Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 0]

Delhi High Court

M/S Ilfs Engineering And Construction ... vs M/S Indian Strategic Petroleum ... on 15 April, 2021

Equivalent citations: AIRONLINE 2021 DEL 534

Author: C. Hari Shankar

Bench: C. Hari Shankar

                          $~2
                          *     IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                Date of Decision: 15th April, 2021
                          +     ARB.P. 578/2020
                                M/S ILFS ENGINEERING AND CONSTRUCTION
                                COMPANY LIMITED                             ..... Petitioner
                                               Through: Mr. Hrishikesh Baruah, Ms.
                                               Aditi Mittal, Mr. Aditya Narayan Mahajan,
                                               Mr. Siddhant Tripathi and Mr. Jatin Kumar,
                                               Advs.

                                                     versus

                                M/S INDIAN STRATEGIC PETROLEUM RESERVES
                                LIMITED                                   ..... Respondent
                                              Through: Mr. Dinesh Pardasani, Adv.
                                              with Ms. Shania Elias, Advs.

                                CORAM:
                                HON'BLE MR. JUSTICE C. HARI SHANKAR

                          %                  J U D G M E N T (ORAL)
                                               (Video-Conferencing)


                          1.    By this petition under Section 11 (6) of the Arbitration and
                          Conciliation Act, 1996 ("the 1996 Act"), the petitioner seeks reference
                          of its dispute with the respondent to arbitration.


                          2.    The issue in controversy being limited, equally limited need be
                          the reference to the factual fasciculus in which the dispute arises.


                          3.    By contract dated 9th September, 2014, respondent entrusted, to
                          the petitioner, the work of laying of a pipeline from Land Fall Point
                          (LFP) to Mangalore/Padur Cavern for the Strategic Storage of Crude
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 1 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           Oil at Padur. The contract contained General and Special Conditions,
                          i.e. the GCC and the SCC, respectively.


                          4.    Vide letter dated 9th February, 2018, the petitioner raised claims
                          for compensation towards cost escalation borne by it in performing of
                          the contracted work. The claims were rejected by the respondent vide
                          letter dated 16th February, 2018. The petitioner rejoined vide letter
                          dated 3rd April, 2018.


                          5.    At this juncture, it would be appropriate to reproduce Clauses
                          1.0.34.0, 6.2.5.0, 6.3.3.0, 6.6.0.0, 6.6.1.0, 6.6.2.0, 6.6.3.0, 6.6.3.1 and
                          9.1.0.0 of the GCC, governing the contract between the parties, thus:
                                "1.0.34.0 "Notified Claim" shall mean a claim of the
                                CONTRACTOR notified in accordance with the provisions of
                                Clause 6.6.1.0."

                                                            *****

                                6.2.5.0 Payments of the amount(s) due on the Final Bill to
                                the extent certified by the Engineer-in-Charge, shall be made
                                within 84 (Eighty Four) days from the due date as specified in
                                Clause 6.2.4.0 hereof, subject to the deductions provided in
                                Clause 6.2.5.1.

                                                            *****

                                6.3.3.0 The rates stated in the Price Schedule and the lump
                                sum price(s) shall not be subject to escalation or increase for
                                any reason whatsoever."

                                                            *****

                                6.6.0.0 CLAIMS BY THE CONTRACTOR

                                       6.6.1.0 Should the CONTRACTOR consider that he is
                                       entitled to any extra payment or compensation in
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 2 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                       respect of the works or supplies over and above the
                                      amounts due in terms of the Contract as specified in
                                      Clause 6.3.1.0 hereof, the CONTRACTOR shall give
                                      notice in writing of its claim in this behalf to the
                                      Engineer-in-Charge and the OWNER within 14
                                      (Fourteen) days from the date of the issue of orders or
                                      instructions relative to any work(s) for which the
                                      CONTRACTOR claims such additional payment or
                                      compensation, or from the date of the happening of any
                                      other event upon which the CONTRACTOR bases
                                      such claim, as the case may be. Such notice shall give
                                      full particulars of the nature of such claim, grounds on
                                      which it is based, and the amount claimed. The
                                      OWNER shall not anywise [sic] be liable in respect of
                                      any claim by the CONTRACTOR unless notice of
                                      such claim shall have been given by the
                                      CONTRACTOR to the Engineer-in-Charge and the
                                      OWNER in the manner and within the time aforesaid,
                                      and the CONTRACTOR hereby waives and
                                      relinquishes any and all claims and all his rights in
                                      respect of any claim which is not notified by the
                                      CONTRACTOR to the Engineer-in-Charge and the
                                      OWNER in writing in the manner and within the time
                                      aforesaid.


                                      6.6.2.0 The Engineer-in-Charge and/or the OWNER
                                      shall be under no obligation to reply to any notice of
                                      claim given or claim made by the CONTRACTOR
                                      within the provisions aforesaid or otherwise, or to
                                      otherwise reject the same, and no omission or failure
                                      on the part of the Engineer-in-Charge or the OWNER
                                      to reject any claim made or notified by the
                                      CONTRACTOR nor any consideration thereof or
                                      dealing therewith shall be deemed to be an admission
                                      by the OWNER of the validity of such claim or waiver
                                      by the OWNER of the provisions of Clause 6.6.1.0
                                      hereof.

                                      6.6.3.0 Any or all claims of the CONTRACTOR
                                      notified in accordance with the provision of Clause
                                      6.6.1.0 hereof as shall remain/ persist at the time of
                                      preparation of the Final Bill by the CONTRACTOR
                                      shall be separately included in the Final Bill prepared
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                Page 3 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                       by the CONTRACTOR in the form of a Statement of
                                      Claims attached thereto, giving particulars of the
                                      nature of such claim, grounds on which it is based, and
                                      the amount claimed, and shall be supported by
                                      copy(ies) of the notice(s) sent in respect thereof to the
                                      Engineer-in-Charge and the OWNER under Clause
                                      6.6.1.0 hereof. In so far as such claim shall in any
                                      material particular be at variance with the claim
                                      notified by the CONTRACTOR within the provisions
                                      of Clause 6.6.1.0 hereof, it shall be deemed to be a
                                      claim different from the notified claim with
                                      consequence in respect thereof indicated in Clause
                                      6.6.1.0 hereof, and with consequence in respect of the
                                      notified claim as indicated in Clause 6.6.3.1 hereof.

                                      6.6.3.1 Any and all notified claims not specially
                                      reflected and included in the Final Bill in accordance
                                      with the provisions of Clause 6.6.3.0 hereof shall be
                                      deemed to have been waived and relinquished by the
                                      CONTRACTOR, and the CONTRACTOR hereby
                                      waives and relinquishes all rights to raise or include in
                                      the Final Bill any claim(s) other than a notified claim
                                      conforming in all respects to and in accordance with
                                      the provisions of Clause 6.6.3.0 hereof.

                                                           *****

                               9.0.0.0 ARBITRATION

                                      9.1.0.0 Subject to the provisions of Clauses 6.7.1.0,
                                      6.7.2.0 and 9.1.1.0 hereof, any dispute arising out of a
                                      Notified Claim of the CONTRACTOR included in the
                                      Final Bill of the CONTRACTOR in accordance with
                                      the provisions of Clause 6.6.3.0 hereof, if the
                                      CONTRACTOR has not opted for the Alternative
                                      Dispute Resolution Machinery referred to in Clause
                                      9.2.0.0 in respect thereof, and any dispute arising out
                                      of an amount claimed by the OWNER against the
                                      CONTRACTOR shall be referred to the arbitration by
                                      an Arbitral Tribunal comprised of 3 (three) arbitrators
                                      selected in accordance with the provisions of the
                                      Arbitration & Conciliation Act, 1996. It is specifically
                                      agreed that the OWNER may prefer its Claim(s)
                                      against the CONTRACTOR as counterclaim(s). The
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 4 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                       CONTRACTOR shall not, however, be entitled to raise
                                      as a setoff, defence or counter-claim any claim which
                                      is not a Notified Claim included in the
                                      CONTRACTOR's Final Bill in accordance with the
                                      provisions of Clause 6.6.3.0 hereof."


                          6.    On    9th   February,   2018,   the   petitioner   addressed     a
                          communication to M/s Engineers India Limited (appointed by the
                          respondent as the Engineer-in-Charge of the project and referred to,
                          hereinafter, as "EIL"), notifying the following claims as payable to it
                          by the respondent:
                                S.               Description               Amount (Rs.)
                                No.
                                I   Plant and Machinery Costs which are    17,21,48,149
                                    deployed during the overstay period
                                    from July, 2015 to 15th Nov 2017
                                II Overhead Expenses incurred in the       25,01,73,689
                                    prolonged period of forced overstay
                                    from July, 2015 to 15th Nov 2017
                                III Head Office Overheads expenditure      14,95,70,375
                                    incurred from July, 2015 to 15th Nov
                                    2017
                                IV Compensation for the losses of          50,58,75,000
                                    opportunity incurred due to delay in
                                    execution for the reasons not
                                    attributable to the contractor from
                                    July, 2015 to 15th Nov 2017
                                V Compensation for losses against          27,19,078
                                    margin money deposited for the bank
                                    guarantees from July, 2015 to 15th
                                    Nov 2017 due to prolongation of
                                    Project.
                                VI Compensation for the losses against     14,54,27,797
                                    the interest on working capital and
                                    profits blocked up during the
                                    stipulated completion of Contract
                                    due to delay in handing over of land
                                    and other reasons from July 2015 to
                                    15th Nov 2015
                                                                   Total   1,22,59,14,088
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                              Page 5 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           7.      The controversy in the present case essentially revolves around
                          three communications addressed by the petitioner to EIL on 16th July,
                          2018, 5th September, 2018 and 20th September, 2018 respectively.


                          8.      Given the vehemence of opposition, by the respondent, to the
                          reference of disputes between the parties to the arbitration, predicated
                          entirely on these three documents, it is necessary, at the cost of
                          brevity, to reproduce these three communications in their entirety,
                          thus:

                                  Petitioner to EIL dated 16th July, 2018

                                  "Ref: CS-ES /6979/L/412/2018
                                  Date: 16th July, 2018

                                  To,

                                  Mr. Vijay Shahri,
                                  Resident Construction Manager,
                                  Engineers India Limited,
                                  SSCD-Padur Post, Via Kaup,
                                  Udupi - 574106

                                  Sub: Pipe Line Laying from LFP to Mangalore /Padur
                                  Cavern via Intermediate Valve Station (lVS) for ISPRL
                                  Project: Submission of RA Bill No.-35/ Final Bill

                                  Ref: AS /6979-003-MK-TN-1010/1001- Pipeline Laying
                                  from LFP to Mangalore / Padur cavern,

                                  Dear Sir,

                                        Please find enclosed herewith the RA Bill No.35/Final
                                  for an amount of INR. 27,23,12,488.00/- (Indian Rupees
                                  Twenty Seven Crore Twenty Three lakhs Twelve Thousand
                                  Four Hundred Eighty Eight only) against Work Done value
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 6 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                including Goods & Service Tax (GST) in terms-of Clause
                               6.2.1.0 of GCC for your kind verification and certification for
                               payment along with Contract Closing Documents and
                               Notified Claims.

                                      As per Clause 5.3.5 of Special Conditions of Contract
                               (Part A, Sub Section A-2.2) Contractor is entitled for payment
                               against statutory variation in respect of change in service tax
                               rate after the submission of final price bid. Accordingly the
                               Contractor herewith submit the claim against service tax
                               variation payable till RA-35/Final Bill for an amount of
                               Rs.38,132,366/·

                                       As per Clause 14.0; the Contractor is entitled for Price
                               Variation and accordingly the Claim for Price Variation for an
                               amount of Rs.4,12,390/- is submitted herewith for your
                               certification and further release of payment.

                                     As per Clause 21.0; the Contractor is entitled for
                               reimbursement of Fee paid for obtaining Statutory approvals
                               and accordingly we are herewith submitting our claim for
                               reimbursement of Statutory Approvals fees amounting to
                               Rs.7,03,916/- for your certification and further release of
                               payment.

                                      You are requested to kindly certify the RA Bill -
                               35/Final bill and release our due and eligible payments as per
                               the terms and conditions of the Contract.

                                      This is without prejudice to our right and privileges
                               under the contract and applicable law.

                                        Thanking you and assuring our best services at all
                               times.

                               Thanking you,
                               For IL&FS Engineering Construction Co. Ltd.
                               Oil & Gas Project -Mangalore"

                               Petitioner to EIL dated 5th September, 2018

                               "Ref: CS-ES /6979/L/412/2018
                               Date: 5th September, 2018
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 7 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                To,

                               Mr. Vijay Shahri,
                               Resident Construction Manager,
                               Engineers India Limited,
                               SSCD-Padur Post, Via Kaup,
                               Udupi - 574106

                               Sub: Pipe Line Laying from LFP to Mangalore /Padur
                               Cavern via Intermediate Valve Station (lVS) for ISPRL
                               Project: Submission of RA Bill No.-35/ Final Bill

                               Ref: AS /6979-003-MK-TN-1010/1001- Pipeline Laying
                               from LFP to Mangalore / Padur cavern,

                               Dear Sir,

                                     Please find enclosed herewith the RA Bill No.35/Final
                               for an amount of INR. 27,19,36,236.00/- (Indian Rupees
                               Twenty Seven Crore Nineteen lakhs Thirty Six Thousand'two
                               Hundred Thirty Six only) against Work Done value including
                               Goods & Service Tax (GST) in terms-of Clause 6.2.1.0 of
                               GCC for your kind verification and certification for payment
                               along with Contract Closing Documents and Notified Claims.

                                      As per Clause 5.3.5 of Special Conditions of Contract
                               (Part A, Sub Section A-2.2) Contractor is entitled for payment
                               against statutory variation in respect of change in service tax
                               rate after the submission of final price bid. Accordingly the
                               Contractor herewith submit the claim against service tax
                               variation payable till RA-35/Final Bill for an amount of
                               Rs.38,113,877/·

                                       As per Clause 14.0; the Contractor is entitled for Price
                               Variation and accordingly the Claim for Price Variation for an
                               amount of Rs.4,12,390/- is submitted herewith for your
                               certification and further release of payment.

                                     As per Clause 21.0; the Contractor is entitled for
                               reimbursement of Fee paid for obtaining Statutory approvals
                               and accordingly we are herewith submitting our claim for
                               reimbursement of Statutory Approvals fees amounting to
                               Rs.7,03,916/- for your certification and further release of
                               payment.
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 8 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                       You are requested to kindly certify the RA Bill -
                               35/Final bill and release our due and eligible payments as per
                               the terms and conditions of the Contract.

                                      This is without prejudice to our right and privileges
                               under the contract and applicable law.

                               Thanking you and assuring our best services at all times.

                               Thanking you,
                               For IL&FS Engineering Construction Co. Ltd.
                               Oil & Gas Project -Mangalore"

                               Petitioner to EIL dated 20th September, 2018

                               "Ref: CS-ES /6979/L/415/2018
                                Date: 20th September, 2018

                               To,

                               Mr. Vijay Shahri,
                               Resident Construction Manager,
                               Engineers India Limited,
                               SSCD-Padur Post, Via Kaup,
                               Udupi - 574106

                               Sub: Pipe Line Laying from LFP to Mangalore /Padur
                               Cavern via Intermediate Valve Station (lVS) for ISPRL
                               Project: Submission of RA Bill No.-35/ Final Bill

                               Ref: AS/6979-003-MK-TN-l0l0/l00l- Pipeline Laying from
                               LFP to Mangalore/Padur Cavern,

                               Dear Sir,

                                      Please find enclosed herewith the RA Bill No.35/Final
                               for an amount of INR. 27,19,36,236.00/- (Indian Rupees
                               Twenty Seven Crore Nineteen Lakhs Thirty Six Thousand
                               Two Hundred Thirty Six only) against Work Done value
                               including Goods & Service Tax (GST) in terms of Clause
                               6.2.1.0 of GCC for your kind verification and certification for
                               payment along with Contract Closing Documents. With this
                               we are withdrawing our earlier submission vide our letter no.
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                  Page 9 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                  CS-ES /6979/l/412/2018, dated 08th September 2018.

                                        As per Clause 5.3.5 of Special Conditions of Contract
                                 (Part A, Sub Section A-2.2) Contractor is entitled for payment
                                 against statutory variation in respect of change in service tax
                                 rate after the submission of final price bid. Accordingly the
                                 Contractor herewith submit the claim against service tax
                                 variation payable till RA-35/Final Bill for an amount of
                                 Rs.38,113,877/- As per Clause 14.0; the Contractor is entitled
                                 for Price Variation and accordingly the Claim for Price
                                 Variation for an amount of Rs. 4,12,390/- is submitted
                                 herewith for your certification and further release of payment.

                                        As per Clause 21.0; the Contractor is entitled for
                                 reimbursement of Fee paid for obtaining Statutory approvals
                                 and accordingly 'we are herewith submitting our claim for
                                 reimbursement of Statutory Approvals fees amounting to
                                 Rs.7,03,916/- for your certification and further release of
                                 payment. You are requested to kindly certify the RA Bill -
                                 35/Final bill and release our due and eligible payments as per
                                 the terms and conditions of the Contract.

                                        This is without prejudice to our rights and privileges
                                 under the contract and applicable law.

                                          Thanking you and assuring our best services at all
                                 times.

                                 Thanking you
                                 For IL&FS Engineering & Construction Co.Ltd.
                                 Oil & Gas Project -Mangalore"

                          9.     According to Mr. Hrishikesh Baruah, learned counsel for the
                          petitioner, the following list of notified claims were annexed to the
                          first of the aforesaid three communications, dated 16th July, 2018:
                               PROJECT: PIPELINE LAYING FROM LFP TO MANGALORE/FADUR CAVERNS
                                  CLIENT:CLIENT: INDIAN STRATEGIC PETROLEUM RESERVES LTD.

                                                      NOTIFIED CLAIMS
                                       ENGINEERING IN-CHARGE ENGINEERS INDIA LTD. (EIL)
                               CONTRACTOR: IL&FS ENGINEERING AND CONSTRUCTION COMPANY LTD.
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 10 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                               FOA NO : ISPRL/MG/RPA/34 Dated 03.07.2014
                                               LOA NO ISPR/MG/RPA/35/Dated 11.08.2014

                           Sr.
                                 Item No.        ITEM DESCRIPTION                  Rate(INR)         REMARKS
                           No.

                                                         Uncertified Extra Claim

                                             Interim Claim for compensation
                                             against losses/damages incurred
                                             due to extremely slow progress of                      Submitted Vide
                            1     EX-03      Works due to various reasons not    1,225,914,088.00   letter No. 405,
                                             attributable to the Contractor.                        09th Feb, 2018
                                             From July 2015 to November
                                             2017
                                                                                                    Submitted Vide
                                                                                                    Letter No. 180,
                            2     EX-04      Boring - Silver Gate Xing                 3,751,110
                                                                                                    09th October,
                                                                                                    2015
                                                                                                    Submitted Vide
                                                                                                    Letter No. 248,
                            3     EX-05      Boring - IVS                              1,811,649
                                                                                                    09th October,
                                                                                                    2015
                                                                                                    Submitted Vide
                            4     EX-06      Boring - ELF Junction                     1,112,182    Letter No. 249,
                                                                                                    25th April, 2016
                                                                                                    Submitted Vide
                                             Extra Claim for 20 Nos. LR                             Letter No. 293,
                            5     EX-07                                               10,198,842
                                             Bends                                                  11th August,
                                                                                                    2016
                                                                                                    Submitted Vide
                                             Extra Claim for Additional Cold
                            6     EX-08                                               29,196,813    Letter No. 278,
                                             Bend
                                                                                                    12th July, 2016
                                                                                                    Submitted Vide
                                             Cost Incurred for Supply of 42"                        Letter No. 399,
                            7     EX-09                                                5,888,362
                                             & 48" Piping                                           09th January,
                                                                                                    2018
                                          Total Amount (INR)                       1,277,873,046
                                             Rent Payment at Soorianje                              Deducted in
                            8       -        (Deducted in RA - 29, 30, 31,32,          1,522,500    Running Bills
                                             33 & 34)                                               by ISPRL
                                                                                                    Payment
                            9       -        Police Protection                            15,450
                                                                                                    Details attached
                                                                                                    Payment
                            10      -        Blasting Payment at Kalathur              4,784,928
                                                                                                    Details attached
                                             BSNL Payment for Leased Line                           Payment
                            11      -                                                    389,400
                                             at Padur                                               Details attached
                                             BSNL Payment for Leased Line                           Payment
                            12      -                                                    105,238
                                             at Mangalore                                           Details attached
                                          Total Amount (INR)                           6,817,416
                                        Sub Total Amount (INR)                     1,284,690,462



Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                            Page 11 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           10.   As these claims remained outstanding, the petitioner invoked
                          the provision for arbitration contained in Clause 9.1.0.0 of the GCC,
                          vide letter dated 5th December, 2019 addressed to the respondent. The
                          notice also nominated Hon'ble Mr. Justice A.P. Shah, an eminent
                          retired Chief Justice of this Court and former Chairman of the Law
                          Commission of India, as the petitioner's arbitrator. The respondent
                          was called upon to appoint its arbitrator, so that the two learned
                          arbitrators could appoint a third Presiding Arbitrator and the coram of
                          the Arbitral Tribunal could be completed.


                          11.   The respondent, however, replied on 23rd December, 2019,
                          denying the arbitrability of the disputes and also denying that any
                          amount was payable to the petitioner.


                          12.   It is in these circumstances that the petitioner has moved this
                          Court by the present petition under Section 11(6) of the 1996 Act,
                          praying that this Court appoint a nominee arbitrator for the
                          respondent, so that the two learned arbitrators could proceed to
                          appoint the third arbitrator and the arbitral proceedings could take off.
                          The respondent has filed reply to the petition and the petitioner has
                          filed his rejoinder thereto.


                          13.   Mr. Hrishikesh Baruah, learned counsel for the petitioner, and
                          Mr. Dinesh Pardasani, learned counsel for the respondent, have been
                          heard at length.


                          14.   Mr. Baruah submits that the claims had been notified by the
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                             Page 12 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           petitioner in accordance with Clause 6.6.1.0 and that there is no
                          dispute regarding the fact that this notification had taken place within
                          the period of 14 days stipulated in the said clause. He also invited my
                          attention to the days entered in the "Remarks" column in the list of
                          notified claims attached to the letter dated 16th July, 2018, which also
                          bear out the fact that the claims were notified within the aforesaid 14
                          days period.      Though Mr. Pardasani, learned counsel for the
                          respondent, sought to submit that he was disputing the contention of
                          Mr. Baruah that the invocation of the claims was within the 14 day
                          period contemplated by Clause 6.6.3.0, he acknowledges that no such
                          specific challenge has been raised in the reply filed by the respondent
                          in response to the present petition. To a query from the court as to
                          when, according to him, the 14 day period stipulated in Clause 6.6.1.0
                          had expired, Mr. Pardasani submits that the claims related to delay and
                          that, therefore, the said period of 14 days was required to be reckoned
                          from the date of delay. To my mind, prima facie, such an argument
                          would amount to re-writing Clause 6.6.1.0 which specifically states
                          that the period of 14 days has to be from the "date of the issue of
                          orders or instructions relative to the work for which the contractor
                          claims additional payment or compensation". This being a statutory
                          prescription, it would bind the parties to the contract. Inasmuch as the
                          disputes are being referred to arbitration, I do not see to state anything
                          further in this regard. It would be open to the parties to agitate the
                          point before the learned Arbitral Tribunal, which is eminently
                          competent to adjudicate thereon.


                          15.   The objection of Mr. Pardasani essentially revolves around the
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                              Page 13 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           Clause 6.6.3.0, 6.6.3.1, 6.2.3.0 and 6.2.5.0 of the GCC. He submits
                          that Clause 6.6.1.0 cannot be read in isolation. Clause 6.6.3.0, he
                          points out, is in clear continuation of Clause 6.6.1.0, and requires
                          claims, notified under Clause 6.6.1.0, remaining unpaid at the time of
                          preparation of the final bill to be separately included in the final bill
                          prepared by the contractor, i.e. by the petitioner in the form of
                          statement of form attached thereto, giving particulars of such claims,
                          the grounds on which it was based, the amount claimed and supported
                          by copies of notices sent in respect thereof to the EIC and the
                          respondent. In the event of variance with the claims notified in Clause
                          6.6.1.0, Mr. Pardasani points out that Clause 6.6.3.0 deems the claims
                          to be different from the notified claims. Mr. Pardasani also emphasises
                          the effect of Clause 6.6.3.1, as deeming claims not specifically
                          reflected and included in the final bill in accordance with Clause
                          6.6.3.0 to be deemed to have been waived and relinquished. Such
                          disputes, therefore, points out Mr. Pardasani, cannot be referred to
                          arbitration and are, ex-facie, not arbitrable in nature.


                          16.   Mr. Pardasani also draws my attention to Clause 6.2.3.0 to
                          submit that the final bill drawn in accordance with Clause 6.2.1.0 was
                          required to be submitted along with the completion certification to EIL
                          for certification, and that EIL was required to certify the final bill. Mr.
                          Pardasani submits that the "final bill" submitted with the letter dated
                          16th July, 2018 was only a draft final bill, as it was not accompanied
                          by any completion certificate. He points out that the only final bill
                          submitted by the petitioner was the bill attached to the letter dated 20th
                          September, 2018, after the completion certificate had been issued. It
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 14 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           was precisely for this reason, submits Mr. Pardasani, that though the
                          bill attached to the letter dated 16th July, 2018 was submitted to EIL,
                          EIL did not certify it or forward it to the respondent. (Significantly,
                          however, Mr Pardasani does not seek to contend that EIL returned the
                          bill dated 16th July, 2018 to the petitioner as not having been
                          submitted in accordance with the provisions of the GCC.)


                          17.       In these circumstances, Mr. Pardasani submits that the only
                          final bill submitted by the petitioner, in accordance with the contract,
                          was the bill attached to the communication dated 20th September,
                          2018. No statement of notified claims was attached to that bill. As
                          such, submits Mr. Pardasani, the list of notified claims submitted with
                          the bill of 16th July, 2018 could not come to the help of the petitioner
                          and ought to be treated as having been waived by the petitioner. There
                          being no list of notified claims attached to the final bill submitted with
                          the letter dated 20th September, 2018, as was required by Clause
                          6.6.1.0, Mr. Pardasani submits that the claims of the petitioner cannot
                          be referred to arbitration, in view of the strict protocol prescribed in
                          Clause 9.1.0.0 of the GCC.


                          18.       Mr. Pardasani relies on the judgment of this Court in Brilltech
                          Engineers Pvt. Ltd. v Darrameks Hotels and Developers Pvt. Ltd 1.


                          19.       In   rejoinder,   Mr.   Baruah   invites   my   attention   to   a
                          communication, dated 21st June, 2018, from the respondent to the
                          petitioner, which reads thus:

                          1
                              MANU/DE/2093/2020
Signature Not Verified
Digitally Signed           ARB.P. 578/2020                                               Page 15 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                     "Dear Sir,

                                          As discussed with Planning engineer M/s ILFS is
                                    advised to submit the final bill by 22.06.2018.

                                             This is for your information & necessary action please.

                                    Regards,

                                    Dharuman Meyyazhagan

                                    For Vijay Shahri
                                    Resident Construction Manager
                                    Engineers India Limited
                                    Strategic Storage of Crude Oil Project-Padur
                                    Mob: 9008071836"


                          20.       Mr. Baruah also relies on the judgment of the Supreme Court in
                          Vidya Drolia v. Durga Trading Corporation2, and a coordinate Single
                          Bench of this Court in NCC Ltd. v. IOCL3.

                          Analysis


                          21.       The scope of examination by this Court, exercising jurisdiction
                          under Section 11(6), is extremely limited and stands authoritatively
                          delineated by the Supreme Court in its decision in Vidya Drolia2.


                          22.       There is no dispute, by the respondent, in the present case, of
                          the existence of an arbitration agreement between the parties. The
                          contest is only regarding the arbitrability of the dispute raised by the
                          petitioner. Mr. Pardasani's contention is that no arbitrable dispute,
                          within the meaning of Clause 9.1.0.0 of the GCC, exists. This Court

                          2
                              2020 SCC OnLine SC 1018
                          3
                              2019 SCC OnLine Del 6964
Signature Not Verified
Digitally Signed           ARB.P. 578/2020                                                    Page 16 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           has, in its recent judgment in Mahindra Susten Pvt. Ltd. v NHPC
                          Ltd.4 had occasion to study, in detail, the principles relating to the
                          scope of examination by the court exercise jurisdiction under Section
                          11(6) of the 1996 act, into the aspect of arbitrability of the dispute, vis-
                          a-vis the jurisdiction statutorily vested by Section 16 on the arbitral
                          tribunal in that regard, as enunciated by the Supreme Court in Vidya
                          Drolia2. After extracting, in extenso, the relevant passages from Vidya
                          Drolia2, this Court arrived at the following conclusions:
                                    "31. The import of the above passages from Vidya Drolia2
                                    is clear and unmistakable. Section 11(6A) of the 1996 Act
                                    has been held to continue to apply, as a guiding principle to
                                    be followed by courts at the referral stage, even after its
                                    omission. Even while holding that the "arbitrability" of the
                                    dispute, along with the aspect of existence of an arbitration
                                    agreement between the parties, could be examined, to a
                                    limited extent, by the Court exercising jurisdiction under
                                    Section 8 or Section 11 of the 1996 Act, the Supreme Court
                                    has been circumspect, many times over, in emphasising the
                                    limitations of the Court in this regard. It has been made
                                    unmistakably clear that, in exercise of its limited scope of
                                    authority, to examine the questions of existence of the
                                    arbitration agreement and arbitrability of the dispute, at the
                                    referral stage, the Court has to be careful not to usurp the
                                    jurisdiction of the arbitral tribunal which, ideally, should
                                    examine these aspects. The scope of examination by the
                                    referral court under Section 11(6), into the aspects of
                                    existence of the arbitration agreement, or arbitrability of the
                                    dispute, is, strictly, prima facie. In other words, it is only if,
                                    prima facie, the Court finds that no valid arbitration
                                    agreement exists, that it would refuse to refer the dispute to
                                    arbitration. In undertaking this exercise, the Court should
                                    not get lost in thickets, or enter into debatable factual issues.
                                    Unless there are good and substantial reasons to the
                                    contrary, the Court is required to compel the parties to abide
                                    by the arbitration agreement. It is only in the case where the
                                    arbitration agreement is "ex facie non-existent or invalid",
                                    or the dispute is ex facie non-arbitrable, that the court would

                          4
                              MANU/DE/0288/2021
Signature Not Verified
Digitally Signed           ARB.P. 578/2020                                                      Page 17 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                refuse to refer the dispute to arbitration. The intention is "to
                               cut off the deadwood and trim off the side branches in
                               straightforward cases where dismissal is barefaced and
                               pellucid and when on the facts and law the litigation must
                               stop at the first stage", and to ensure that "vexatious and
                               frivolous matters get over at the initial stage". This would
                               also "save costs and check harassment of objecting parties
                               when there is clearly no justification and a good reason not
                               to accept the plea of non-arbitrability". "Senseless and ill-
                               considered claims" and "ex facie meritless, frivolous and
                               dishonest litigation" were required to be weeded out, as, "on
                               the other side of a very irresponsible and senseless claim",
                               there was an innocent sufferer. Certainty, in the mind of the
                               Court, that no valid arbitration agreement exists or that the
                               disputes/subject matter are not arbitrable, is the sine qua non
                               for rejection of the prayer for referring the dispute to
                               arbitration, whether made under Section 8 or Section 11. The
                               scope of examination at this stage is preliminary and
                               summary and not in the nature of a mini-trial.

                                                           *****

                               33.    It has been made further clear that the dispute would
                               be regarded as "non-arbitrable", at the Section 8 or Section
                               11 stage, only where the nature of the dispute is ex facie non-
                               arbitrable, or where the dispute does not relate to the
                               arbitration agreement. The situation has to be "chalk and
                               cheese" or, alternatively, "black and white... without shades
                               of grey". In all other cases, the Section 11 court should
                               follow the more conservative course of allowing the parties
                               to have their say before the arbitral tribunal. Cases where
                               the dispute is, by law, ex facie non-arbitrable, would, for
                               example, be criminal cases, cases involving exercise of
                               sovereign power, cases which, by statutory fiat, are required
                               to be determined by courts, cases in which the cause of
                               action is in rem, or where the subject matter of the dispute
                               affects third parties or has erga omnes effect, requiring
                               centralised adjudication. "On the other hand, issues relating
                               to contract formation, existence, validity and non-
                               arbitrability ... would be factual and disputed and for the
                               arbitral tribunal to decide". Questions involving mixed
                               issues of fact and law have to be left to the arbitral tribunal.

                               34.    In order to underscore the limitations of the Section 8,
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 18 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                or Section 11 Court, in entering into debatable issues of
                               existence of the arbitration agreement or arbitrability, the
                               Supreme Court has emphasised the purpose behind
                               conferring a limited jurisdiction, on the referral court, to
                               examine these aspects. The conferral of such limited
                               jurisdiction is intended "to prevent wastage of public and
                               private resources", and to protect parties from being forced
                               to arbitrate when the matter is clearly non-arbitrable. Where,
                               however, prima facie review appears to be inconclusive, or
                               inadequate as it requires detailed examination, the matter
                               has to be left for determination by the arbitral tribunal.
                               Parties should not be allowed to use the referral proceedings
                               as a ruse to delay or obstruct resolution of the dispute.
                               Unjustified impairment of the referral proceedings should
                               not be permitted. Even in cases which may fall under one of
                               the limited categories where prima facie examination is
                               permitted under Section 8 or Section 11, the Court may,
                               nevertheless, decide that allowing the arbitrator to rule first
                               on her, or his, competence would be best for the arbitration
                               process.

                               35.     This position was alternately exposited, by the
                               Supreme Court, as clarifying that the requirement of the
                               court was "to see if the underlying contract contains an
                               arbitration clause for arbitration of the disputes which have
                               arisen between the parties-nothing more, nothing less". The
                               court was permitted to interfere at the referral stage "only
                               when it is manifest that the claims are ex facie time-barred
                               and dead, or there is no subsisting dispute", all other cases
                               requiring to be referred to the arbitral tribunal for decision on
                               merits. The position was summed up by holding that "in case
                               of debatable and disputable facts and good reasonable
                               arguable case, etc., the court would force the parties to
                               abide by the arbitration agreement as the arbitral tribunal
                               has primary jurisdiction and authority to decide the disputes
                               including the question of jurisdiction and non-arbitrability".

                               36.    Significantly, the Supreme Court opined that, in the
                               case of pure commercial disputes, the more appropriate
                               principle of interpretation would be one of liberal
                               construction, as there was a presumption in favour of one-
                               stop adjudication.

                               37.    On the aspect of examination of the arbitrability of
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                  Page 19 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                 the dispute at the referral stage, the Supreme Court held that
                                "the court by default would refer the matter when
                                contentions regarding to non-arbitrability are plainly
                                arguable; when consideration in summary proceedings
                                would be insufficient and inclusive; when facts are
                                contested; when the party opposing arbitration adopts
                                delaying tactics or impairs conduct of arbitration
                                proceedings", cautioning the court not to usurp the
                                jurisdiction of the arbitral tribunal, but to affirm and uphold
                                the integrity and efficacy of arbitration as an alternative
                                dispute resolution mechanism."
                                                            (Italics and underscoring supplied)


                          23.   The position in law which emerges from Vidya Drolia2 is that,
                          while the arbitrability of the dispute may also be examined by the
                          Section 11 court, the examination has strictly to be prima facie in
                          nature, with an intention to trimming off the side branches and
                          weeding out the deadwood. The Court must recognize and respect the
                          fact that pre-eminent jurisdiction, even to decide the question of
                          arbitrability of the dispute, stands statutorily conferred, under Section
                          16 of the 1996 Act, on the arbitral tribunal.            Usurping of that
                          jurisdiction has, at all costs, to be avoided. It is only in a case where
                          dispute is ex facie non-arbitrable in nature that the court can refuse to
                          refer the dispute to arbitration.


                          24.   Clause 9.1.0.0 of the GCC in the present case stipulates, at best,
                          the following three pre-requisites, for a dispute to be arbitrable
                          thereunder:
                                (i)     that the dispute must arise out of a notified claim of the
                                contractor,
                                (ii)    that the notified claim must be included in the final bill of
                                the contractor and
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 20 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                  (iii)   that such inclusion must be in accordance with the
                                 provisions of Clause 6.6.3.0 of the GCC.
                          If these three conditions are satisfied, the dispute is arbitrable under
                          Clause 9.1.0.0.


                          25.    The extent to which this Court can wade into the morass of
                          facts, while exercising jurisdiction in a case such as the present, can
                          only be such as would enable it to arrive at a prima facie view
                          regarding the arbitrability of the dispute, and no more.


                          26.    Viewed thus, I fail to see how it can be contended that the
                          dispute raised by the petitioner is not arbitrable in nature.

                          27.    The disputes were notified by the petitioner, firstly in its letter
                          dated 9th February, 2018, and, later, in the list of notified claims
                          attached to the letter dated 16th July, 2018, alongwith the final bill,
                          annexed with the said letter (though Mr. Pardasani disputes that the
                          bill could be treated as "final" at all).

                          28.    These claims were, undisputedly, notified within the period of
                          14 days stipulated in Clause 6.6.1.0 of the GCC. The letter dated 16th
                          July, 2018 expressly attached, therewith, the final bill. In this context,
                          I find substance in the reliance, by Mr. Baruah, on the communication
                          dated 21st June, 2018 from the respondent to the petitioner, requiring
                          the petitioner to submit the final bill by 22nd June, 2018. It cannot lie
                          in the mouth of the respondent to state that no final bill was submitted
                          by the petitioner with the letter dated 16th July, 2018, though the
                          petitioner was always well within its right to contest the payability of
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 21 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           the final bill, or of the notified claims attached to the said final bill in
                          the arbitral proceedings.


                          29.   The third requirement in Clause 9.1.0.0, for the dispute to be
                          arbitrable in nature, was that the inclusion of the notified claims with
                          the final bill was required to be in accordance with Clause 6.6.3.0. All
                          that Clause 6.6.3.0 states is that notified claims, remaining unpaid at
                          the time of preparation of final bill, were to be "separately included in
                          the final bill....... in the form of a statement of claim attached thereto,
                          giving particulars of nature of such claims, grounds on which it is
                          based and the amount claimed", supported by copies of notices sent in
                          respect thereof. Mr. Baruah has pointed out that the list of notified
                          claims set out the details of the claims, the documents claiming the
                          amounts, the amounts claimed and the dates when these claims were
                          first submitted to the respondent, were duly attached to the
                          communication dated 16th July, 2018. It cannot, therefore, be said that
                          the notified claims were not included in the final bill in accordance
                          with the provisions of Clause 6.6.3.0.


                          30.   Thus, all three ingredients, envisaged as pre-requisites for the
                          dispute to be arbitrable, by Clause 9.1.0.0 stand, therefore, prima
                          facie, satisfied in the present case.


                          31.   The reliance, by Mr. Pardasani, on Clause 6.2.3.0 of the GCC
                          cannot, in my view, militate against this factual position. Clause
                          6.2.3.0 requires the final bill drawn in accordance with Clause 6.2.1.0
                          to be submitted to the Engineer-in-Charge together with the
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                Page 22 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           completion certificate for certification. The issue, so far as Section
                          11(6) of the Act, juxtaposed with Clause 9.1.0.0 of the GCC, is
                          concerned, is not whether the final bill was submitted in accordance
                          with Clause 6.2.3.0 or not, but whether the notified claims were
                          submitted in accordance with Clause 9.1.0.0. On this issue, I have
                          already recorded a prima facie finding in favour of the petitioner.


                          32.   Within the limited extent of my jurisdiction under Section 11(6)
                          of the 1996 Act, I seriously doubt whether I can enter into the
                          intricacies of whether the final bill was in accordance with clause
                          6.2.3.0 or not.


                          33.   There is another aspect of the matter. Mr. Pardasani himself
                          admits the fact that, on 20th September, 2018, a final bill was
                          submitted by the petitioner. He contends, therefore, that the final bill
                          which was earlier submitted on 16th July, 2018 was a "draft final bill".
                          With the letter dated 20th September, 2018, with which, according to
                          him, the final bill was actually submitted by the petitioner, Mr
                          Pardasani points out that there were no notified claims attached.


                          34.   This argument would throw up the issue of whether, merely
                          because, with the letter dated 20th September, 2018, the list of notified
                          claims, attached to the earlier letter dated 16th July, 2018, was not re-
                          attached, the petitioner could be treated as having given up the said
                          claims. It is relevant to note, in this context, that the letter dated 20th
                          September, 2018 only withdrew the earlier letter dated 8th September,
                          2018, and that there is no communication from the petitioner to the
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 23 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           respondent withdrawing the earlier letter dated 16th July, 2018. It
                          merits reiteration, in this context, that the EIL, too, never deemed it
                          appropriate to return the letter dated 16th July, 2018 to the petitioner,
                          stating that it was irregular in any respect. More importantly, the
                          petitioner has never, expressly or by necessary implication, withdrawn
                          its Notified Claims, as attached to the letter dated 16th July, 2018.


                          35.   It may, therefore, be also open to the petitioner to contend that
                          the notified claims attached with the letter dated 16th July, 2018
                          continue to remain arbitrable, as they were never withdrawn by the
                          petitioner by any letter or subsequent communication.


                          36.   All these issues, clearly, would require a detailed factual
                          analysis, which a court exercising jurisdiction under Section 11 of the
                          1996 Act can hardly be expected to undertake. No doubt, Vidya
                          Drolia2 specifically cautions courts, exercising jurisdiction under
                          Section 11 from wading into these thickets. It cannot be said, at any
                          rate, that a prima facie case of non-arbitrability of the dispute raised
                          by the petitioner exists, as would justify rejection of the present
                          petition.


                          37.   Before concluding this judgment, I may also refer to the
                          decision of this Court in Brilltech Engineers Pvt. Ltd.1, on which Mr.
                          Pardasani placed reliance. A bare reading of the said decision reveals
                          that the facts of that case are completely distinct from those of the
                          present case. In that case, this Court found, on facts, as under:

                                "11. There is no doubt that there has been a series of
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 24 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                communications, between the petitioner and the respondent,
                               in connection with the claims of the petitioner. At the same
                               time, I am not able to convince myself that these
                               communications can suffice to constitute notification of the
                               said claims, in accordance with the protocol set out in the
                               various sub-clauses of Clause 52.1 of the GCC. It is seen that
                               Clause 52.1.1 and Clause 52.1.2 prescribed a rigorous
                               discipline, to be followed, in the matter of notification of
                               claims. The contractor is required to give notice in writing of
                               his claim within 10 days from the date of issue of orders or
                               instructions relating to the works for which additional
                               payment of compensation is sought. This notice is required to
                               contain full particulars of the nature of claim, the grounds on
                               which it is based and the amount claimed. The notice is
                               required to be addressed to the Project Manager and the
                               owner of the respondent. Clause 52.1.2 requires any such
                               notified claims, which remain unpaid at the time of
                               preparation of the final bill by the contractor, to be separately
                               included in the final bill in the form of a statement of claim
                               attached thereto, giving particulars of the nature of the claim,
                               grounds on which it is based and the amount claimed,
                               supported by copies of the notices sent in respect thereof by
                               the contractor to the Project Manager and owner under Clause
                               52.1.1. Clause 52.2.1 provides for arbitration only of notified
                               claims, included in the final bill in accordance with the
                               provisions of Clause 52.1.2.

                               12.     The petitioner has filed a rejoinder, to the counter
                               affidavit of the respondent, which raises the specific
                               contention that the claims of the petitioner, which the
                               petitioner seeks to be referred to arbitration, have not been
                               notified in accordance with Clause 52.1.1, and no statement
                               of claim, in accordance with Clause 52.1.2, has been issued in
                               respect thereof. There is no traversal, of this contention, in the
                               rejoinder filed by the petitioner. Even during oral arguments,
                               Mr. Singhal, while acknowledging that the strict discipline of
                               Clauses 52.1.1 and 52.1.2 may not have been followed by his
                               client, nevertheless submits that the prayer, of his client, to
                               refer the disputes to arbitration, ought not to be rejected on
                               this ground, as the communications between the petitioner
                               and the respondent indicate that the respondent had
                               acknowledged the tenability of the petitioner's claims.

                               13.    Reference of claims to arbitration can be made, by the
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 25 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                                 Court, under Section 11, only if the claims are themselves
                                arbitrable, in accordance with the Arbitration Agreement
                                between the parties. The claims of the petitioner not having
                                been notified, and no statement of claim having been
                                submitted, in that regard, in accordance with the protocol set
                                out in Clauses 52.1.1 and 52.1.2, cannot be regarded as
                                arbitrable within the meaning of Clause 52.2.1 of the GCC."
                                                                         (Emphasis supplied)


                          38.   Brilltech Engineers1, therefore, involved a situation in which
                          the contention, of the respondent, in that case, that the claims being
                          sought to be referred to arbitration were not notified in accordance
                          with the appropriate contractual provision, and no statement of claim,
                          in respect thereof, was attached with the final bill, remained
                          untraversed in rejoinder.      Even during oral arguments, it was
                          conceded, by learned counsel for the petitioner in that case, that the
                          discipline envisaged in the contractual clauses referring to notification
                          of claims, and inclusion thereof in the final bill, had not been followed
                          by the petitioner. Reference of the claims was, nevertheless, sought on
                          the ground that the tenability of the claims remained undisputed by the
                          respondent. It is in these circumstances that the court went on to hold
                          that the protocol for notifying claims, submitting them with the bill
                          and referring them to arbitration not having been followed, the prayer
                          for referring of dispute could not be allowed.


                          39.   These infirmities do not attach to the claims of the petitioner in
                          the present case. The claims were invited within the stipulated period,
                          and submitted along with the final bill, in accordance with Clause
                          6.6.3.0 of the GCC.


Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                               Page 26 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           40.   As such, it cannot be said that no prima facie case of non-
                          arbitrability of the disputes raised by the petitioner has been made out
                          by the respondent.


                          41.   By way of a closing observation, para 154.4 of the judgment in
                          Vidya Drolia2 may be reproduced thus:
                                "154.4         Rarely as a demurrer the court may interfere at
                                the Section 8 or 11 stage when it is manifestly and ex facie
                                certain that the arbitration agreement is non- existent, invalid
                                or the disputes are non-arbitrable, though the nature and facet
                                of non-arbitrability would, to some extent, determine the level
                                and nature of judicial scrutiny. The restricted and limited
                                review is to check and protect parties from being forced to
                                arbitrate when the matter is demonstrably 'non-arbitrable' and
                                to cut off the deadwood. The court by default would refer the
                                matter when contentions relating to non-arbitrability are
                                plainly arguable; when consideration in summary proceedings
                                would be insufficient and inconclusive; when facts are
                                contested; when the party opposing arbitration adopts
                                delaying tactics or impairs conduct of arbitration proceedings.
                                This is not the stage for the court to enter into a mini trial or
                                elaborate review so as to usurp the jurisdiction of the arbitral
                                tribunal but to affirm and uphold integrity and efficacy of
                                arbitration as an alternative dispute resolution mechanism."


                          42.   Resistance, such as that manifested in the present case by the
                          respondent, to arbitration of the dispute, even after admitting the
                          existence of the arbitration agreement in the contractual executed, ad
                          idem, with the petitioner, does complete disservice to the avowed
                          statutory objective of "affirming and upholding the integrity and
                          efficacy of arbitration as an alternative dispute resolution mechanism".
                          It is unfortunate that a public sector undertaking, such as the
                          respondent, is adopting such a stance. At the end of the day, reference
                          of the disputes to arbitration causes no prejudice to anyone and, if
Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                                 Page 27 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           anything, aids in expeditious resolution thereof.


                          43.   Accordingly, this Court appoints Hon'ble Mr. Justice Mukul
                          Mudgal, former Chief Justice of Punjab and Haryana High Court, as
                          the respondent's arbitrator in the present case. The contact details of
                          learned arbitrator are as under:

                                Phone No: 9818000250
                                Email ID: [email protected]


                          44.   The parties are directed to contact the learned arbitrator at the
                          aforesaid contact details within a period of one week from today.


                          45.   The learned arbitrator appointed by the petitioner and the
                          aforesaid learned arbitrator appointed by this Court on behalf of the
                          respondent would, thereafter, proceed to appoint a third arbitrator so
                          that the arbitral proceedings could commence.


                          46.   The fees of the learned arbitrator appointed by the present
                          judgement would be decided by the learned arbitrator in consultation
                          with the parties.


                          47.   In view of the transparent attempt, of the respondent, to thwart
                          the enforcement of the arbitration agreement with the petitioner, I was
                          inclined to mulct the respondent with costs. However, keeping in mind
                          the fact that the respondent is a wholly owned subsidiary of the Oil
                          Industry Development Board, I refrain from doing so.

Signature Not Verified
Digitally Signed          ARB.P. 578/2020                                            Page 28 of 29
By:SUNIL SINGH NEGI
Signing Date:19.04.2021
21:42:56
                           48.   The petition is allowed in the aforesaid terms.

                          49.   All findings contained in this judgment, needless to say, are
                          only for determining whether the prayer for referring the disputes to
                          arbitration was required to be allowed, under Section 11(6) of the
                          1996 Act. They are strictly prima facie in nature and would not inhibit
                          the Arbitral Tribunal, in any manner, from arriving at a different
                          finding, on facts or in law, during the course of the arbitral
                          proceedings.




                                                                       C. HARI SHANKAR, J.

APRIL 15, 2021 dsn Signature Not Verified Digitally Signed ARB.P. 578/2020 Page 29 of 29 By:SUNIL SINGH NEGI Signing Date:19.04.2021 21:42:56