Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 30, Cited by 0]

Madras High Court

The Management vs The Presiding Officer on 23 December, 2014

Author: S.Vaidyanathan

Bench: S.Vaidyanathan

       

  

   

 
 
  
IN THE HIGH COURT OF JUDICATURE AT MADRAS
 
DATE:    23.12.2014
 
CORAM:
 
THE HONBLE MR.JUSTICE S.VAIDYANATHAN
 
W.P.Nos.21656 of 2011 and 16285 of 2012
And M.P.Nos.1 and 1 of 2013
 
W.P.NO.21656 OF 2011
1    THE MANAGEMENT                
     M/S.FLORAM SHOES (INDIA) PVT. LTD  M.C.ROAD  
     AGARAMCHERRY POST  MADHANUR VIA  VELLORE 
     DISTRICT  REP. BY ITS MANAGING DIRECTOR.  
                                                                       .. PETITIONER
Vs
1    THE PRESIDING OFFICER                     
     ADDITIONAL LABOUR COURT  VELLORE.
2    MOHAMMED RAQEEF
 
3    E.SAMSATHBEGUM
    
4    S.SAANBABBI
    
5    Y.RASEEYA
    
6    A.BAIRVEEN
    
7    S.SABIRA
   
8    A.ABDUL SHUOOR
   
9    C.ANWAR
   
10   K.VASANTHI
     
11   T.GANESAN
     
12   A.USMAN
     
13   D.K.SANKAR(SOC)
   
14   K.DILSHATHI
     
15   A.TAJEEDEN
     
16   A.AZHAMUDIN
     
17   G.SARGUNAM
     
18   G.SIVAKUMAR
     
19   D.DAIDASS
     
20   B.MANIMEGALAI
     
21   R.MARTEEN
     
22   P.BALAN
     
23   P.SARASVATHI
     
24   P.MUTHULAKSHMI
     
25   R.MARAGATHAM
     
26   S.MARAGATHAM
     
27   M.SAMEENA
     
28   M.VEENDA
     
29   S.RANI (NOT PRESS)
     
30   G.KUPPABAI
     
31   M.BANUMATHI (NOT PRESS)
     
32   P.SELVAM
     
33   J.SUJATHA
    
34   S.KHAMURUNISSA
     
35   S.PARIMALA
     
36   A.JAYA
     
37   P.LATHA
     
38   J.JANBASHA
     
39   C.SIVANANTHAM
     
40   JAZIR
     
41   KANTHA
     
42   C.WILLIYAMS
     
43   V.S.GOVINDARAJ
     
44   N.BASKARAN
     
45   N.YUVARAJ
     
46   K.DHASITHAZIR
     
47   C.VALLI
     
48   A.LAKSHMI
     
49   B.KALIYAPPAN
     
50   B.SIVAKUMAR
     
51   V.SELVAKUMAR
     
52   J.KESAVAN
     
53   S.VENKATESAN
     
54   M.NIRMALA
     
55   V.RANI
     
56   M.JAISHANKAR
     
57   B.SANTHI
     
58   T.BUVANESHWARI
     
59   M.DHANALASKHMI
     
60   V.SIVARAJ
     
61   G.KUMARI
     
62   S.GANDHI
     
63   N.GANESAN
     
64   V.MUNUSAMY
     
65   S.VENKATESAN
     
66   D.THIRUMURUGAN
     
67   T.AZHILARASI
     
68   V.RAMESH
     
69   G.SIVAKUMAR
     
70   G.SRINIVASAN
     
71   G.SARATHI
     
72   SYED KARIMULLA
     
73   S.KALALKUMARI
     
74   B.K.JAYADEVI
     
75   S.RADHA
     
76   B.SELVAKUMAR
     
77   N.K.ABRAK AHAMED
     
78   R.HEMAMALINI
     
79   S.ESWARI
     
80   V.VIJAYA
     
81   S.NIHAR AHAMED
     
82   USMAN
     
83   MURAK ALI
     
84   M.JAYANTHI
     
85   R.THAVAMANI
     
86   G.VIJI
     
87   MEENAKSHI
     
88   I.SHEELA
     
89   T.TAMILARASI
     
90   M.MURUNNISA
     
91   P.AMUTHAVALLI
     
92   V.VANNAMAIYIL
     
93   K.SHEELADEVI
     
94   G.REVATHI
     
95   T.M.ASHAFF ALI
     
96   J.M.ASKAR BASHA
     
97   V.S.VENKATESAN
     
98   K.SANTHI
     
99   K.KUMARI
     
100  A.THOMASAM
     
101  C.PREMA
     
102  SURIYA PRAKASH
     
103  K.ULAGANTHAN
     
104  M.H.ABUBAKAR
     
105  K.DURAISAMY
     
106  N.SANTHURU
     
107  K.S.SANKAR
     
108  K.PREMALATHA
     
109  P.CHITRA
     
110  C.PALANI
     
111  V.KUMAR
     
112  G.PADMA
     
113  R.SANTHI
     
114  S.SHAMIYULLA
     
115  B.MANIMEGALAI
     
116  S.MEGALA
     
117  G.MALATHI
     
118  S.SANTHI
     
119  S.PREMA
     
120  S.GOWRI
     
121  SENTHILKUMAR
     
122  G.SATHISHKUMAR
     
123  M.DEVENDIRAN
     
124  P.MARGABANDU
     
125  T.SANTHASEELAN
     
126  P.LATHA
     
127  J.SHAKEERABEGAM
     
128  B.SUMATHI
     
129  L.RAHAMAN
     
130  V.S.RANGASAMY
     
131  R.NALINI
     
132  K.SARAVANAN
     
133  T.RAMANI
     
134  A.BASHA
     
135  P.KROLINA
     
136  G.ANJALI
     
137  G.MERRY
     
138  K.SAVITHRI
     
139  A.S.SURIYAKALA
     
140  S.SANTHA
     
141  A.LOGAMBIGAI
     
142  D.MUNUSAMY
     
143  J.RAMESH
     
144  R.GUHASELVI
     
145  K.PENNARASI
     
146  C.E.MOHAMED ISMAIL
     
147  C.N.THAIYUFF
     
148  V.SARASA 
149  K.RANI
     
150  M.AMMU
     
151  D.RAJA
     
152  Z.M.IBRAHIM
     
153  M.MUMTAZ
     
154  D.SARALA
    
155  H.ALIM BASHA
156  J.LATHA
     
157  M.KANAKAMBAL
     
158  C.VENDA (SOC)
     
159  R.KALAIYARASI
     
160  S.DOULATH KHAN
     
161  K.MALLIGA
     
162  G.JAMUNA
     
163  A.ALLIRANI (SOC)
     
164  S.SHAKERA
     
165  N.FARHANA
166  K.SIVAGAMI
167  C.LILLY
168  M.SAKTHIVEL
169  M.SIVAGAMI
     
170  L.USHA (NOT PRESS AS PER MEMO)
171  M.KARUNANIDHI
     
172  R.AKILABANU
173  Y.AMEEN
174  R.INDRANI                                       .. RESPONDENTS
 
Prayer:  This Writ Petition is filed under Article 226 of the Constitution of India, praying for the issuance of Writ of Certiorari, to call for the records pertaining to the common order, dated 28.7.2011 passed in C.P. Nos. 164/2005  165/2005  166/2005  167/2005  168/2005   169/2005  170/2005  207/2005  233/2005  244/2005   245/2005  246/2005  247/2005  248/2005  249/2005  349/2005  369/2005  86/2006  87/2006  88/2006  254/2006  67/2007  106/2007  107/2007  114/2007 and 115 of 2007 by the 1st respondent  Presiding Officer  Additional Labour Court  Vellore
 
W.P.No.16285 of 2012:
1    THE MANAGEMENT                                
     M/S. FLORAM SHOES (INDIA) PVT. LTD.  M.C. 
     ROAD  AGARAMCHERRY POST  MADHANUR VIA  
     VELLORE DISTRICT-635804  
     REP. BY ITS 
     MANAGING DIRECTOR.                         ..        PETITIONER
          Vs
1    THE PRESIDING OFFICER                         
     PRINCIPAL LABOUR COURT  VELLORE.
2    M.DEVINDRAN 
     S/O.G.MUNISAMY  NO.2/40  OLAKASI VILLAGE  
     VEPPUR POST  GUDIYATHAM TALUK  VELLORE 
     DISTRICT.
3    A.MOHAMED RAFIQUE 
     S/O.ABDUL AJIZ  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
4    I.SAMSHAD BEGUM 
     W/O.IQBAL  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
5    S.SAMBA BEE 
     W/O.SAYED BASHA  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
6    Y.RAZIA 
     W/O.SAYED BASHA  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
7    A.PARVEEN 
     W/O.SAYED BASHA  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
8    S.SABIRA 
     W/O.ABDUL SUKUR  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
9    ABDUL SUKUR 
     S/O.ABDUL SUBAN  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
10   C.A.ANWAR 
     S/O.SATHUR SAIBU  MAJID STREET  AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
11   K.VASANTHI 
     W/O.KASINATHAN  EDA STREET   AGARAMCHERRY 
     VILLAGE & POST  VELLORE DISTRICT.
12   T.GANESAN 
     S/O.THANGARAJ  KUTHAMPAKKAM VILLAGE  
     VADAKATHIPATTI POST  VELLORE DISTRICT.
13   A.USMAN 
     S/O.AFFIZ  PALUR VILLAGE AND POST  MADANUR 
     VIA  VELLORE DISTRICT.
14   K.DILSHATH 
     W/O.KADHAR BASHA  PALUR VILLAGE AND POST  
     MADANUR VIA  VELLORE DISTRICT.
15   A.THAJUDEEN 
     S/O.ABDUL SALAM  PALUR VILLAGE AND POST  
     MADANUR VIA  VELLORE DISTRICT.
16   A.AJIMUDEEN 
     S/O.ABDUL SALAM  PALUR VILLAGE AND POST  
     MADANUR VIA  VELLORE DISTRICT.
17   G.SARGUNA 
     W/O.KANNAN  PALUR VILLAGE AND POST  MADANUR 
     VIA  VELLORE DISTRICT.
18   G.SIVAKUMAR 
     S/O.GAJENDRAN  RANGAPURAM VILLAGE  PALUR 
     VILLAGE AND POST  MADANUR VIA  VELLORE 
     DISTRICT.
19   D.TITUS 
     S/O.DURAISAMY  PALUR VILLAGE AND POST  
     MADANUR VIA  VELLORE DISTRICT.
20   R.MARTIN 
     S/O.RAMAN  PERIYATHOTALAM VILLAGE AND POST  
     MADANUR VIA  VELLORE DISTRICT.
21   P.BALAN 
     S/O.PERUMAL  PERUMAL KOIL STREET  
     ALINCHIKUPPAM VILLAGE  RAJAKAL POST  
     GUDIYATHAM TALUK  VELLORE DISTRICT.
22   P.SARASWATHI 
     W/O.PARASURAMAN  MARIYAMMAN KOIL STREET  
     MELMONUR  VELLORE DISTRICT.
23   P.MUTHULAKSHMI 
     W/O.PARASURAMAN  NO.99  THAMARAIKULAM  
     PALLIKONDA  VELLORE DISTRICT.
24   R.MARAGATHAM 
     W/O.M.JAGANNATHAN  96/2  TKS STREET  
     PALLIKONDA  VELLORE DISTRICT.
25   S.MARAGATHAM 
     W/O.GOPAL  BAZAR STREET  VETTUVANAM VILLAGE 
     AND POST  PALLIKONDA  VELLORE DISTRICT.
26   M.SAMEENA 
     D/O.MEHAYUB JOHN SAIBU  AGARAMCHERRY VILLAGE 
     AND POST  MADANUR VIA  VELLORE DISTRICT.
27   M.VENDA 
     W/O.GOVINDARAJ  NAIDU STREET  AGARAMCHERRY 
     VILLAGE AND POST  MADANUR VIA  VELLORE 
     DISTRICT.
28   G.KUPPA BAI 
     W/O.SARAVANAN  AMMAN NAGAR  AGARAMCHERRY 
     VILLAGE AND POST  MADANUR VIA  VELLORE 
     DISTRICT.
29   J.SUJATHA 
     W/O.NANTHAGOPAL  THANGAL VILLAGE  OTHIYATHUR 
     POST  PALLIKONDA  VELLORE DISTRICT.
30   S.KAMARUNIZA 
     W/O.JOHN BASHA  MAJITH STREET  AGARAMCHERRY 
     VILLAGE AND POST   VELLORE DISTRICT.
31   S.PARIMALA 
     D/O.SAMPATH  104  PALUR VILLAGE & POST  
     MADANUR  VELLORE DISTRICT.
32   A.JAYA 
     W/O.ANUMUTHU  BHARATHI NAGAR  MADANUR  
     VELLORE DISTRICT.
33   P.LATHA 
     W/O.J.KESAVAN  109  PALUR VILLAGE  MADANUR 
     VIA  VELLORE DISTRICT.
34   J.CHAN BASHA 
     S/O.JAYANULLAH  MAJITH STREET  AGARAMCHERRY 
     VILLAGE AND POST   VELLORE DISTRICT.
35   C.SIVANATHAM 
     S/O.CHINNARAJ  BHARATHI NAGAR  MADANUR  
     VELLORE DISTRICT.
36   A.JAGIR 
     S/O.ABDUL RAKEEN  MAJITH STREET  
     AGARAMCHERRY VILLAGE AND POST   VELLORE 
     DISTRICT.
37   K.KANTHA 
     W/O.KARUNAKARAN  PERIYATHOTTALAM  MADANUR 
     POST  VELLORE DISTRICT.
38   C.WILLIAMS 
     S/O.CHRISTUDOSS  MV KUPPAM VILLAGE  MELPATTI 
     POST  VELLORE DISTRICT.
39   V.S.GOVINDARAJ 
     S/O.SAMINATHAN  2/123  MUPAR STREET  VENKILI 
     VILLAGE AND POST  VELLORE DISTRICT.
40   N.BASKARAN 
     S/O.NATARAJAN  JAMIN KULITHIGAI VILLAGE  
     VENKILI POST  VELLORE DISTRICT.
41   N.YUVARAJ 
     S/O.NATARAJAN  JAMIN KULITHIGAI VILLAGE  
     VENKILI POST  VELLORE DISTRICT.
42   K.DHASTHAGIR 
     S/O.KALEEL  PADE SAIBU STREET  THALAYATHAM  
     GUDIYATHAM TALUK  VELLORE DISTRICT.
43   C.VALLI 
     W/O.BALAKRISHNAN  RANGAPURAM  PALUR VILLAGE 
     AND POST  MADANUR VIA  VELLORE DISTRICT.
44   A.LAKSHMI 
     W/O.NATARAJAN  ANANGANALLUR VILLAGE AND POST 
     GUDIYATHAM TALUK  VELLORE DISTRICT.
45   K.KALIYAPPAN 
     S/O.R.KRISHNAN  BATTAI STREET  SERPADI 
     VILLAGE AND POST  ODUKATHUR  VELLORE 
     DISTRICT.
46   B.SIVAKUMAR 
     S/O.K.BALARAMAN  RN KUPPAM POST  GR PALAYAM 
     VIA  MADANUR  VELLORE DISTRICT.
47   V.SELVAKUMAR 
     S/O.M.VELU  AGARAM VILLAGE & POST   MADANUR 
     VIA  VELLORE DISTRICT.
48   J.KESAVAN 
     S/O.JAYARAMAN  PALUR VILLAGE & POST   
     MADANUR VIA  VELLORE DISTRICT.
49   S.VENKATESAN 
     S/O.SETTU  PALUR VILLAGE & POST   MADANUR 
     VIA  VELLORE DISTRICT.
50   M.NIRMALA 
     D/O.MATHIAZHAGAN  PALUR VILLAGE & POST   
     MADANUR VIA  VELLORE DISTRICT.
51   V.RANI 
     D/O.LOGANATHAN  RANGAPURAM VILLAGE  PALUR 
     POST  VELLORE DISTRICT.
52   M.JAISANKAR 
     S/O.MURUGESAN  32/36  AMMANI NAGAR  
     PALLIKONDA POST  VELLORE DISTRICT.
53   B.SHANTHI 
     W/O.BASKAR  97  KADAI STREET  AGARAM POST  
     VELLORE DISTRICT.
54   BUVANESWARI 
     W/O.NANTHAKUMAR  THIRUVALLUVAR NAGAR  OPP. 
     HOLY ANGELS SCHOOL  PALLIKONDA  VELLORE 
     DISTRICT.
55   M.DHANALAKSHMI 
     W/O.VELAN  AMMAIYAPPAN STREET  SANRORKUPPAM  
     AMBUR.
56   V.SIVARAJ 
     S/O.VEERASAMI  PATCHAIYAMMAN KOIL STREET  
     ALINCHIKUPPAM VILLAGE  RAJAKAL POST  VELLORE 
     DISTRICT.
57   G.KUMARI 
     W/O.MUNIRATHINAM  SAMINATHAPURAM  PALUR POST 
     MADANUR VIA  VELLORE DISTRICT.
58   G.GANDHI 
     S/O.A.GOVINDAN  VADAKATHIPATTI VILLAGE & 
     POST  VELLORE DISTRICT.
59   N.GANESAN 
     S/O.NAARAYANAN  549  TNHB PHASE-I  
     KRISHNAGIRI ROAD  THIRUPATTUR.
60   S.VENKATESAN 
     S/O.SEENU NAIDU  119  SCHOOL STREET  
     KOMMALAM KUTTAI POST  OTHIYATHUR  VELLORE 
     DISTRICT.
61   D.THIRUMURUGAN 
     S/O.DURAISAMI  110  BAJANAI KOIL STREET  
     VADAKATHIPATTI VILLAGE & POST  VELLORE 
     DISTRICT.
62   T.EZHILARASI 
     W/O.THIRUMURUGAN  110  BAJANAI KOIL STREET  
     VADAKATHIPATTI VILLAGE & POST  VELLORE 
     DISTRICT.
63   V.RAMESH 
     S/O.VINAYAGAM  VADAKATHIPATTI VILLAGE & POST 
     VELLORE DISTRICT.
64   G.SIVAKUMAR 
     S/O.GANESAN  1/143  VADAKATHIPATTI VILLAGE & 
     POST  VELLORE DISTRICT.
65   G.SRINIVASAN 
     S/O.GANESAN  1/143  VADAKATHIPATTI VILLAGE & 
     POST  VELLORE DISTRICT.
66   G.SARATHI 
     VADAKATHIPATTI VILLAGE & POST  VELLORE 
     DISTRICT.
67   S.SAYED KARIMULLAH 
     S/O.AMEEN  5/150  5TH STREET  BEERAN NAGAR  
     MOSAN PETTAI  GUDIYATHAM  VELLORE DISTRICT.
68   S.KALAIKUMARI 
     W/O.SOUNDARAPANDI  1/29  AGARAMCHERRY 
     VILLAGE AND POST  VELLORE DISTRICT.
69   B.K.JALADEVI 
     W/O.BALASUNDARAM  NO.9  METTU STREET  
     VETTUVANAM VILLAGE & POST  VELLORE DISTRICT.
70   S.RADHA 
     W/O.KANNAN  EYEL ROAD STREET  VETTUVANAM 
     VILLAGE & POST  VELLORE DISTRICT.
71   B.SELVAKUMAR 
     S/O.BULLAN  MADANUR VIA  VELLORE DISTRICT.
72   N.K.ABRAR AHAMED 
     S/O.KHALEEL AHAMED  NO.50/1  KANAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
73   R.HEMAMALINI 
     D/O.RAMACHANDRAN  NO.12  BUDHAR NAGAR  
     PALLIKONDA  VELLORE DISTRICT.
74   S.ESWARI 
     W/O.VENUGOPAL  OPP. RAJESWARI MILL  
     RAGAVENDRA STREET  R.S.ROAD  GUDIYATHAM.
75   V.VIJIYA 
     W/O.BABU  NO.56  KOTTAI STREET  PALLIKONDA  
     VELLORE DISTRICT.
76   S.NIKAR AHAMED 
     S/O.SALEEM SAIBU  43  MILLATH STREET  
     PALLIKONDA  VELLORE DISTRICT.
77   K.USMAN 
     S/O.KHADAR USAIN  MUSLEEM STREET  
     PERIYACHETTY KUPPAM  GUDIYATHAM TALUK  
     VELLORE DISTRICT.
78   Z.MUBARAM 
     S/O.ZEEYAUDEEN  52/49  KANAR STREET  
     PALLIKONDA.
79   M.JAYANTHI 
     W/O.RAMESH  21/61  GOVINDAPADI STREET  
     PALLIKONDA VIA  VELLORE DISTRICT.
80   R.THAVAMANI 
     D/O.RAMAN  KONNAIYATHAM VILLAGE  MELALATHUR 
     POST  GUDIYATHAM TALUK  VELLORE DISTRICT.
81   G.VIJI 
     D/O.T.GANESAN  CHENNACHERRY VILLAGE  
     AGARAMCHERRY POST  MADANUR VIA  VELLORE 
     DISTRICT.
82   D.MEENAKSHI 
     W/O.JAISANKAR  32/36  AMMANI NAGAR  
     PALLIKONDA VIA  VELLORE DISTRICT.
83   I.SHEELA 
     W/O.RAJAMANICKAM  286  BAJANAI KOIL STREET  
     VIRINCHEPURAM  VELLORE DISTRICT.
84   T.TAMILARASI 
     S/O.VISWANATHAN  25  VEERASAMY STREET  
     MULLIPALAYAM  VELLORE DISTRICT.
85   M.MUNIRUZA 
     D/O.ESSAC AHAMED  58A/30  AMMANI NAGAR  
     PALLIKONDA  VELLORE DISTRICT.
86   V.VANAMAYEL 
     W/O.VENKATESAN  73  KOTHAKUPPAM  42  INDRA 
     KUDIYIRUPPU  PUDHUMANAI  MELALATHUR POST  
     VELLORE DISTRICT.
87   K.SHEELA DEVI 
     W/O.SAMIVEL  73  KOTHAKUPPAM  42  INDRA 
     KUDIYIRUPPU  PUDHUMANAI  MELALATHUR POST  
     VELLORE DISTRICT.
88   G.REVATHI 
     W/O.DAYALAN  MARIYAMMAN KOIL STREET  
     GUDIYATHAM VILLAGE  VELLORE DISTRICT.
89   T.M.ASRAF ALI 
     S/O.T.M.SAIYATHULLAH  55/25  HAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
90   J.M.ASKAR BASHA 
     S/O.AHMED BASHA  32  MILLATH STREET  
     PALLIKONDA  VELLORE DISTRICT.
91   V.S.VENKATESAN 
     S/O.SAMIVEL  28/15  NEW KANAR STREET  AYYAYU 
     NAGAR  PALLIKONDA  VELLORE DISTRICT.
92   K.SANTHI 
     D/O.KANNAN  92  SAMINATHAPURAM  PALUR 
     VILLAGE & POST  VELLORE DISTRICT.
93   K.KUMARI 
     D/O.KANNAN  92  SAMINATHAPURAM  PALUR 
     VILLAGE & POST  VELLORE DISTRICT.
94   A.THAMSAM 
     W/O.KANNAN  92  SAMINATHAPURAM  PALUR 
     VILLAGE & POST  VELLORE DISTRICT.
95   C.PREMA 
     W/O.D.ANBAZHAGAN  KONNAIYATHAM VILLAGE  
     MELALATHUR POST  GUDIYATHAM TALUK  VELLORE 
     DISTRICT.
96   K.DURAISAMI 
     S/O.KANNAPPAN  36  RAIL ROAD STREET  
     VETTUVANAM VILLAGE & POST  VELLORE DISTRICT.
97   C.PALANI 
     S/O.CHINNADURAI  BHRAMANA MANGALAM  
     VETTUVANAM POST  PALLIKONDA  VELLORE 
     DISTRICT.
98   V.KUMAR 
     S/O.GOPAL  9  KANNADHASAN NAGAR  
     SANRORKUPPAM  AMBUR  VELLORE DISTRICT.
99   G.PADMA 
     W/O.GOVINDASAMY  AGARAMCHERRY VILLAGE & POST 
     MADANUR VIA  VELLORE DISTRICT.
100  R.SHANTHI 
     D/O.PANNIRSELVAM  187  RS ROAD  SETHUKARAI 
     POST  GUDIYATHAM TALUK  VELLORE DISTRICT.
101  S.SAMIULLAH 
     D/O.SAMEER AHAMED  NO.29  MILLATH STREET  
     PALLIKONDA  VELLORE DISTRICT.
102  P.MANIMEGALAI 
     W/O.VENKATESAN  6/4  KASTHURIBAI STREET  
     KEMARANIPET  PALLIKONDA  VELLORE DISTRICT.
103  S.MEGALA 
     W/O.LAKSHMANAN  KOLLAMANGALAM VILLAGE & POST 
     MADANUR VIA  VELLORE DISTRICT.
104  G.MALATHI 
     W/O.BHAGAVANDOSS  57/140  PUDUMANAI  
     MELALATHUR VILLAGE AND POST  VELLORE 
     DISTRICT.
105  S.SHANTHI 
     W/O.ARUMUGAM  OM SAKTHI KOIL STREET  AGARAM 
     POST  MADANUR VIA  VELLORE DISTRICT.
106  S.PREMA 
     W/O.ANNADURAI  OM SAKTHI KOIL STREET  AGARAM 
     POST  MADANUR VIA  VELLORE DISTRICT.
107  S.GOWRI 
     W/O.YESSU  MALAIYAMODU STREET   AGARAM POST  
     MADANUR VIA  VELLORE DISTRICT.
108  R.SENTHIL KUMAR 
     S/O.RANGANATHAN  SN PALAYAM  AGARAM POST  
     MADANUR VIA  VELLORE DISTRICT.
109  P.MARGABANDU 
     S/O.PANNIRSELVAM  NO.9  AVVAYAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
110  T.SANTHASEELAN 
     S/O.A.THANGARAJ  SOUTH COLONY  AGARAM 
     VILLAGE & POST  VELLORE DISTRICT.
111  V.S.RANGASAMY 
     S/O.SUBRAMANI  THEERTHANATHIPURAM  
     VETTUVANAM VILLAGE & POST  PALLIKONDA  
     VELLORE DISTRICT.
112  R.NALINI 
     W/O.G.RAJASEKAR  SN PALAYAM  AGARAM POST  
     MADANUR VIA  VELLORE DISTRICT.
113  K.SARAVANAN 
     S/O.KRISHNAN  PILLAYAR KOIL STREET  
     VETTUVANAM VILLAGE & POST  PALLIKONDA  
     VELLORE DISTRICT.
114  T.RAMANI 
     W/O.SATHIYARAJ  AVVAI NAGAR  SERUVANKI  
     GUDIYATHAM  VELLORE DISTRICT.
115  VALLI 
     W/O.SINGARAM  262  KUDANAGARAM VILLAGE & 
     POST  2ND BLOCK  GUDIYATHAM TALUK  VELLORE 
     DISTRICT.
116  M.JAYANTHI 
     W/O.THENNARASU  2/124  ANNA NAGAR  
     KUDANAGARAM VILLAGE & POST  GUDIYATHAM TALUK 
     VELLORE DISTRICT.
117  K.SELVI 
     WO.MUNISAMI  MALAYAMODU  CHURCH STREET  
     AGARAMCHERRY POST  MADANUR VIA  VELLORE 
     DISTRICT.
118  S.VIJIYA 
     W/O.DHAYANEETHI  ANNA NAGAR  KUDANAGARAM 
     VILLAGE & POST  GUDIYATHAM TALUK  VELLORE 
     DISTRICT.
119  S.CHITRA 
     W/O.MAGESAN  KEELMURUNGAI VILLAGE  
     VADAPUTHUPET POST  AMBEDKAR NAGAR  AMBUR  
     VELLORE DISTRICT.
120  A.BASHA 
     S/O.ANWAR  17/6  CHITTOR ROAD  MUNAB TIPPO  
     GUDIYATHAM TALUK  VELLORE DISTRICT.
121  G.MERRY 
     W/O.E.KUPPUSAMY  SOUTH COLONY  AGARAMCHERRY 
     POST  MADANUR VIA  VELLORE DISTRICT.
122  K.SAVITHRI 
     W/O.ANANTHAN  234  POOKAR STREET  
     BHRAMANGAMANGALAM VILLAGE  VETTUVANAM POST  
     PALLIKONDA  VELLORE DISTRICT.
123  A.S.SURIYAKALA 
     W/O.ARULMOZHI SAMUEL  73  KOTHAKUPPAM  
     MELALATHUR POST  GUDIYATHAM TALUK  VELLORE 
     DISTRICT.
124  G.LOGAMBIGAI 
     D/O.GANESH UDAYAR  ARUMBAKKAM  MOOTUR 
     VILLAGE  THONDA THOLASI POST  LATHERI  
     KATPADI TALUK  VELLORE DISTRICT.
125  D.MUNUSAMY 
     S/O.DURAISAMI  KOTHAMPAKKAM VILLAGE  
     VADAKATHIPETTI POST  MADANUR VIA  VELLORE 
     DISTRICT.
126  J.RAMESH 
     S/O.JOSEPH  KOTHAMPAKKAM VILLAGE  
     VADAKATHIPETTI POST  MADANUR VIA  VELLORE 
     DISTRICT.
127  R.GUNASELVI 
     W/O.THIRUGANAM  MC COLONY  MADANUR  VELLORE 
     DISTRICT.
128  K.PENNARASI 
     W/O.SATHIK  DEVICHETTIKUPPAM POST  
     THEEPABATH VILLAGE  GURUVARAJAPALAYAM VIA  
     VELLORE DISTRICT.
129  C.E.MOHAMED ISMAIL 
     S/O.MOHAMED IBRAHIM  7/63  KAMARAJ NAGAR  
     PALLIKONDA.
130  K.RANI 
     D/O.KRISHNASAMI  OLD POLICE STATION STREET  
     LATHERI VILLAGE AND POST  KATPADI TALUK  
     VELLORE DISTRICT.
131  C.N.THAYUB 
     S/O.ABDUL MAJITH  45  KANAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
132  M.AMMU 
     W/O.MANOHARAN  PUDUMANAI  AGARAMCHERRY POST  
     MADANUR VIA  AMBUR TALUK  VELLORE DISTRICT.
133  D.RAJA 
     S/O.DURAISAMI  AYYAYU NAGAR  PALLIKONDA  
     VELLORE DISTRICT.
134  Z.M.IBRAHIM 
     S/O.ZAKKRIAH SAHIB  22/45  HRA STREET  NEW 
     MEHILLAH  PALLIKONDA  VELLORE DISTRICT.
135  M.MUMTHAJ 
     D/O.YAKUB  NO.60  KANAR STREET  NEW MEHILLAH 
     PALLIKONDA  VELLORE DISTRICT.
136  D.SARALA 
     W/O.BABU  MARIYAMMAN KOIL STREET  MC ROAD  
     AGARAMCHERRY VILLAGE AND POST  VELLORE 
     DISTRICT.
137  H.ALEEM BASHA 
     S/O.MOHAMED ANIF  3  HAR STREET  NEW 
     MEHILLAH  PALLIKONDA  VELLORE DISTRICT.
138  J.LATHA 
     W/O.MURALI  57  THIPPASAMUDRAM VILLAGE & 
     POST  PALLIKONDA  VELLORE DISTRICT.
139  M.KANAGAMBAL 
     D/O.MANICKAM  75  KATTUPUDI VILLAGE  
     VETTUVANAM POST  PALLIKONDA  VELLORE 
     DISTRICT.
140  R.KALAIARASI 
     W/O.RAJIDRAN  NO.121  MARIYAMMAN KOIL STREET 
      AGARAMCHERRY VILLAGE AND POST  MADANUR VIA  
     VELLORE DISTRICT.
141  S.DOULATHKHAN 
     S/O.SARTHAR KHAN  55  NEW KANAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
142  K.MALLIGA 
     W/O.KUPPUSAMI  MARIYAMMAN KOIL STREET  
     AGARAMCHERRY VILLAGE AND POST  MADANUR VIA  
     VELLORE DISTRICT.
143  G.JAMUNA 
     W/O.EKAMBARAM  37/7  KOTHAVAL STREET  
     KEELACHUR VILLAGE  PALLIKONDA  VELLORE 
     DISTRICT.
144  S.SHAKIRA 
     W/O.YUNUS  MAJITH STREET  AGARAMCHERRY 
     VILLAGE AND POST   VELLORE DISTRICT.
145  N.FARHANAN 
     S/O.S.DOULATHKHAN  55  NEW KANAR STREET  
     PALLIKONDA  VELLORE DISTRICT.
146  K.SIVAGAMI 
     W/O.VELU  KANNAMANGALAM POST  20/24  KAVARAI 
     STREET  ARNI POST.
147  C.LILLY 
     W/O.ASHOK  PUDUMANAI ASHOK NAGAR  
     AGARAMCHERRY VILLAGE AND POST  MADANUR VIA  
     VELLORE DISTRICT.
148  M.SAKTHIVEL 
     S/O.MURUGESAN  28  RAIL ROAD  VETTUVANAM 
     VILLAGE AND POST  PALLIKONDA  VELLORE 
     DISTRICT.
149  M.SIVAGAMI 
     D/O.MANOHARAN  KOTHAMPAKKAM VILLAGE  
     VADAKATHIPATI  MADHANUR VIA  AMBUR TALUK  
     VELLORE DISTRICT.
150  M.KARUNANEETHI 
     S/O.MUNISAMY  KOLLAMANGALAM VILLAGE & POST  
     AMBUR TALUK  VELLORE DISTRICT.
151  R.AKILA BANU 
     W/O.MOHAMED IMRAN  INDRA NAGAR  SETHUVALAI  
     VELLORE DISTRICT.
152  V.MUNISAMY 
     S/O.K.VENKATESAN  CHINNAMALAIYAMPET  
     KARAPATTU  VANIYAMBADI TK.  VELLORE DISTRICT.
153  R.INDRANI 
     W/O.GOVINDASAMY  RAGAVENDRA STREET  LENIN 
     NAGAR  KODASAMUDRAM  GUDIYATHAM  VELLORE 
     DISTRICT.
                                                             .. RESPONDENTS
     
Prayer:  This Writ Petition is filed under Article 226 of the Constitution of India, praying for the issuance of Writ of Certiorari, to call for the records pertaining to the Order dated 22.05.2012 passed in the unnumbered I.A. of 2012 in C.P.230 of 2011 by the 1st Respondent  Presiding Officer  Principal Labour Court  Vellore and quash the same.
         
	 For Petitioners in both W.Ps. : Mr.Gupta for
                                                   M/s.Gupta and Ravi

          For Respondents in both WPs: Mr.V.Prakash, SC for
                                                   Mr.E.Srinivasan

COMMON ORDER

The petitioner is a company engaged in the manufacture of shoes, meant for export. There were as many as 482 workers engaged in the company and due to certain constraints, the said company suspended its operation from 12.11.2004 and thereafter, it was suspended its operation with effect from 12.11.2004. The Floram Shoes Employees Union, which is a recognized one, took up the matter before the Joint Commissioner of Labour, Chennai. During the pendency of the same, bilateral talks were held with the said Union representing all 482 workmen. In the meanwhile, two other unions, namely, Leather & Leather Goods Democratic Labour Union (affiliated to AICCTU) and Desiya Podu Thozhilalar Sangam (affiliated to INTUC) raised a dispute under Section 2K of the Industrial Disputes Act, 1947 (hereinafter, referred to the Act ) before the Joint Commissioner of Labour on the issue of closure. In the meantime, a settlement between the petitioner Management and the Floram Shoes Employees Union was entered on 2.3.2005 under Section 18(1) of the Act, in and by which, as many as 472 workers who were the members of the said Union got the benefit and out of them, about 164 workmen were reengaged on restructured wages in the petitioner company in terms of the settlement while the remaining 318 workers accepted the compensation in lieu of agreeing cessation of employment with effect from 12.11.2004. However, the disputes raised by the other Unions came to be dismissed on 27.8.2008 for non-prosecution since the said Unions had not participated in the proceedings. The remaining 173 workers, who accepted the terms of settlement, however, disputing the closure of the petitioner company on and from 10.11.2004 as illegal, since the petitioner management without obtaining any permission from the Government of Tamil Nadu as provided under Section 25-O of the Act and it was not a lock-out as contended by the petitioner management, filed computation petitions in CP NOs.164 of 2005, etc., before the Addl.Labour Court, Vellore, claiming wages and other benefits from the date of alleged closure, i.e.10.11.2004.

2. While analysing the evidence available before it coupled with the facts and contentions raised, the Labour Court framed the issues for consideration, viz.,, Whether it was a lock-out (suspension of operation) as contended by the petitioner management or closure as contended by the workers and whether the termination of the workers amounts to illegal retrenchment and in violation of Section 33(2)(b) of the Act?

3. The Labour Court, having considered the rival contentions in the light of the evidence, has held that it was an illegal closure and not lockout as contended by the petitioner management and as such, the petitioner company has not followed the mandatory provisions as laid down in the Act and thereby, the so-called settlement though accepted by the majority of the workmen, cannot bind on the workers and hence, the termination of the workers amounts to illegal retrenchment and contrary to Section 25(o), 25(N) and 33(i)(b) of the Act and thereby, the workers are entitled to invoke Section 33(C)(2) of the Act to compute the benefits and claim wages and consequential benefits from the date of alleged closure. While holding so, the Labour Court has allowed all the computation petitions filed by the workers and directed the petitioner company to pay monetary value as prayed for by them, after deducting the money if any paid to them.

4. Questioning the above, the petitioner management has come forward with a writ petition in W.P.No.16285 of 2011.

5. While so, the workers who filed CP Nos.164 of 2005 and got the favourable order, has also subsequently filed another computation petition in CP No.230 of 2011 before the Labour Court, claiming wages for the subsequent period, i.e. from 01.04.2005 to 31.7.2011 based on the same contentions raised in the earlier writ petition mentioned above. Pending disposal of the said CP No.230 of 2011, the petitioner management filed an interlocutory application (unnumbered), invoking Section 11 of the Act, questioning the maintainability of the said CP and prayed the Labour Court to decide the same as preliminary issue.

6. According to the petitioner management, already in earlier Computation Petitions, the Labour Court erroneously passed the award and it has been under challenge in W.P.No.21656 of 2011 and when the matter is seized of by this Court and until the same is decided by this Court, it cannot be considered that the orders passed in CP No.164 of 2005 has attained finality and thereby, the workers can maintain similar computation petition for the subsequent period. Hence, the petitioner management prayed the Labour Court, to decide the maintainability of the said CP as preliminary issue. By order, dated 22.5.2012, the Labour Court, rejected the said interlocutory application with costs of Rs.3000/-, holding that the said application filed by the petitioner management is not maintainable since in earlier CP No.164 of 2005, etc., it had already decided the issue that the retrenchment was in violation of Section 25(N) of the Act while rejecting the version of the petitioner management lockout and it was a closure, for which, no prior permission of the government as required under Section 25(O) of the Act was obtained and passed the award, again forwarding with the interlocutory application questioning the maintainability of the Computation Petition by the petitioner management would clearly amount to abuse of process of Court with mala fide intention to cause delay and harass the workmen. Questioning the said order of the Labour Court, the petitioner management has come forward with the present writ petition in WP No.16285 of 2012.

7. A counter affidavit has been filed by the respondents/workers in W.P.No.21656, inter alia, stating that the petitioner management illegal closed the factory w.e.f.10.11.2004 and before such closure, no notice as contemplated under Section 25(o) of the Act was issued and since the closure is illegal, the workers are deemed to be in service and they are entitled to get wages under Section 25(o)(6) of the Act. The Union had raised a dispute on 12.11.2004 alleging that the petitioner management had illegally locked out the factory in the name of suspension of operation w.e.f.12.11.2004. However, the said Union colluded with the petitioner management and raised the dispute with mala fide intention to save the management from the illegal closure. Though the petitioner management entered into a settlement with the Union, the respondents/workers had not authorized the Union to terminate their service nor accepted the settlement and therefore, it amounts to illegal retrenchment. Before terminating all the workers, the petitioner management did not issue notice and got permission from the Government as contemplated under Section 25(N) of the Act. The management witness RW.1 in cross examination, has stated that the settlement was not concluded in accordance with the provisions of the Act or standing orders. The petitioner management sent cheques to the workers by post towards compensation in lieu of employment the same were refused by the workers, however, due to sudden non-employment, as the workers were suffering in economical crisis, the workers were forced to receive the cheques. After closure of the factory, the petitioner newly opened the factory in the year 2005 and engaged new workers and re-engaged some of the old workers without continuity of service and with new service conditions. Invoking Section 33(C)(2) of the Act, the workers filed computation petitions before the Labour Court, which were rightly dealt with the Labour Court in a perspective manner and passed the award, which requires no interference, but confirmation. Therefore, the workers sought for dismissal of the writ petitions.

8. Since the subject matter of the writ petitions as well as the issue involved therein, is one and the same, both of these writ petitions are taken up together and disposed of by this common order.

9. Challenging the award passed by the Labour Court, Mr.Gupta, learned counsel appearing for the petitioner management would contend that it is not fair on the part of the respondents workmen in questioning the suspension of operation under the guise of closure and claiming the wages for their non-employment once having accepted and derived the benefits of the Settlement entered between the Union and the petitioner management on 2.3.2005 and despite bringing the existence of the said settlement to its knowledge, the first respondent Labour Court, has erroneously passed the award. He relied upon a decision reported in Tata Engineering and Locomotive Co.Ltd. versus Workmen reported in (1981) 4 SCC 627, wherein, the Honble Supreme Court, has held that the settlement, accepted by majority of the workmen, must be presumed to be fair and just. In para 10, it has been held as under:

If the Settlement had been arrived at by a vast majority of the concerned workers with their eyes open and was also accepted by them in its totality, it must be presumed to be just and fair and not liable to be ignored while deciding the reference merely because a small number of workers (in this case 71 i.e. 11.18 per cent) were not parties to it or refused to accept it, or because the Tribunal was of the opinion that the workers deserved marginally higher emoluments than they themselves thought they did. A settlement cannot be weighed in any golden scales and the question whether it is just and fair has to be answered on the basis of principles different from those which come into play when an industrial dispute is under adjudication. In this connection we cannot do better than quote extensively from Herbertsons Ltd. v. Workmen1 wherein Goswami, J., speaking for the Court observed: (SCC pp. 743-45, paras 21, 24-25 and 27) Besides, the settlement has to be considered in the light of the conditions that were in force at the time of the reference. It will not be correct to judge the settlement merely in the light of the award which was pending appeal before this Court. So far as the parties are concerned there will always be uncertainty with regard to the result of the litigation in a court proceeding. When, therefore, negotiations take place which have to be encouraged, particularly between labour and employer, in the interest of general peace and well being there is always give and take. Having regard to the nature of the dispute, which was raised as far back as 1968, the very fact of the existence of a litigation with regard to the same matter which was bound to take some time must have influenced both the parties to come to some settlement. The settlement has to be taken as a package deal and when labour has gained in the matter of wages and if there is some reduction in the matter of dearness allowance so far as the award is concerned, it cannot be said that the settlement as a whole is unfair and unjust.

10. He would also contend that when a recognized Union, representing the workers, negotiates with the employer and entered into settlement, which is collective bargaining, and having accepted same and having gained thereof, the claims made by the workers in individual capacity contrary to the terms of the settlement, cannot be maintained. In this regard, he relied upon a decision reported in Herbertsons Ltd. & Others versus Workmen reported in (1976) 4 SCC 736, wherein, the Honble Supreme Court has held as underin para 18:

18. When a recognised union negotiates with an employer the workers as individuals do not come into the picture. It is not necessary that each individual worker should know the implications of the settlement since a recognised union, which is expected to protect the legitimate interests of labour, enters into a settlement in the best interests of labour. This would be the normal rule. ...

11. The learned counsel would contend that in order to maintain a claim petition under Section 33(c)(2) of the Act, there should be a pre-existing right in favour of the employee against the employer and admittedly, in the case on hand, admittedly, there was no adjudication in respect of the disputed questions of facts inasmuch as the dispute raised by two unrecognized unions regarding the illegal closure of the factory, was subsequently ended in non-prosecution and hence, without there being any pre-existing right, the workers cannot maintain the claim petitions. He relied upon a decision of a Division Bench of this Court, reported in The Management of M/s.R.S.L. BTannery, Vellore versus the Presiding Officer, Vellore & Others reported in CDJ 2012 MHC 4495, wherein, having following the various rulings of the Honble Supreme Court, viz., AIR 1974 SC 1604, 1995 I LLJ 395, 2001 (1) LLN 58 and 2009(1) LLN 340, it has been held as under in para 25 and 26:

25. At this juncture, we deem it appropriate to pertinently point out that Section 33C of the Industrial Disputes Act, 1947 provides not only a form but also a procedure in regard to the computation of monetary, as well as non-monetary benefits in terms of money. Also, it speaks of a machinery for effecting the recovery of such claims. As such, the workmen can claim not only a benefit which could be computed in terms of money, but also any monetary sum due from their employer, like arrears of wages, salary or other allowances which were withheld. Persons falling within the definition of Section 2(s) 'Workman' of the Industrial Disputes Act, 1947 viz., workmen are entitled to maintain an application under Section 33C (2) of the I.D. Act read with necessary rules.
26. However, in Section 33C (2) proceedings of the Industrial Disputes Act, if the rights of workmen were denied by an employer, the same would not oust the jurisdiction of the Labour Court, in our considered opinion. In this connection, it is to be noted that if the foundation of the claim is in serious doubt and the matter is hotly contested between the parties, then, the core issue will have to be determined in an elaborate fashion and admittedly, when the main dispute is pending with the Industrial Tribunal, the 1st Respondent/ Labour Court, in our opinion, is not competent to decide the matter even incidentally as regards the computation of benefits. To put it precisely, a pre-existing right or benefit will squarely attract the jurisdiction of the Labour Court exercising its powers as per Section 33C (2) of the Industrial Disputes Act.

12. The learned counsel also contended that there was no closure of the factory, but it was declared only suspension of operation with effect from 12.11.2004 due to certain constraints and as such, notice as contemplated under Sections 25 N and 25(O) does not arise and that the petitioner management never resorted to any retrenchment of the workers at any point of time and therefore, the respondents workers have no legal right either to raise the dispute under Section 2A or to file any claim petition under Section 33(C)(2) of the Act and the findings of the Labour Court on these issues, are perverse and liable to be set aside.

13. On the other hand, Mr.V.Prakash, learned senior counsel appearing for the workers would contend that the petitioner management closed the factory on 10.11.2004, which was proved as illegal closure by evidence since the witnesses examined on behalf of the petitioner management have not specifically denied the same and that the contention of the petitioner management that there was no closure, but suspension of operation w.e.f.12.10.2004 cannot be accepted since the suspension of lockout could be imposed only while the factory is operation, whereas, it is admitted fact that the factory was not in operation on 12.10.2004 and even if it is a lockout, the petitioner management ought to have re-inducted the workers with same service conditions when the lockout is lifted, but it is was not done when the factory was reopened on 2.5.2005. He also contended that in the case of closure, there would be cession of employee and employer relationship while during the lockout period, the employee and employer relationship would continue and therefore, since the relationship of the workers and the management is continued and as it has been proved that there was illegal closure of the factory since no notice as contemplated under Section 25(O) or 25(N) of the Act was issued nor any permission from the Government and therefore, when once the illegal closure of the factory was established, the workmen are entitled to get benefits under Section 25(O(6) of the Act. He would also contend that the petitioner management entered into 18(1) Settlement with the trade union and terminated the service of all 482 workmen in the name of cession of employment which would not fall within the categories mentioned in Section 2(oo) of the Act and therefore, it would amount to illegal retrenchment and the non-compliance of Section 25(N) would render the termination of the workers void, illegal and inoperative. As regards the industrial dispute in I.D.No.37 of 2007 is concerned, the learned counsel would contend that the above said ID was raised by two other unions to which, the respondent workers were not the members and hence, the award passed therein, is no way connected to them. The learned counsel would contend that having issued notice, the respondent workers filed computation petitions under Chapter V-B of the Act, which were dealt with by the Labour Court in a proper perspective and passed the award, which requires no interference. He has further contended that already, earlier computation petitions were dealt with and passed award, the subsequent petitions in CP Nos.230 of 2011 filed by the respondent workers were maintainable as rightly held by the Labour Court while dismissing the interlocutory application filed by the petitioner management, is in perfectly in order and no interference is required and hence, he sought for dismissal of both the writ petitions.

14. In support of his contentions, learned senior counsel relied upon the following decisions, viz.,

i) Management of Express Newspapers (P) Ltd. versus The Workers and others reported in AIR 1963 SC 569, wherein, it has been held as under in para 14.

14. ... In fact, Industrial Tribunals have been specially established in order to deal with industrial disputes in different places. That is one consideration which is relevant. The other consideration which is equally material is that a question of this complicated character cannot be satisfactorily dealt with merely on affidavits. The theoretical distinction between a closure and a lockout is well settled. In the case of a closure, the employer does not merely close down the place of business, but he closes the business itself; and so, the closure indicates the final and irrevocable termination of the business itself. Lockout, on the other hand, indicates the closure of the place of business and not the closure of business itself. Experience of Industrial Tribunals shows that the lockout is often used by the employer as a weapon in his armoury to compel the employees to accept his proposals just as a strike is a weapon in the armoury of the employees to compel the employer to accept their demands. Though the distinction between the two concepts is thus clear in theory, in actual practice it is not always easy to decide whether the act of closure really amounts to a closure properly so called, or whether it is a disguise for a lockout. In dealing with this question, industrial adjudication has to take into account several relevant facts and these facts may be proved before the Industrial Tribunal either by oral evidence, or by documentary evidence and by evidence of conduct and circumstances. Whenever a serious dispute arises between an employer and his employees in regard to a closure which the employees allege is a lockout, the enquiry which follows is likely to be long and elaborate and the ultimate decision has always to depend on a careful examination of the whole of the relevant evidence.

ii) General Labour Union (Red Flag) Bombay versus B.V.Chavan and others reported in (1985) 1 SCC 312, wherein, it has been held by the Supreme Court as under:

11. While examining whether the employer has imposed a lockout or has closed the industrial establishment, it is not necessary to approach the matter from this angle that the closure has to be irrevocable, final and permanent and that lockout is necessarily temporary or for a period. The employer may close down industrial activity bona fide on such eventualities as suffering continuous loss, no possibility of revival of business or inability for various other reasons to continue the industrial activity. There may be a closure for any of these reasons though these reasons are not exhaustive but are merely illustrative. To say that the closure must always be permanent and irrevocable is to ignore the causes which may have necessitated closure. Change of circumstances may encourage an employer to revive the industrial activity which was really intended to be closed.....
iii) Clifton Electronics and Lt.Governor & Others reported in 1996-II LLJ-1110, wherein, the High Court of Delhi, has held as under:
Where the statutory requirement is making an application 90 days before the date of closure, in the instant case the closure was effect on March 31, 1993 while the application was dated April 26,1993, the closure is illegal. Section 25-O provides that workmen shall be entitled to all benefits under any law for the time being in force as if the undertaking had not been closed down. This apart of the sub-clause confers a right to the benefits. Benefits obviously include wages. If that be so, there is no need for any adjudication of the right to wages. What merely remained was the quantification of the amount for which Section 33-C(1) is applicable.
iv) Management of Chemech Engineers (P) Ltd. Chennai versus Presiding Officer, Principal Labour Court, Chennai reported in 2012-LL-181, wherein, the a learned single Judge has held as under:
Computation by Labour Court of benefits claimed by workmen upon closure of company was held valid and proper, as the factory engaging more than 100 workers was covered by chapter V-B of Industrial Disputes Act and approval for closure was not obtained by employer.
v) Dhanalakshmi Mills Ltd. versus Presiding Officer, Labour Court, Coimbatore reported in 2012-1-LLJ-673, wherein, a learned single Judge of this Court has held as under:
If the claim for wages due made in application under Section 33-C(2) of the I.D.Act, was under Chapter V-A of the Act, jurisdiction of Court was not ousted merely because employer disputed the retrenchment.
vi) Management of Sundram Fasteners Ltd. versus the Presiding Officer, Labouir Court, Salem reported in 2012-3-LLN-358, wherein, a learned single Judge of this Court has held as under:
It is clearly pleaded that it is a factory covered by Chapter V-B of the Industrial Disputes Act and inasmuch as a prior approval under Section 25-N of the Industrial Disputes Act was not obtained, it is a clear case of illegal retrenchment and the workers are entitled to be continued in service.
vii) Oswal Agro Furane Ltd., and another versus Oswal Agro Furane Workers Union & others reported in (2005) 3 SCC 224, wherein, the Honble Supreme Court has held as under:
Prior permission constitutes a condition precedent for retrenchment and/or closure and is mandatory. Need for such permission is not obviated by settlement between employer and workmen under Section 18 r/w S.2(p) of the Act. Tough a settlement within meaning of Section 18(3) r/w S.2(p) undoubtedly binds the workmen but this wouild not mean that thereby provisions contained in Ss.25-O and 25-N are not required to be complied with. An agreement which opposes public policy as laid down in Ss.25-O and 25-N would be void and of no effect, having regard to maxim ex turpi causa non oritur actio.
viii) Sri Arunachaleswarar Mills versus Joint Secretary, Department of Industries and Labour, Chennai and others, reported in 2010-II-LLJ-783 (Mad), wherein, a learned single Judge of this Court, has held that as per Section 25-O of the Act, closure of undertaking without prior permission was not binding on the workmen and that the settlement relied on by the management could not be upheld as it was contrary to statutory provisions and did not satisfy the tests of public policy under Section 23 of the Indian Contract Act and therefore, the workmen are entitled to benefits under Section 25-O(6) and recovery certificate under Section 33-C(1) of the Act.

15. Heard the learned counsel appearing for the petitioner management and the learned senior counsel appearing for the workmen.

16. The case of the petitioner is that due to adverse market volatile during the period 2002-2003, the order position rapidly declined progressively over a period of time, the petitioner management was not in a position to meet out the expenditure towards payment of wages to the workers who were kept idle, it was constrained for the petitioner management to suspend its manufacturing operations and accordingly, on 12.11.2004, a notice to this effect was put up on the notice board, which reads as under:

It is a fact that this unit cannot be operated without the assistance of other companies. At the same time, when the order book position has come down, the possibility of other companies coming to the rescue of Floram has become remote. In the above circumstances, the company cannot run every month with borrowings. Hence with deep regret all the employees are informed that the operation of Floram is suspended from 12.11.2004 onwards. It is brought to the notice of the employees that on the basis of no work no pay, there will not be any payment or compensation during the period of suspension of operation. We wish to bring to your notice that the suspension of operations is brought about due to reasons beyond the control of the management.

17. Aggrieved over the same, the Floram Shoes Employees Union, a recognized union, raised a dispute in conciliation before the Joint Commissioner of Labour, Chennai, who in turn, suggested the parties to resolve the dispute by negotiating themselves. While so, two other unions, viz., Leather and Leather Goods Democratic Union (affiliated to AICCTU) and Desiya Podu Thozhilalar Sangam (affiliated to INTUC) raised a dispute under Section 2K of the Act before the Joint Commissioner of Labour on the issue of closure. This was resisted by the petitioner management and questioned the maintainability of the dispute on the ground that the said two unions were not recognized. However, in the mean time, on 2.3.2005, the petitioner management entered into a settlement under Section 18(1) of the Act, with the recognized union, i.e. Floram Shoes employees Union, wherein, the respondents workers are the members. The relevant terms of the settlement are that, all workmen shall accept cessation of employment with effect from 12.11.2004, the factory would likely to be reopened on 25.2005 and if necessary arises, workers would be re-engaged on restructured wages and other monetary benefits, such as, gratuity, etc. In fact, by virtue of settlement, options were given to the workers, either to accept cessation of employment with effect from 12.11.2004 and receive monetary compensation in lieu thereof in full quit or to continue employment on restructured wages. Pursuant to the said settlement, the Union agreed not to press the issues raised before the Joint Commissioner of Labour and not to claim any other benefits for the period from 12.11.2004 when the suspension of operations was declared till the date of signing of the settlement. Out of total 482 workers of the Union, as many as 472 workers got the benefit and out of them, about 164 workmen were reengaged on restructured wages in the petitioner company in terms of the settlement while the remaining 318 workers accepted the compensation in lieu of agreeing cessation of employment with effect from 12.11.2004.

18. The dispute over the closure, raised by the Leather and Leather Goods Democratic Labour Union and INTUC was referred to adjudication by the Government of Tamil Nadu vide G.O.D.No.219 dated 14.3.2007 to the Industrial Tribunal, Chennai, which was taken on file as I.D.No.37 of 2007, which was subsequently dismissed for non-prosecution since the above said Unions had not participated in the proceedings.

19. While so, some of the workers (respondent-workers herein), who, in fact, accepted the terms of settlement dated 2.3.2005 have approached the Labour Court by way of computation petitions in C.P.Nos.164 of 2005, etc., alleging the closure of the petitioner company on and from 10.11.2004 as illegal, since the petitioner management without obtaining any permission from the Government of Tamil Nadu as provided under Section 25-N of the Act and it was not a lock-out as contended by the petitioner management, and claimed wages and other benefits from the date of alleged closure, i.e.10.11.2004. By order, dated 28.7.2011, the Labour Court has passed the award, which is impugned in the writ petition.

20. The main contention of the petitioner management is that they never resorted to any closure, but due to certain constraints as the management was not a position to run the factory, declared suspension of operation w.e.f. 12.11.2004 and it would not amount to closure.

21. Section 2(cc) of the Act defines Closure, meaning, the permanent closing down of a place of employment or part thereof.

22. Section 2(l) of the Act defines lock-out, means the temporary closing of a place of employment or the suspension of work, or the refusal by an employer to continue to employ any number of persons employed by him.

23. A reading of the above, it is clear that lock-out means a temporary suspension of work, whereas, closure means, permanent closing down of the place of employment. It is not in dispute that the petitioner management had issued notice of lock-out, on 12.11.2004 declaring the suspension of manufacturing operations and questioning the same, the recognized Floram Shoes Employees Union raised a dispute in conciliation before the Joint Commissioner of Labour, Chennai. It is also pertinent to note that two other unions, viz., Leather and Leather Goods Democratic Labour Union and INTUC have also raised dispute under Section 2(k) of the Act. While pending the same, the petitioner management and the recognized Union had entered into Settlement under Section 18(1) of the Act on 2.3.2005. Consequent to the same, the dispute raised by the recognized union came to be withdrawn, while the disputes raised by two other unions came to be dismissed for non-prosecution. As on the date of filing of the computation petitions by the respondent/workers, already there was a settlement and no individual worker has questioned or raised the dispute regarding the validity of the settlement and further, there was no award or finding that the workmen are entitled to receive from the petitioner management any money or benefit which is capable of being computed in terms of money to enable the workmen to invoke Section 33(C)(2) of the Act.

24. The Labour Court is of the view that since the mandatory requirements under Sections 25-N and 25-O of the Act were not complied with by the petitioner management while resorting to suspension of operation, it cannot be construed as lockout, but it is a closure and there was illegal retrenchment of the respondent/workers.

25. The theoretical distinction between a closure and a lockout is well settled. In the case of a closure, the employer does not merely close down the place of business, but he opposes the business itself; and so, the closure indicates the final and irrevocable termination of the business itself. Lockout, on the other hand, indicates the closure of the place of business and not the closure of business itself. It is to be noted that closure is a matter of policy of the employer, whether to run his business or not. The employer may close down an industrial activity bona fide on such eventualities as suffering continuous loss, no possibility of a revival of the business or an inability for various other reasons. The word closure means, perpetual, i.e. business can under no circumstances be revived till eternity.

26. In the present case, the petitioner management declared suspension of operation on 12.11.2004 and admittedly, the petitioner management has not resorted to termination of its employees. However, even presuming that there was a closure as contended by the respondent/workers, it is relevant to determine whether such closure was a device or a pretence to terminate the services of the workmen or whether it is bona fide and far beyond the control of the employer, has to be decided on the evidence produced before the Court. On a perusal of the entire material and evidence as well as the award passed by the Labour Court, this Court finds that the Labour Court has not given any cogent reasons that the alleged closure resorted to by the petitioner management is not bona fide and tainted with mala fide intention to terminate the services of the workmen and the respondent/workers have not alleged that the so-called closure is not genuine one and merely alleging that the closure is illegal without assigning any reasons, it cannot be construed that it is illegal closure when the employer has proved that the suspension of operation was for bona fide reasons. On overall consideration of the facts and evidence available on record, this Court could analyse that in order to wriggle out the financial constraints and adverse market conditions which were prevailing during the material period due to which, the petitioner management was not in a position to continue the business operation, has genuinely resorted to suspension of operation and a notice to that effect was put on board on 12.11.2004. Therefore, this Court is of the considered view that the petitioner Management has resorted to only suspension of operation and not closure as contended by the learned counsel for the respondent/workmen. The decision relied upon by the learned counsel for the respondents/workmen in Sri Arunachaleswarar Mills (cited supra), cannot be made applicable to the facts of the present case in view of the fact that in the present case, the petitioner management has only resorted to suspension of operation and not closure, whereas, the above said decision deals with the closure and since the management therein had resorted to closure without prior permission, this Court held that the same was not binding on the workmen and the settlement relied on by the management could not be upheld as it was contrary to the statutory provisions. It is well settled law that the closure or stoppage of the whole or part of the business is the function of the management which is entirely in the discretion of the employer carrying on the business. The industrial adjudication cannot interfere with the discretion exercised by the employer in such a matter and it has no power to direct the employer to continue the whole or part of the business which the employer has decided to shut down. However, it is no doubt true and settled that if the employer resorted to closure, it is mandatory on his part to comply with all the requirements as envisaged under the Act.

27. It may be true that the petitioner management has declared suspension of operation in order to negotiate with the respondent/workers and as expected by it, the Union, representing the workers has come forward to settle the disputes by entering into the settlement which was arrived at amicably on 2.3.2005. It is to be noted that if the settlement was not arrived at and the industrial dispute regarding the so-called closure was persuaded, the matter altogether would have been different and the consequences arose thereof, have to be borne by the petitioner management. It is reported that by way of settlement, the petitioner management has borne out more than Rs.3,12,30,000/- towards compensation of the claims of the workmen. It is not in dispute that the said settlement was accepted by majority, i.e. 479 workers out of 482 and thereby, it is held that the settlement is a valid one. It is settled law that the workmen, having received the amounts in full, quit all their claims, cannot question the same later and once an agreement under Section 18(1) was entered into which provided compensation in lieu of the claims of the workmen and the said agreement was acted upon, the parties to it, cannot turn round and say that it was not an agreement within the meaning the of provision of the Act and not binding on them. Therefore, once the agreement is acted upon, there was a performance of the terms and once it is so performed, even in part, would attract the principle of equitable estoppel.

28. In an establishment, wherein, more than 100 workmen are employed, falling within the meaning of the Act, it is mandatory on the part of the employer to get prior permission for laying off, retrenchment or closing down the establishment as contemplated under Sections 25-M, 25-N and 25-O of the Act and there is no need for the employee to raise an industrial dispute to claim wages or getting the said action of the employer bad in law by competent Court as contemplated by the Honble Apex Court in Jaipur Zila Sahakari Bhoomi Vikas Bank Limited versus Ram Gopal Sarma reported in (2002) 2 SCC 244. But if it does not fall under the above said sections, the remedy is only to raise an industrial dispute except in case wherein, industrial dispute is pending and the employer do not take prior approval or permission of his action. It is to be noted that none of the conditions applied to the facts of the present case. In this case, in order to bring it within the ambit of retrench and closure, the respondent/workers have converted the original dispute, namely, suspension of work into one of closure/retrenchment, which is condemnable. In this case, it is not in dispute that the recognized Union to which, the respondent/workers were the members, has ostensibly represented all the workers and finalized the settlement and having received the compensation by entering into settlement, the respondent/workers again came forward with the computation petitions, contending that there was illegal closure and that they were illegally terminated, which was erroneously allowed by the Labour Court, holding that the so-called settlement is not valid in the light of non-compliance of Sections 25-N and 25-O of the Act, which in fact, relate to illegal retrenchment and closure of the establishment and as already held by this Court, the petitioner management has resorted only lock-out and there was no retrenchment of the workers and therefore, the finding of the Labour Court that the settlement is not valid and not binding upon, cannot be sustained. If the award of the Labour Court impugned in the writ petition is implemented, it would be nothing but amount to double jeopardy and cause great prejudice to the petitioner management since the petitioner has to be bear more than Rs.5 Crores for implementation of the impugned award and in such event, there would be permanent closure of the establishment.

29. For the all the fore going reasons, this Court is of the considered view that the award dated 28.7.2011 impugned in the writ petition in W.P.No.21656 of 2011 cannot be sustained and it is liable to be set aside and accordingly set side.

30. In the light of the main award itself is set aside, consequently, the order, dated 22.5.2012 impugned in the writ petition in W.P.No.16285 of 2012 is also liable to be set aside and accordingly, it is set aside.

In the result, both the Writ Petitions are allowed as prayed for. No costs. Consequently, connected MPs are closed.

Suk                                                                       23-12-2014 
Index: Yes/No
Internet: Yes/No
S.VAIDYANATHAN, J.
 
Suk
 
 

 
 
 
 
 
 
 
PRE DELIVERY COMMON ORDER
IN W.P.NOS.21656 OF 2011 AND
W.P.NO.16285 OF 2012
 
 
 
 
 
 
 
 
 
23-12-2014