Section 144 in The Petroleum Rules, 2002

144. No objection certificate

.-(1) Where the licensing authority is the Chief Controller or the Controller, as the case may be, an applicant for a new license other than a license in Form III, XI, XVII, XVIII or XIX shall apply to the District Authority with two copies of the site-plan showing the location of the premises proposed to be licensed for a certificate to the effect that there is no objection to the applicant receiving a license for the site proposed and the District Authority shall, if he sees no objection, grant such certificate to the applicant who shall forward it to the licensing authority with his application in Form IX.
(2)Every certificate issued by the District Authority under sub-rule (1) shall be accompanied by a copy of the plan of the proposed site duly endorsed by him under his official seal.
(3)The Chief Controller or the Controller, as the case may be, may refer an application not accompanied by certificate granted under sub-rule (1) to the District Authority for his observations.
(4)If the District Authority, either on a reference being made to him or otherwise, intimates, to the Chief Controller or the Controller, as the case may be, that any license which has been applied for should not, in his opinion, be granted, such license shall not be issued without the sanction of the Central Government.
(5)The District Authority shall complete his inquiry for issuing NO OBJECTION CERTIFICATE (NOC) under sub-rule (1) and shall complete the action for issue or refusal of the NOC, as the case may be, as expeditiously as possible but not later than three months from the date of receipt of application by him.