Section 8 in Central Electricity Regulatory Commission (Fees and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019

8. Capital Expenditure (CAPEX) and Replacement Expenditure (REPEX) Plan.

(1)The RLDCs and NLDC shall formulate the scheme for Capital Expenditure (CAPEX) and Replacement Expenditure (REPEX) for the control period duly approved by the Board of Directors of Power System Operation Corporation Limited. The CAPEX and REPEX plan shall also include future costs to be incurred for the up-gradation, modernization, automation and expansion of infrastructure in addition to existing capital assets.
(2)The concerned RLDCs or NLDC as the case may be shall submit the following along with the petition for determination of fees and charges:
(i)the CAPEX for the control period along with details of estimated expenses, and estimated completion period of each scheme;
(ii)the REPEX plan for capital expenditure of existing asset, completion of life of existing asset, cumulative depreciation recovered, date of replacement, cumulative repayment of loan upto date of replacement, writing off of the gross value of the original assets from the original fixed assets along with estimated expenses and estimated completion period of each scheme.
(3)In relation to any consolidated schemes of CAPEX and REPEX involving one or more RLDCs and/or NLDC, the capital expenditure chargeable to each RLDC and NLDC shall be segregated and considered as a part of capital expenditure of RLDC concerned and NLDC, as the case may be .