). But the condition imposed

was not complied with within the stipulated period of two weeks for

which the protection granted in the interim order lapsed. It further

appears that the Respondent-BDA had sent a copy of Draft Lease-

cum-Development Agreement to the Appellant. Although the

Appellant claims to have signed and submitted the same to the

Respondent as token of its acceptance of the offer, but, Respondent

on the other hand, took a stand that the Appellant did not come

forward to execute the agreement by depositing the balance bid

amount. But, the fact remains that the Appellant never deposited

the balance bid amount of Rs.7.05 crore within the stipulated date,

which was a condition for execution of agreement.

11.         The arbitration clause can only be made operational

/invoked, if there is a concluded contract between the parties.

Hon'ble Supreme Court in the case of M/s. P.S.A. Mumbai
                                  10

Investments PTE Ltd. (supra) at paragraphs 14, 19 and 20 held as

follows:

             "14. Under Section 7 of the Indian Contract Act,
             1872 in order to convert a proposal into a
             promise, the acceptance must be absolute and
             unqualified. It is clear on the facts of this case
             that there is no absolute and unqualified
             acceptance by the Letter of Award - two or three
             very important steps have to be undergone
             before there could be said to be an agreement
             which would be enforceable in law as a contract
             between the parties.
                 xxx               xxx               xxx

             19. Mr. Dave also strongly relied upon the
             judgment in INOX Wind Ltd v. Thermocables
             Limited. This judgment in paras 17 to 19
             thereafter made it clear that an exception to the
             general rule laid down in M.R. Engineers and
             Contractors Private Limited as to standard forms
             of practice containing arbitration clauses would
             be extended also to standard forms between
             individual persons and not merely standard
             forms of professional assessments.

             20. We may hasten to add that this judgment in
             INOX Wind Ltd v. Thermo cables Ltd. case would
             have no manner of application on the facts of
             this case for the reason that it has been found
             by us that there is no agreement between the
             parties at all in the facts of the present case,
             making it clear, therefore, that the arbitration
             clause contained in the draft Concession
             Agreement would not apply. Further, even the
             without prejudice argument of Mr. Sibal is
             worthy of acceptance. Mr. Sibal argued, relying
             strongly upon M.R. Engineers and Contractors
             (P) Ltd., that assuming that there was an
             arbitration clause which governs the parties, the
             said clause would be wholly inapt as it would
             only cover disputes between a Special Purpose
             Vehicle and the Respondent No.1 arising from
             the Concession Agreement not yet entered into,
                                    11

              and not between the Respondent No.1 and the
              appellant and Respondent No. 2. He is correct,
              and we agree with this contention as well."
                                        (emphasis supplied)

11.1        In the case of National Highway (supra) the Hon'ble

Supreme Court following the ratio decided in the case of M/s. P.S.A

Mumbai Investments PTE Ltd. (supra) at paragraph 16 held as

follows:

            "16. It is not possible to say that a standard form
            arbitration clause contained in a draft agreement
            would then oust Clause 6.1 and disturb the entire
            scheme of the schedule of bidding process. This
            being the case, it is clear that even at the stage of
            acceptance of LOA, if disputes arise between the
            parties, they can only be resolved by the courts of
            Delhi and not by arbitration. This being case, it is
            clear that PSA Mumbai Investments Pte. Ltd.
            judgment is, in fact, on all fours and would govern
            the facts of the present case."

12.         In view of the ratio decided by Hon'ble Supreme Court,

it is crystal clear that in order to invoke the arbitration clause and

make it operational, there must be a concluded contract between

the parties as envisaged under Section 7 of the Contract Act, 1872

which is conspicuously absent in the case at hand, in view of the

aforesaid reasons.

13.         Although Mr. Bose, learned counsel for the Appellant

vehemently argued that an agreement in a project under PPP mode

is not required to be signed by the Principal, but he could not

produce any material in support of his contention.
                                    12

14.         It is not clear as to why the Appellant preferred to file

writ petition in W.P.(C) No.8653 of 2015 assailing cancellation of

the LOI instead of invoking the arbitration clause, if at all it was

available to be invoked. It further appears that this Court

considering the case of the Appellant had also granted an interim

protection subject to compliance of certain conditions. The

Appellant did not comply with the said conditions. As such, the

interim protection granted by this Court lost its effect by efflux of

time. The averment at paragraph 19 of the counter affidavit filed by

the Respondent-BDA in W.P.(C) No.8653 of 2015 cannot confer a

right on the parties to invoke arbitration clause or confer

jurisdiction on the arbitrator to arbitrate the dispute, if at all it

was not there in the agreement itself. As has been discussed earlier

there is no concluded contract between the parties. Thus, the

Appellant could not have invoked the jurisdiction of learned

District Judge under Section 9 of the Arbitration Act, more

particularly when an interim protection in respect of the lis has

already been granted by this Court in W.P.(C) No.8653 of 2015.

15.         In view of the discussions made above, this Court is of

the considered opinion that learned District Judge has committed

no error in holding the petition under Section 9 of the Arbitration

Act not maintainable. Accordingly, this appeal being devoid of any
                                            13

merit stands dismissed, but in the circumstances there shall be no

order as to costs.

 15.1            Delink W.P. (C) No. 8653 of 2015 to be listed before the

assigned Bench.

15.2              LCR be sent back immediately.

15.3             Authenticated copy of this order downloaded from the

website of this Court shall be treated at par with the certified copy

of this order in the manner prescribed in this Court's Notice

No.4587 dated 25.03.2020.




                                           .................................
                                            K.R.MOHAPATRA, J.

Orissa High Court, Cuttack Dated the day of December, 2020/bct/ss