Section 25(5) in Tamil Nadu Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005

(5)In case of the thermal power generating stations declared under commercial operation on or after the notification of these Regulations, the base operation and maintenance expenses shall be fixed at 1.0% of the actual capital cost (as admitted by the Commission), in the year of commissioning and shall be subject to an annual escalation of 4% per annum for the subsequent years.