State of Jammu-Kashmir - Section

Section 57 in Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2013

57. Capital Cost.

(1)The normative capital cost for setting up Solar Photovoltaic Power Project shall be Rs.1000Lakh/MW for FY 2013-14. Provided that the Commission may deviate from above norm in case of project specific tariff determination in pursuance of Regulation 7 and Regulation 8.