Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 0]

Madras High Court

M/S.Chikku Energy Private Limited vs M/S.Siemens Gamesa Renewable Power ... on 20 November, 2024

Author: C.V.Karthikeyan

Bench: C.V.Karthikeyan

                                     IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                       Dated: 20.11.2024

                                                            Coram:

                                    THE HONOURABLE MR.JUSTICE C.V.KARTHIKEYAN

                                              Arb.O.P.(Com.Div.) No.404 of 2024

                     M/s.Chikku Energy Private Limited,
                     Mysore Mercantile House,
                     #46, III & IV Floor, 36th Cross,
                     Jayanagar 4th T Block,
                     Bangalore - 560 041.
                     Rep. by its authorized Signatory Mr.Rakesh Shetty               .. Petitioner

                                                              Vs.

                     M/s.Siemens Gamesa Renewable Power Private Limited,
                     Formerly Known as Gamesa Renewable Private Limited,
                     The Futura IT Park, Block B,
                     8th Floor, No.334, Rajiv Gandhi Salai,
                     Sholinganallur,
                     Chennai – 600 119.
                     Presently at,
                     No.489, GNT Road, Thandal Kazhani Village,
                     Chennai – 600 052                                               .. Respondent

                                  This Petition filed under Section 11(6) of the Arbitration and
                     Conciliation Act, 1996 praying to appoint an arbitrator for the respondent or
                     alternatively, appoint a Sole Arbitrator to resolve the disputes amongst the
                     parties arising out of the two Work Orders dated 09.03.2016.
                                            For petitioner : Mr.S.Sathiyanarayanan


                     Page No.1/11


https://www.mhc.tn.gov.in/judis
                                                             ORDER

                                  This Original Application has been filed taking advantage of Section

                     11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an

                     Arbitrator consequent to two separate Work Order Agreements, the first one

                     relating to supply of 3 MV Grid – Interactive ground mounted solar PV system

                     in Karnataka and the second one relating to installation and commissioning of

                     3 MV Grid – Interactive ground mounted solar PV System in Karnataka.



                                  2.The petitioner, M/s.Chikku Energy Private Limited having registered

                     office at Bangalore in Karnataka is a company incorporated under the

                     provisions of the Companies Act, 2013 and are in the business of production,

                     generation, distribution, sales, development and maintenance of renewable

                     energy and renewable energy products. The Government of Karnataka had

                     called for tenders through KREDL for development of 1 to 3 MW Solar Power

                     Project for land owned farmers on a scheme. This was invited through online

                     bidding process. The farmers who owned land of 5 acres were eligible to set up

                     1 MW AC solar power project. The farmers who owned land of 10 acres were

                     eligible to set up 2 MW AC solar power project. The farmers who owned land

                     of 15 acres were eligible for 3 MW AC solar power project.

                     Page No.2/11


https://www.mhc.tn.gov.in/judis
                                  3.One of the Directors of the petitioner company, Mr.Halady Srinivasa

                     Shetty was eligible for allotment of 3 MW AC solar power project. He had

                     applied for such allotment. He owned 19 acres and 01 guntas of land at

                     S.No.104/2 of Devasamudra Village, Molakalmur Taluk, Chitradurga District.

                     He was also allotted 3MW AC solar power project. In accordance with the

                     allotment letter, he had to give a bank guarantee. He also furnished a bank

                     guarantee.



                                  4.M/s.Chamundeshwari Electricity Supply Company Limited entered

                     into a power purchase agreement with him. Mr.Halady Srinivasa Shetty was

                     under an obligation to commission the project within 18 months of execution

                     of the power purchase agreement executed on 20.06.2015.



                                   5.Thereafter, offers were invited from prospective bidders for actual

                     supply of the 3 MW AC solar power and for its installation. The respondent

                     was chosen as the successful bidder. Two work order agreements had been

                     entered with the respondent as stated above. Both the agreements had Clauses

                     to refer disputes to Arbitration.




                     Page No.3/11


https://www.mhc.tn.gov.in/judis
                                  6.Clause 17 of 1st Work Order Agreement (Supply of 3 MV Grid –

                     Interactive ground mounted solar PV System in the State of Karnataka

                     (Project) relating to arbitration is reproduced below:

                                          “17.Dispute Resolution: (a) Any Controversy or claim
                                    (“Dispute) arising out of or in connection with the validity,
                                    application or interpretation of this order shall be settled by
                                    consultation between the parties initiated by written notice of
                                    the Dispute to the other party. The parties shall attempt to
                                    settle such Disputes by way of negotiation within sixty (60)
                                    days of notice of any Dispute by any party to the other party.
                                    In such events, the parties shall each arrange for an officer
                                    or member of management with authority to meet resolve, in
                                    good faith, any pending Disputes during such time period.
                                       (b) In the event of parties cannot reach settlement pursuant
                              to sub-clause (i) supra within sixty (60) days of receipt notice
                              thereunder, the parties agree to refer such dispute to arbitration.
                              The venue of arbitration shall be Chennai. Each party will
                              appoint one arbitrator and two appointed arbitrators will
                              appoint the third arbitrator who will act as a presiding
                              arbitrator. The language of such arbitration shall be English.
                              The arbitration shall, in all other respects, be conducted as per
                              the Arbitration and Conciliation Act, 1996.
                                       (c) Responsibility of payment for all costs of arbitration,
                              excepting counsel fees, shall be as per the arbitration award.

                     Page No.4/11


https://www.mhc.tn.gov.in/judis
                                       (d) While any Dispute under this order is pending, the
                              parties shall continue to perform all of their respective
                              obligations under this order without prejudice to the final
                              determination in accordance with the provisions under this
                              Clause.”



                                  7.Clause 14 of 2nd Work Order Agreement (Installing & Commissioning

                     of 3 MV Grid – Interactive ground mounted solar PV System in the State of

                     Karnataka (“Project)) relating to arbitration is reproduced below:



                                        “14.Dispute Resolution: (a) Any Controversy or claim
                                  (“Dispute) arising out of or in connection with the validity,
                                  application or interpretation of this order shall be settled by
                                  consultation between the parties initiated by written notice of the
                                  Dispute to the other party. The parties shall attempt to settle
                                  such Disputes by way of negotiation within sixty (60) days of
                                  notice of any Dispute by any party to the other party. In such
                                  events, the parties shall each arrange for an officer or member of
                                  management with authority to meet resolve, in good faith, any
                                  pending Disputes during such time period.
                                        (b) In the event of parties cannot reach settlement
                                  pursuant to sub-clause (i) supra within sixty (60) days of receipt
                                  notice thereunder, the parties agree to refer such dispute to

                     Page No.5/11


https://www.mhc.tn.gov.in/judis
                                  arbitration. The venue of arbitration shall be Chennai. Each
                                  party will appoint one arbitrator and two appointed arbitrators
                                  will appoint the third arbitrator who will act as a presiding
                                  arbitrator. The language of such arbitration shall be English.
                                  The arbitration shall, in all other respects, be conducted as per
                                  the Arbitration and Conciliation Act, 1996.
                                        (c) Responsibility of payment for all costs of arbitration,
                                  excepting counsel fees, shall be as per the arbitration award.
                                        (d) While any Dispute under this order is pending, the
                                  parties shall continue to perform all of their respective
                                  obligations under this order without prejudice to the final
                                  determination in accordance with the provisions under this
                                  Clause.”


                                  8.Mr.Halady Srinivasa Shetty then assigned to the petitioner herein the

                     said agreements. It is for that reason that the petitioner had come forward

                     before this Court seeking appointment of an arbitrator.



                                  9.Disputes had arisen between the parties. The respondent had initially

                     responded to notices and had also come forward to negotiate the issues. The

                     petitioner had issued the first notice on 07.02.2022 and a second notice again

                     on 03.03.2022. They were both issued to two separate addresses. The first


                     Page No.6/11


https://www.mhc.tn.gov.in/judis
                     notice was not received and therefore, the second notice was issued.

                     Thereafter, the respondent had come forward accepting a joint inspection to be

                     conducted. There was a meeting between the parties on 13.05.2022. The

                     minutes of the meeting were also reduced in writing. It is alleged that still the

                     respondent did not fulfil their part of the agreement. Thereafter, an e-mail had

                     been sent by the respondent on 28.06.2022 for which the petitioner replied on

                     29.06.2022, again on 30.06.2022 and again on 04.07.2022. A further notice

                     was issued by the petitioner on 06.12.2023. In all these notices, the petitioner

                     had been insisting on resolution of the disputes either by negotiation or by

                     appointment of an arbitrator. There were further e-mail correspondences

                     between the parties on subsequent dates.



                                  10.It is under those circumstances, since the respondent had not come

                     forward for appointment of arbitrator though the petitioner had actually named

                     the arbitrator, this petition has been filed.



                                  11.The learned counsel stated that the agreements contemplated

                     appointment of two separate arbitrators and a third arbitrator to be appointed as

                     an umpire.

                     Page No.7/11


https://www.mhc.tn.gov.in/judis
                                   12.I am however of the considered opinion that it would only

                     appropriate that a sole arbitrator with some experience would be able to

                     examine the issues between the parties and come to a conclusion within a

                     reasonable period of time.



                                  13.In view of the fact that settlement could not be reached and the

                     respondent had also not come forward to accept for constitution of arbitral

                     tribunal, there was no other alternate left with the petitioner, but to approach

                     this Court seeking constitution of an arbitral tribunal.



                                  14.Accordingly, I would appoint Hon'ble Mr. Justice P. Kaliyarasan,

                     former Judge of this Court, [Plot No.64, 3rd Cross Street, CBI Colony,

                     Kandanchavai, Chennai - 96, as sole Arbitrator to enter reference on the

                     issues between the petitioner and the respondent.



                                  15.The following order is therefore passed:

                                  (i) The learned Arbitrator appointed herein, shall after issuing notice to

                     the parties and upon hearing them, endeavour to complete the arbitral

                     Page No.8/11


https://www.mhc.tn.gov.in/judis
                     proceedings and pass an award strictly in accordance with the provisions of the

                     Arbitration and Conciliation Act, 1996, as expeditiously as possible, preferably

                     within a period of twelve months after the date of completion of pleadings

                     under Sub-Section 4 to Section 23 as is contemplated in Section 29-A of the

                     Arbitration and Conciliation Act, 1996, without getting influenced by any of

                     the observations made by this Court in this order.



                                  (ii) The learned Arbitrator appointed herein shall be paid fees and other

                     incidental charges as may be fixed with the consent of parties or in accordance

                     with the provisions of the Arbitration and Conciliation Act, 1996, and the same

                     shall be borne by the parties equally. In case, the respondent remain ex parte,

                     the petitioner shall pay the entire fee and other incidental charges to the

                     Arbitrator and later recover the same from the respondent.



                                  16.This Arbitration Original Application stands allowed.



                                                                                               20.11.2024

                     smv
                     Index : Yes / No
                     Neutral Citation : Yes / No

                     Page No.9/11


https://www.mhc.tn.gov.in/judis
                     Speaking order : Yes / No



                                                          C.V.KARTHIKEYAN,J.

smv Arb.O.P (Com.Div.)No.404 of 2024 Page No.10/11 https://www.mhc.tn.gov.in/judis