National Green Tribunal

Shamsher Singh vs Govt. Of Nct Of Delhi & Ors on 2 May, 2025

Item No. 09                                                          Court No. 1

                BEFORE THE NATIONAL GREEN TRIBUNAL
                    PRINCIPAL BENCH, NEW DELHI

                              M.A. No. 105/2023
                                      In
                         Original Application No. 365/2021


 Shamsher Singh                                                     Applicant

                                   Versus

 Govt. of NCT of Delhi & Ors.                                    Respondent(s)



     Date of hearing: 02.05.2025


CORAM:         HON'BLE MR. JUSTICE PRAKASH SHRIVASTAVA, CHAIRPERSON
               HON'BLE MR. JUSTICE SUDHIR AGARWAL, JUDICAL MEMBER
               HON'BLE DR. A. SENTHIL VEL, EXPERT MEMBER


Respondent:    Mr. A.D.N. Rao, Senior Advocate with Ms. Richa Kapoor & Ms. Atika
               Singh, Advs. for Delhi Jal Board
               Ms. Jyoti Mendiratta & Ms. Ananya Basudha, Advs. for GNCTD
               Mr. Balendu Shekhar & Ms. Tanisha Samanta, Advs. for DPCC (Through
               VC)
               Ms. Puja S. Kalra & Mr. Virendra Singh, Advs. for MCD



                                     ORDER

1. In terms of the previous order granting time to the Delhi Jal Board (DJB) to file the affidavit of competent officer disclosing the timeline for providing sewage coverage to all the JJ Clusters and trapping the sewer lines and diverting them to the proper STPs, affidavit of Chief Engineer (SDW) DJB dated 29.04.2025 has been filed. In paragraph 4 of the said affidavit, it is stated that out of 639 total JJ Clusters, drains of 574 JJ Clusters have already been trapped in nearby DJB sewerage network.

2. Learned Senior Counsel appearing for DJB submits that in respect of remaining 65 JJ Clusters, details are contained in annexure-C which is as under:-

1
"Status of trapping of balance 65 nos. JJ drains S.N CE SE EE Name of JJ Discharge Present Timeless Command Remarks o. Concerned Concerned Concerned Cluster of Status (Not for STP/Propo JJC/drain Feasible/F Trapping sed DSTP (in KLD) easible) 1 Sh. Pawan SE(M)-4 Sh Dr. 25 NOC is 30.06.2025 Proposed For Sharma , Satender Ambedker awaited DSTP treating CE(Central Kumar, JJC Near from I & FC the North) EE(M)-03 Wazirabad departmnt discharge, Timarpur. and ASI installation also. of DSTP is proposed 2 Sh. Anil SE(M)-10 Sh. Okhla DTC 110 There is 30.06.2025 Okhla STP Kumar , Naresh Depot-I some CE(South) Kumar, public EE(M)-51 hindrance the drain will be trapped by 30 June 2025 (subject to the removal of hindrance.

) 3 Sh. Anil SE(M)-10 Sh. Gandhi 125 There is 30.06.2025 Okhla STP Kumar , Naresh Camp some CE(South) Kumar, Behind public EE(M)-51 Fruit & hindrance Vegitable the drain Market will be Okhla trapped by Railway 30 June Station 2025 (subject to the removal of hindrance. ) 4 Sh. Mukesh SE(M)-7 / Sh Harish Khub Ram 15 The work 30.06.2025 Sec-25, NA Jindal, SE(C )-6 Chander, park Pem of laying Rohini CE(West ) EE(M)-9 / Nagar the sewer Sh. Kirari line in N.K.Sharm Kirari GoC a, is in EE(Pr)Sr.-I progress and 70% work is completed by EE(PR)-

SR-1 ,this drain will be trapped into sewer line after commissio ning of sewer line. 5 Sh. Anil SE(M) -10/ Sh N.K Madrasi 330 Installation The Okhla STP NA Kumar, SE(DR.)PR Verma, Basti Near of DSTP is discharge CE(South)/ OJ -I EE(M) - Railway not from the JJC 2 Sh. Pankaj 41/ Sh. Line Jal feasible drain is Kumar Sanjay Viha due to ultimately Atray Kumar space out -falling CE(Dr)Proj - EE(C)DR -II constraint. in Barapulla II However, Drain which this drain is likely to is be trapped ultimately by out -falling 31.05.2025. in Barapulla Drain which is likely to be trapped by 31.05.2025 6 Sh. Anil SE(M) -10/ Sh N.K Shri Ram 140 Installation The Okhla STP Kumar , SE(DR.)PR Verma, JJC near of DSTP is discharge CE(South)/ OJ -I EE(M) - SPRINGDAL not from the JJC Sh. Pankaj 41/ Sh. E School feasible drain is Kumar Sanjay Dhaula due to ultimately Atray Kumar Kaun space out -falling CE(Dr)Proj - EE(C)DR -II constraints in Barapulla II . However, Drain which this drain is likely to is be trapped ultimately by out -falling 31.05.2025. in Barapulla Drain which is likely to be trapped by 31.05.2025 7 Sh. Anil SE(M) -10/ Sh N.K Ambedkar 300 Installation The Okhla STP Kumar , SE(DR.)PR Verma, Basti West of DSTP is discharge CE(South)/ OJ -I EE(M) - Block -II not from the JJC Sh. Pankaj 41/ Sh. R.K.Puram feasible, as drain is Kumar Sanjay discharge ultimately Atray Kumar into storm out -falling CE(Dr)Proj - EE(C)DR -II water in Barapulla II drain is Drain which directly is likely to from be trapped individual by household. 31.05.2025. Discharge pipes from individuals houses are undergrou nd up to the storm water drain.

Hence, it is difficult to collect discharge of JJC at single point.

However, this drain is 3 ultimately out -

falling in Barapulla Drain which is likely to be trapped by 31.05.2025 .

8 Sh. Anil SE(M) -10/ Sh N.K Leprosy 16 Installation The Okhla STP Kumar , SE(DR.)PR Verma, Colony of DSTP is discharge CE(South)/ OJ -I EE(M) - Infront of not from the JJC Sh. Pankaj 41/ Sh. Mohan feasible, as drain is Kumar Sanjay Singh discharge ultimately Atray Kumar Market into storm out -falling CE(Dr)Proj - EE(C)DR -II R.K.Puram water in Barapulla II drain is Drain which directly is likely to from be trapped individual by household. 31.05.2025. Discharge pipes from individuals houses are undergrou nd up to the storm water drain.

Hence, it is difficult to collect discharge of JJC at single point.

However, this drain is ultimately out -

falling in Barapulla Drain which is likely to be trapped by 31.05.2025 9 Sh. Anil SE(M)-10/ Sh N.K Nehru Ekta 85 Individual The Okhla STP Kumar, SE(DR.)PR Verma, Camp household discharge CE(South) OJ-I EE(M)-44 Sector-VII sewer from the R.K.Puram connection JJC drain is of JJC ultimately directly out-falling falling into in drain at Barapulla multiple Drain points. It is which is not likely to feasible to be lay the trapped by sewer line 31.05.20 to collect and trap 25.

4

the sewage flow.

However, this drain is ultimately out-falling in Barapulla Drain which will be trapped by Project Division.

10 Sh. Anil SE(M)-10/ Sh N.K S.P./J.P. 30 Individual The Okhla STP Kumar, SE(DR.)PR Verma, Colony household discharge CE(South) OJ-I EE(M)-44 Sector 6 sewer from the JJC R.K.Puram connection drain is of JJC ultimately directly out-falling falling into in Barapulla drain at Drain which multiple is likely to points. It is be trapped not by feasible to 31.05.2025. lay the sewer line to collect and trap the sewage flow..

However, this drain is ultimately out-falling in Barapulla Drain which will be trapped by Project Division.

11 Sh. Anil SE(M)-10/ Sh N.K Sector-I 95 Installation The Okhla STP Kumar , SE(DR.)PR Verma, R.K.Puram of DSTP is discharge CE(South)/ OJ-I EE(M)-41/ Police Post not from the JJC Sh. Pankaj Sh. Sanjay (Hanuman feasible drain is Kumar Kumar Camp) due to ultimately Atray CE(D EE(C)DR-I space out-falling constraint. in Barapulla However, Drain which this drain is likely to is be trapped ultimately by outfalling 31.05.2025. in Barapulla Drain which is likely to be trapped by 31.05.2025 .

5

12 Sh. Pankaj SE(DR.)PR Sh. V.D Ravi Dass 40 DPR for 9 months Proposed Kumar OJ -III/ Gautam, Camp feasible after DSTP Atray, SE(P) - 3 EE(C)Dr - Sector - 3 sites receipt of CE(Dr)Proj - XII/ R.K.Puram approved funds from II /Sh. Sh.Amit by NMCG NMCG and Bhupesh Tripathi,E after joint availibility of kumar,CE(S E( SDW) - inspection land for DW) V/ Sh N.K is DSTP Verma, prepared. EE(M) -44 The DPR and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare 6 new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

13 Sh. Anil SE(M) -10/ Sh N.K Nepali 175 This drain The Okhla STP Kumar , SE(DR.)PR Verma, Camp Near is discharge CE(South)/ OJ -I EE(M) - Bhanwar ultimately from the Sh. Pankaj 41/ Sh. Singh Camp out -falling JJC drain Kumar Sanjay Vasant in is Atray Kumar Vihar Barapulla ultimately CE(Dr)Proj - EE(C)DR -II Drain out - II which is falling in likely to be Barapulla trapped by Drain 31.05.2025. which is likely to be trapped by 31.05.20 25. 14 Sh. Anil SE(M)-10/ Sh N.K Sewa Camp 23 Installation The Okhla STP Kumar , SE(DR.)PR Verma, Behind of DSTP is discharge CE(South)/ OJ-I EE(M)-41/ Police Staff not from the Sh. Pankaj Sh. Sanjay Quarter feasible JJC drain Kumar Kumar Vasant due to is Atray EE(C)DR-II Vihar Depot space ultimately CE(Dr)ProjII Munirika constraints. out-

However, falling in this drain is Barapull ultimately a Drain out-falling which is in likely to Barapulla be Drain trapped which is by likely to be 31.05.20 trapped by 25.

7

31.05.2025 .

15 Sh. Anil SE(M)-10/ Sh N.K Shiva Camp 45 Installation The Okhla STP Kumar , SE(DR.)PR Verma, Vasant of DSTP is discharg CE(South)/ OJ-I EE(M)-41/ Vihar Near not e from Sh. Pankaj Sh. Sanjay Petrol feasible as the JJC Kumar Kumar Pump discharge drain is Atray EE(C)DR-II into storm ultimatel CE(Dr)ProjII water y out-

drain is falling in directly Barapull from a Drain individual which is household. likely to Discharge be pipes from trapped individuals by houses are 31.05.20 undergrou 25. nd upto the storm water drain.

Hence, it is difficult to collect discharge of JJC at single point.

However, this drain is ultimately out falling in Barapulla Drain which is likely to be trapped by 31.05.2025 16 Sh. Pankaj SE(DR.)PR Sh. V.D Priyanka 30 DPR for 9 months Proposed Kumar OJ-III/ Gautam, Camp feasible after DSTP Atray, SE(P)-3 EE(C)Dr- Mathura sites receipt of CE(Dr)ProjIII XII/ Road approved funds /Sh. Sh.Amit Opposite by NMCG from Bhupesh Tripathi, Sukhdev after joint NMCG kumar,CE(S EE(SDW)- Vihar Depot inspection and DW) V/ Sh N.K is availibility Verma, prepared. of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, 8 the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinize it and release the funds on approval of C/A of NMCG. The estimate has been reframed 9 and forwarded to NMCG for releasing the funds.

17 Sh. Pankaj SE(DR.)PR Sh. V.D CRRI Camp 40 DPR for 9 months Proposed Kumar OJ -III/ Gautam, Mathura feasible after DSTP Atray, SE(P) - 3 EE(C)Dr - Road sites receipt of CE(Dr)Proj - XII/ Opposite approved funds III /Sh. Sh.Amit Sukhdev by NMCG from Bhupesh Tripathi,E Vihar Depot after joint NMCG kumar,CE(S E( SDW) - inspection and DW) V /Sh N.K is availibility Verma, prepared. of land EE(M) -44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 10 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

18 Sh. Pankaj SE(DR.)PR Sh. V.D Priya Camp 40 DPR for 9 months Proposed Kumar OJ-III / Gautam, Mathura feasible after DSTP Atray, SE(P)-3 EE(C)Dr- Road sites receipt of CE(Dr)ProjIII XII/ Opposite approved funds /Sh. Sh.Amit Sukhdev by NMCG from Bhupesh Tripathi, Vihar Depot after joint NMCG kumar,CE(S EE(SDW)- inspection and DW) V/ Sh N.K is availibility Verma, prepared. of land EE(M)-44 The DPR for DST and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for 12 releasing the funds.

19 Sh. Pankaj SE(DR.)PR Sh. V.D Jhuggies 10 DPR for 9 months Proposed Kumar OJ-III/ Gautam, Kewal feasible after DSTP Atray, SE(P)-3 EE(C)Dr- Krishan sites receipt of CE(Dr)ProjII XII/ Chowk Post approved funds /Sh. Sh.Amit Rajokari by NMCG from Bhupesh Tripathi,E after joint NMCG kumar,CE(S E( SDW)-V inspection and DW) /Sh N.K is availibility Verma, prepared. of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB 13 will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

20 Sh. Anil SE(M)-11 Sh. Moti Lal 240 This drain 31.12.2025 Okhla STP Kumar, Prashant Nehru will be CE(South) Goel, Camp J.N.U trapped by EE(M)-45 Maintenance Wing after completion of work of ongoing work of rehabilitiat ion.

21 Sh. Pankaj SE(DR.)PR Sh. V.D Junapur 170 DPR for 9 months Proposed Kumar OJ-III/ Gautam, Bhim Basti feasible after DSTP Atray, SE(P)-3 EE(C)Dr- sites receipt of CE(Dr)ProjII XII/ approved funds /Sh. Sh.Amit by NMCG from Bhupesh Tripathi,E after joint NMCG kumar,CE(S E (SDW)-V inspection and DW) / Sh N.K is availibility Verma, prepared. of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring 14 to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The 15 estimate has been reframed and forwarded to NMCG for releasing the funds.

22 Sh. Anil SE(M)-11 / Sh Mandi 80 This JJC can 31.12.2026 Proposed Low layiing Kumar, SE(C)-4 Prashant Pahari be trapped DSTP area / CE(South) Goel, (Shambhav into DJB personal or EE(M)-46 Camp) sewer line individual / Sh. A.M. after septic tank Sharma, completion (Proposed EE(C)DR- of sewer DSTP) VI network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissioi ng of sewer network of adjoining area by Drainage Project Wing 23 Sh. Anil SE(M) -11 Sh Mandi 90 This JJC can 31.12.2026 Proposed Low laying Kumar, / SE(C) - 4 Prashant Village be trapped DSTP area / CE(South) Goel, Bapu Camp into DJB personal or EE(M) -46 sewer line individual / Sh. A.M. after septic tank Sharma, completion (Proposed EE(C)DR - of sewer DSTP) V network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissioi 16 ng of sewer network of adjoining area by Drainage Project Wing.

24 Sh. Anil SE(M) -11 Sh Mandi 45 This JJC can 31.12.2026 Proposed Low layiing Kumar, / SE(C) - 4 Prashant Village be trapped DSTP area / CE(South) Goel, (Biru Camp) into DJB personal or EE(M) -46 sewer line individual / Sh. A.M. after septic tank Sharma, completion (Proposed EE(C)DR - of sewer DSTP ) VI network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissio ning of sewer network of adjoining area by Drainage Project Wing.

25 Sh. Anil SE(M) -11 Sh Mandi 105 This JJC can 31.12.2026 Proposed Low layiing Kumar, / SE(C) - 4 Prashant Village be trapped DSTP area / CE(South) Goel, (Shanti into DJB personal or EE(M) -46 Camp) sewer line individual / Sh. A.M. after septic tank Sharma, completion (Proposed EE(C)DR - of sewer DSTP) VI network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissioi ng of sewer 17 network of adjoining area by Drainage Project Wing.

26 Sh. Pankaj SE(DR.)PR Sh. V.D Dr. 60 DPR for 9 months Proposed Kumar OJ - Gautam, Ambedkar feasible after DSTP Atray, III/SE(P) - EE(C)Dr - Satwari sites receipt of CE(Dr)Proj - 3 XII/ Mehrauli approved funds II /Sh. Sh.Amit by NMCG from Bhupesh Tripathi,E after joint NMCG kumar,CE(S E( SDW) - inspection and DW) V/ Sh N.K is availibility Verma, prepared. of land EE(M) -44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 18 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

27 Sh. Anil SE(M) -11/ Sh Suhurpuri 15 This JJC can 31.12.2026 Proposed Kumar, SE(C) - 4 Prashant Mehrauli be trapped DSTP CE(South) Goel, into DJB EE(M) -46 sewer line / Sh. A.M. with in 02 Sharma, months EE(C)DR - after V completion of sewer network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissioi ng of sewer network of 19 adjoining area by Drainage Project Wing.

28 Sh. Anil SE(M)-11/ Sh Kharak 20 This JJC can 31.12.2026 Proposed Kumar, SE(C)-4 Prashant Riwara be trapped DSTP CE(South) Goel, Satwari into DJB EE(M)-46 Mehrauli sewer line / Sh. A.M. with in 02 Sharma, months EE(C)DR-V after completion of sewer network laid by Project wing in adjoining areas. The expected date for trapping this drain into sewer line is 31.12.2026 by Maintenan ce Wing subject to commissioing of sewer network of adjoining area by Drainage Project Wing.

29 Sh. Pankaj SE(DR.)PR Sh. V.D Shanshi 50 DPR for 9 months Proposed Kumar OJ-III/ Gautam, Camp feasible after DSTP Atray, SE(P)-3 EE(C)Dr- Mathura sites receipt of CE(Dr)ProjII XII/ road approved funds /Sh. Sh.Amit Badarpur, by NMCG from Bhupesh Tripathi,E Tughlakaba after joint NMCG kumar,CE(S E( SDW)- d inspection and DW) V/ Sh N.K is availibility Verma, prepared. of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has 20 intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded 21 to NMCG for releasing the funds.

30 Sh. Pankaj SE(DR.)PR Sh. V.D Dora Tabu 20 DPR for 9 months Proposed Kumar OJ -III/ Gautam,E Camp Near feasible after DSTP Atray, SE(P) - 3 E( C)Dr - Tughlakaba sites receipt of CE(Dr)Proj - XII/Sh.Ami d Railway approved funds III /Sh. t Tripathi, Station in by NMCG from Bhupesh EE(SDW) - Mohan Co - after joint NMCG kumar,CE(S V /Sh N.K Operative, inspection and DW) Verma, Tughlakaba is availibility EE(M) -44 d prepared. of land The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it 22 was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG.

The estimate has been reframed and forwarded to NMCG for releasing the funds 31 Sh. Pankaj SE(DR.)PR Sh. V.D Indira 20 DPR for 9 months Proposed Kumar OJ -III/ Gautam, Camp feasible after DSTP Atray, SE(P) - 3 EE(C)Dr - Alimore sites receipt of CE(Dr)Proj - XII/ Mathura approved funds II /Sh. Sh.Amit road by NMCG from Bhupesh Tripathi, Mohan Co - after joint NMCG kumar,CE(S EE(SDW) - Operative, inspection and DW) V/Sh N.K Tughlakaba is availibility Verma, d prepared. of land EE(M) -44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 23 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG.

The estimate has been reframed and forwarded 24 to NMCG for releasing the funds.

32 Sh. Pankaj SE(DR.)PR Sh. V.D Ram Pyari 30 DPR for 9 months Proposed Kumar OJ-III/ Gautam,E Camp Near feasible after DSTP Atray, SE(P)-3 E( Nangia sites receipt of CE(Dr)ProjII C)DrXII/Sh Park Lal approved funds /Sh. .Amit kuan, by NMCG from Bhupesh Tripathi,E Tughlakaba after joint NMCG kumar,CE(S E( SDW)- d inspection and DW) V/ Sh N.K is availibilit Verma, prepared. y of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it 25 was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG.

The estimate has been reframed and forwarded to NMCG for releasing the funds.

33 Sh. Pankaj SE(DR.)PR Sh. V.D Shiv Camp 130 DPR for 9 months Proposed Kumar OJ-III/ Gautam, Lal Kuan feasible after DSTP Atray, SE(P)-3 EE(C)Dr- Badarpur sites receipt of CE(Dr)ProjII XII/ ChungiNo approved funds /Sh. Sh.Amit proposal.-2 by NMCG from Bhupesh Tripathi, &3 M.B. after joint NMCG kumar,CE(S EE(SDW)- Road, inspection and DW) V/ Sh N.K Tughlakaba is availibilit Verma, d prepared. y of land EE(M)-44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 26 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for 27 releasing the funds.

34 Sh. Anil SE(M) -11 Sh Khatta 185 Sewer line 30.04.2025 Okhla STP Kumar, / SE(C) - 4 Satender Camp work is in CE(South) Dabas, Gosain progress in EE(M) -52 Crusher the / Sh. A.M. M.B. Road vicinity. Sharma, Lal Kuan, Therefore EE(C)DR - Tughlakaba drain will V d be trapped in DJB sewerage network by Maintenance Wing by 30.04.2025 35 Sh. Pankaj SE(DR.)PR Sh. V.D Subash 130 DPR for 9 months Proposed Kumar OJ -III/ Gautam, Camp NTPC feasible after DSTP Atray, SE(P) - 3 EE(C)Dr - Badarpu sites receipt of CE(Dr)Proj - XII/ approved funds II /Sh. Sh.Amit by NMCG from Bhupesh Tripathi, after joint NMCG kumar,CE(S EE(SDW) - inspection and DW) V/ Sh N.K is availibility Verma, prepared. of land EE(M) -44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG 28 didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds 36 Sh. Anil SE(M) -11/ Sh Manoj BIW JJ 180 The invert 31.12.2026 Proposed Kumar, SE(C) - 4 Kr. Camp B.T. levels of DSTP CE(South) Sharma, Badarpu sewer line EE(M) -53 laid in / Sh. A.M. Gautampu Sharma, ri does not EE(C)DR - permit VI flow from JJC to be trapped and diverted to it. Hence it is required to trap it and take it to the nearest trunk 29 sewer located at a distance of about 0.5 KM on Mathura road. This alignment shall pass through NTPC land.

The issue has been taken up with NTPC for according permission to lay the sewer line through their land but no response is yet received.

Estimate is under preparatio n for this alignment in anticipation of the permission. However, the tentative timelines for trapping of this drain into DJB sewer network is 31.12.2026 37 Sh. Anil SE(M) - Sh Manoj Tajpur 50 The invert 31.12.2026 Proposed Kumar, 11/SE(C) - Kr. Pahari levels of DSTP CE(South) 4 Sharma, Badar sewer line EE(M) -53 laid in / Sh. A.M. Gautampu Sharma, ri does not EE(C)DR - permit VI flow from JJC to be trapped and diverted to it. Hence it is required to trap it and take it to the nearest trunk sewer 30 located at a distance of about 0.5 KM on Mathura road. This alignment shall pass through NTPC land.

The issue has been taken up with NTPC for according permission to lay the sewer line through their land but no response is yet received.

Estimate is under preparation for this alignment in anticipation of the permission. However, the tentative timelines for trapping of this drain into DJB sewer network is 31.12.2026 38 Sh. Pankaj SE(DR.)PR Sh. V.D Parasad 50 DPR for 9 months Proposed Kumar OJ - Gautam, Nagar, feasible after DSTP Atray, III/SE(P) - EE(C)Dr - Molarband sites receipt of CE(Dr)Proj - 3 XII/ Extn, approved funds II /Sh. Sh.Amit Badarpur by NMCG from Bhupesh Tripathi, after joint NMCG kumar,CE(S EE(SDW) - inspection and DW) V/ Sh N.K is availibilit Verma, prepared. y of land EE(M) -44 The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

31

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on open technology though DJB was of the view that funds may be released considering already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of 32 NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

39 Sh. Anil SE(M) -11/ Sh Manoj Bilas Pur 285 This JJC will 31.12.2026 Proposed Kumar, SE(C) - 4 Kr. Camp be trapped DSTP CE(South) Sharma, Molar Band into DJB EE(M) -53 NTPC, sewer line / Sh. A.M. Badarpur only after Sharma, laying of EE(C)DR - sewer VI network in surrounding UACs which is in approval under EE (C) Dr -VI.

Discharge of this JJC is going into Gurgaon Canal, not in River Yamuna.

Installation of DSTP is also not feasible as collection of discharge at one point is not feasible.

Since the trapping of this JJC is dependent on laying of sewer lines in surrounding UACs, the tentative timelines for trapping of this drain into DJB sewer network is 31.12.2026 .

40 Sh. Anil SE(M)-11/ Sh Manoj Subhash 55 This JJC will 31.12.2026 Okhla STP Kumar, SE(C)-4 Kr. Camp, Ali be trapped CE(South) Sharma, Gaon, Near into DJB EE )-54 Old Iron sewer line Bridge. to be laid in nearby 33 areas of Ali Vihar, Ali Ext., Ali Village, Jagdamba Colony etc. by EE (C) Dr-VI which is yet under approval stage. The JJC shall be trapped when this sewer line is laid and commissio ned, tentatively by 31.12.2026 by Maintenan ce Wing.

41 Sh. Anil SE(M)- Sh Manoj Abul Fazal 50 This JJC will 31.12.2026 Okhla STP Kumar, 11/SE(C)-4 Kr. Enclave be trapped CE(South) Sharma, Okhla into DJB EE )-54 Village sewer line, Across which has Canal been (Pucca completed Structure) by EE (C) Dr-VI. The JJC shall be trapped when this sewer line is laid and commissio ned, tentatively by 31.12.2026 by Maintenan ce Wing.

42 Sh. Pankaj SE(M)- Sh. P.K. Pankaj 145 The work 31.12.2026 Proposed Atray, 9/Sh Sharma, Garden of laying DSTP CE(Dr.)ProjI Adarsh EE(C)DRXI Goela Dairy the sewer Kumar, V/Sh.R.K. line in SE(Dr)Proj- Gupta, Goela I EE(P)SR-II Vihar GoC is in progress.

For DSTP at Goela, tenders have been received.

The drain will be trapped by Maintenan ce wing on completion 34 of sewer line and constructio n of DSTP work.

43 Sh. Pankaj SE(M)- Sh. P.K. JJC at Goela 145 The work 31.12.2026 Proposed Atray, 9/Sh Sharma, Dairy of laying DSTP CE(Dr.)ProjI Adarsh EE(C)DRXI Najafgarh the sewer Kumar, V/Sh.R.K. line in SE(Dr)Proj- Gupta, Goela I EE(P)SR-II Vihar GoC is in progress.

For DSTP at Goela, tenders have been received.

The drain will be trapped by Maintenance wing on completion of sewer line and constructio n of DSTP work 44 Sh. Pankaj SE(DR.)PR Sh. V.D Arjun Camp 325 DPR for 9 months Proposed Atray, OJIII/SE(P) Gautam, Mahipal feasible after DSTP CE(Dr.)ProjI -3 EE(C)Dr- Pur sites receipt of /Sh. XII/ approved funds Bhupesh Sh.Amit by NMCG from Kumar, Tripathi, after joint NMCG CE(SDW) EE(SDW)- inspection and V is availibilit prepared. y of land The DPR for DSTP and estimate has been checked by planning cell of DJB and sent to NMCG on 28.11.2023 for further action.

Referring to the MOM of 8th HLC, the NMCG has intimated DJB on 11.03.2024 stating that they need revised DPR if DJB floats tender on 35 open technology though DJB was of the view that funds may be released considerin g already submitted estimate & DPR. But, NMCG didn't agree to DJB request & called a meeting in the office of ED, NMCG on 7.5.2024 wherein, it was decided that DJB will prepare new estimate on the basis of fresh quotations & send it to NMCG after approval of the Competent Authority. Thereafter, NMCG will scrutinise it and release the funds on approval of C/A of NMCG. The estimate has been reframed and forwarded to NMCG for releasing the funds.

45 Sh. Pankaj SE(M)- Sh.P.K. Rangpur 630 This area is 31.03.2027 Proposed Atray, 9/Sh Sharma, Pahari in the DSTP CE(Dr.)ProjI Adarsh EE(C)DRXI Milkpur command Kumar, V Kohi of SE(Dr)Proj- Rangpuri I STP. Land 36 has been handed over to DJB for c/o DSTP.

Consultanc y for c/o DSTP at the stage of scrutiny of tender.

46 Sh. Pankaj SE(M)- Sh.P.K. Harijan 50 This area is 31.03.2027 Proposed Atray, 9/Sh Sharma, Balmiki in the DSTP CE(Dr.)ProjI Adarsh EE(C)DRXI Camp, command Kumar, V Rangpur of SE(Dr) Pahadi Rangpuri Proj-I STP. Land has been handed over to DJB for c/o DSTP.

Consultancy for c/o DSTP at the stage of scrutiny of tender.

47   Sh. Pankaj     SE(M)-        Sh.P.K.     Rangpuri     40    This area is 31.03.2027   Proposed
     Atray,         9/Sh          Sharma,     Pharai             in      the               DSTP
     CE(Dr.)ProjI   Adarsh        EE(C)DRXI   Nalla              command
                    Kumar,        V                              of
                    SE(Dr)Proj-                                  Rangpuri
                    I                                            STP. Land
                                                                 has been
                                                                 handed
                                                                 over to DJB
                                                                 for     c/o
                                                                 DSTP.

Consultancy for c/o DSTP at the stage of scrutiny of tender.

48 Sh. Pankaj SE(M)- Sh.P.K. Nehru 55 This is in 31.12.2026 Proposed Atray, 9/Sh Sharma, Camp the DSTP CE(Dr.)ProjI Adarsh EE(C)DRXI Behind command Kumar, V Satya Rani of SE(Dr)Proj- Farm Bijwasan I Bijwasan DSTP estimate is under A/A & ES.

49 Sh. Pawan SE(M)-5 EE(D)-052 Madrasi 162 Mori Gate 30.06.2025 Okhla STP Sharma , Basti Mori Drain, SPS CE(CentralN Gate under orth) construction to trapped the flow in Okhla STP catchment area.

50 Sh. Pawan SE(M)-5 EE(D)-052 Railway 36 Mori Gate 30.06.2025 Okhla STP Sharma , Colony Pul Drain, SPS under 37 CE(CentralN Mithai Mori constructio orth) Gate n to trapped the flow in Okhla STP catchment area.

51 Sh. Pawan SE(M)-5 EE(D)-052 DRP Line 156 Mori Gate 30.06.2025 Okhla STP Sharma , Pilli Kothi Drain, SPS CE(CentralN Lahori Gate under orth) construction to trapped the flow in Okhla STP catchment area.

52 Sh. Pawan SE(M)-5 EE(D)-052 Pulmithai 36 Mori Gate 30.06.2025 Okhla STP Sharma , Ke Kinare Drain, SPS CE(CentralN Lahori Gate under orth) construction to trapped the flow in Okhla STP catchment area.

53 Sh. Pawan SE(M)-5 EE(D)-052 Duffrin 18 Mori Gate 30.06.2025 Okhla STP Sharma , Bridge Mori Drain, SPS CE(CentralN Gate under orth) construction to trapped the flow in Okhla STP catchment area.

54 Sh. Dalbir SE(M)-1 EE(D)-052 Along 1350 Not Not NA Singh, Railway feasible as feasible CE(East) Lanes this JJC is Kailash located on Lanes Gali bank of No.-17 drain/Nall a due to which not feasible to connect to DJB sewer line.

55 Sh. Dalbir SE(M)-1 EE (D-014) Chander 220 Not Not NA Singh, Puri feasible as feasible CE(East) Railway this JJC is Lines Old located on Seelam Pur bank of drain/Nall a due to which not feasible to connect to DJB sewer line.

56 Sh. Dalbir SE(M)-1 EE (D-014) Taj Colony 1190 Not Not NA Singh, G.T. Road feasible as feasible CE(East) Railway no DJB Line New sewer line Seelam Pur exist in the nearby this JJC.

38

57 Sh. Dalbir SE(M) - 1 EE (D - Syamli 120 Not Not NA Singh, 014) Chirga, feasible as feasible CE(East) Near Police no DJB Check Post, sewer line Bihari exist in the Building nearby this Yaumna JJC. Bridge 58 Sh. Dalbir SE(M) - 1 EE (D - Aradhik 1218 Not Not NA Singh, 014) Nagar, Dehi feasible as feasible CE(East) U.P. Border no DJB G.T. Road sewer line Shahdara exist in the nearby this JJC.

59 Sh. Anil SE(M) -10 Sh N.K Bhanwar 275 This JJC Not NA Kumar, Verma, Singh Camp cannot be feasible CE(South) EE(M) -44 Behind trapped Janta Flat due to Block -D multiple Vasant out source, Vihar Phase topograph

-I y and Laying of sewer line and installation of lift station is not fessible.

                                                               This        JJ
                                                               Cluster
                                                               may       be
                                                               relocated
                                                               for
                                                               reducing
                                                               pollution
60   Sh. Anil     SE(M) -11   Sh.         Ram Dev       197    Not              Not        NA   Discharge
     Kumar,                   Prashant    Ka Dera              Feasible         Feasible        is going in
     CE(South)                Goel,       BSF Office           due        to                    low lying
                              EE(M) -45   Rajokari             multiple                         area (Not
                                          Pahari,              Discharge                        connected
                                          Delhi                and                              to any
                                                               collection                       drain)
                                                               point.
                                                               DSTP not
                                                               feasible
                                                               due        to
                                                               Forest
                                                               land. This
                                                               JJ Cluster
                                                               may       be
                                                               relocated
                                                               for
                                                               reducing

pollution. However, discharge is going in low lying area, not in River Yamuna 39 61 Sh. Anil SE(M) -11 Sh. Kusumpur 1230 Not Not NA Discharge Kumar, Prashant Pahari Feasible Feasible is going in CE(South) Goel, Block - B due to low lying EE(M) -45 Vasant multiple area (Not Vihar Discharge connected and to any collection drain) point.

DSTP not feasible due to Forest land. This JJ Cluster may be relocated for reducing pollution. However, discharge is going in low lying area, not in River Yamuna 62 Sh. Anil SE(M) -11 Sh. Jai Hind 250 Not Not NA Discharge Kumar, Prashant Camp near Feasible Feasible is going in CE(South) Goel, Masoodpur due to low lying EE(M) -45 Village multiple area (Not Vasant Kunj Discharge connected and to any collection drain) point.

DSTP not feasible due to Forest land. This JJ Cluster may be relocated for reducing pollution. However, discharge is going in low lying area, not in River Yamuna 63 Sh. Anil SE(M)-11 Sh. Sanjay 320 No JJC Not NA Kumar, Prashant Colony- found at feasible. CE(South) Goel, Mehrauli site. This EE(M)-46 Bhatti colony is Mines situated on forest land as informed by area JE (maintena nce) having big size plots, wide roads 40 etc. It was also observed during inspection along with NMCG official and JE maintenan ce that there are so many outfalls of SW drains out falling in low lying forest area/rocky area. This JJ Cluster may be relocated for reducing pollution.

64   Sh. Anil    SE(M)-11   Sh Manoj      New            195        Not            Not         NA
     Kumar,                 Kumar         Priyanka                  feasible       Feasible
     CE(South)              Sharma,       Camp near                 because
                            EE(M)-54      Sarita Vihar              collection
                                                                    of        JJC
                                                                    discharge
                                                                    is        not

possible at single point.

However, this discharge of this JJC is falling into Agra Canal, not in River Yamuna.

This JJ Cluster may be relocated for reducing pollution. 65 Sh. Anil SE(M)-11 Sh. Jhuggies 0 JJC does JJC does JJC does Kumar , Prashant Kholi Wala not exist not exist not exist CE(South) Goel, Baba at site. on on ground.

EE(M)-45 Mandir Hence, no ground.

Rajokari action is required Total discharge 12097 KLD or 2.67 MGD Approx "

41
3. In respect of details disclosed at serial nos.5, 6, 7, 8, 9, 10, 11, 13, 14, 15, submission of Senior Counsel for the DJB is that sewage drains of above JJ Clusters will be diverted to Barapullah drain and taken to Okhla STP. It is not in dispute that Barapullah drain is a storm water drain. The Tribunal in the matter of Nizamuddin West Association v Union of India & Ors.; IA No. 537/2023 in OA No. 06/20212 had directed that untreated sewage cannot be discharged in storm water drain. Hence, we find action which has been proposed in respect of the JJ Clusters noted above is contrary to the order of the Tribunal. We require the CEO, DJB, to appear virtually and explain the reasons on the next date of hearing for taking a decision to divert untreated sewage to the storm water drain which runs contrary to the order of the Tribunal.
4. List on 09.09.2025.
Prakash Shrivastava, CP Sudhir Agarwal, JM Dr. A. Senthil Vel, EM May 02, 2025 M.A. No. 105/2023 JG..