Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 13, Cited by 1]

Patna High Court - Orders

Dr.Priya Ranjan Kumar Singh vs M/S Chitra Deve. & Mark. &Ors on 16 April, 2009

Author: Mihir Kumar Jha

Bench: Mihir Kumar Jha

              IN THE HIGH COURT OF JUDICATURE AT PATNA
                          MA No.659 of 2008

     Dr.Priya Ranjan Kumar Singh, Son of late Kameshwar Prasad
     Singh, Resident of Mohalla-Patliputra, P.S.-Patliputra, town
     and District Patna.
                                         -----Opp. Party/Appellants
                               Versus
     1. M/s Chitra Developers and Marketing Private Limited,
        through its Director, Sri Vikas Kumar, Son of Sri
        Someshwar Lal, having its Office at 307, Adharshila
        Complex, South Gandhi Maidan, town and district Patna.
     2. Sri Vikas Kumar, son of Sri Someshwar Lal, Director M/S
        Chitra Developers and Marketing Private Limited, resident
        of Flat No. 613 B Lotus apartment, Road No. 1F, New
        Patliputra Colony, P.S. Patliputra, town and district
        Patna.
                                      ------Applicants/Respondents.
                               -------------
    For the Appellants         : Mr. Tarakant Jha, Sr. Adv.
                               : Mr. Anjani Kr. Sinha, No. 1 Adv.
    For the Respondent No. 1 : Mr. V. Nath, Adv.
                               : Mr. Ajay K. Singh, Adv.
                               : Mr. Md. Walique Rahman, Adv.
    For the Respondent No. 2 : Dr. K.N. Singh, Sr. Adv.
                               : Mr. Satish Kr., Adv.
                               : Mr. Radha Mohan Pandey, Adv.
                               --------------

                            P R E S E N T

                HON'BLE MR. JUSTICE MIHIR KUMAR JHA


Mihir Kumar Jha,J          This Miscellaneous Appeal is directed

                    against the order dated 29.09.2008 passed in

                    Miscellaneous Case No. 171 of 2008 allowing

                    the prayer of the applicants/respondents under

                    Section 9 of the Arbitration and Consolidation

                    Act (hereinafter to be referred to as „the

                    Act‟) restraining the opposite party appellant

                    from interfering in the work of construction
                         2




of   the    respondents             in    accordance         with     the

development agreement dated 1.9.2002.

           2. Facts required to be noticed for the

purposes      of        this      appeal      lie     in    a    narrow

compass. The appellant being the owner of the

land had entered into a development agreement

with    the    respondents               on   1.9.2002       for      the

purposes      of    getting         a    multistoried           building

constructed.            Such       clause        of        development

agreement in fact was also acted upon by the

parties, inasmuch as, a plan for multistoried

building      was        also       approved        by      Patliputra

Housing Co-operative Society on 3.5.2007 and

arrangement for loan from Housing and Urban

Development Corporation (HUDCO) was also made

wherein HUDCO had sanctioned the loan in the

month of September, 2007. There is also no

dispute that it was in terms of the aforesaid

development             agreement         that        a     plan      was

submitted          to       Patna        Regional          Development

Authority (PRDA) and PRDA had also accorded

approval of such plan on 24.12.2007. Clause-12

of the aforesaid development agreement reads

as follows:-

              "That         the   builders       will     construct
       the total super builtup floor area of the
                       3




        land owner share as detailed in schedule-
        A of this agreement within 3(Three) years
        from   the    date    of    the    sanction      of    the
        final plan of the proposed multi storied
        building/apartment/flats by the competent
        authorities with a further grace period
        of 6(Six) months, provided the delay is
        not    caused        due    to      hindrance         from
        Government bodies/natural calamities/land
        owners/defects        in    land    documents         etc.
        which may be beyond the control of the
        builders."
          3. Though           the          construction              of

multistoried building by the respondents under

the     aforementioned             agreement       was        to     be

completed by 24.12.2010, it is said that on

6.6.2008, the appellant had entered into some

sort     of    memorandum          of     understanding            with

another builder „Apana Awas Construction‟ and

pursuant       thereto,        a     separate       development

agreement was also executed by the appellant

on    16.8.2008       for     construction         of    the       same

building and the same land with the aforesaid

Apana    Niwas       Construction.         There    is    also       no

dispute between the parties that the second

development          agreement            was    executed            on

16.8.2008        without           annulling        the        first

development      agreement          of    the   appellant          with

the respondents dated 1.9.2002.
                      4




           4. It     was        at     this       stage       that    the

respondents had approached the civil court by

filing an application under Section 9 of the

Act   on     19.9.2008          wherein       after       giving      the

details of the earlier development agreement

and making further statement as with regard to

the incurring liabilities by the respondents

for completion of the multistoried building,

it was stated in paragraph no.13 and 14 of the

application        that     the        appellant         had    started

negotiating with other persons and was likely

to create third party interest in the land,

the subject matter of development agreement.

Since the paragraph nos. 13 & 14 are the only

two relevant paragraphs which were capable of

inviting an interim order under Section 9 of

the Act, they are quoted hereinbelow:-

              "13.        That the applicants state that
      when    they       have     reached         such   an    advance
      stage with the project, the opposite party,
      with    ill    motive          and    for    the   purpose     of
      mounting undue pressure for extorting more
      money    and       profit      has    started      negotiating
      with other persons and is likely to create
      third party interest in the land subject
      matter of the development agreement and has
      stopped co-operating in the proceeding of
      the project.
                   14.     That       the     intention        of    the
      opposite party has been mala fide and in
                       5




        order    to   make     undue       gain   and    profit   at
        higher amount he is out to frustrate the
        agreement with the applicant by alienating
        transferring       or encumbering          the plece      of
        land given to the applicant for development
        and it has been necessary to preserve the
        subject matter till the dispute is decided
        in arbitration."
          5. From          a     perusal          of      the     said

application         filed      by    the    respondents         before

the court below, it would be clear that not a

word was said in the said application as with

regard         to     either          the         memorandum          of

understanding          dated         6.6.2008          between    the

appellant and Apna Awas Construction or the

development agreement between the same parties

dated 16.8.2008, while making the prayer for

grant     of     interim        relief       of    the     following

nature:-

                "It is, therefore, prayed that Your
        honour may graciously be pleased to admit
        this applicant, issue notice to opposite
        party, and after hearing the parties be
        further pleased to grant interim relief
        to the applicants for preservation of the
        property      of       the     project         under    the
        development agreement and to restrain the
        opposite party from creating third party
        interest in the land subject matter of
        the development agreement, by alienating,
        transferring or encumbering, the same in
        any manner."
                          6




          6. From            the    records,        it    appears          that

when    the       said       miscellaneous          case        was       filed

before the District Judge on 19.9.2008, the

same was registered and directed to be put up

with office note before the District Judge on

22.9.2008.         On    22.9.2008,           when       the     case      was

placed       for        admission        before           the     District

Judge,       he    had        admitted        the        same     and       had

directed          for        issuance        of     notice           to    the

opposite party appellant fixing 26.9.2008 for

hearing and had transferred the case to the

court of Additional District & Sessions Judge,

FTC    IV,    Patna          for     disposal.          The     transferee

court appears to have received the record on

25.9.2008         and    had        directed        the       case    to    be

placed on the date fixed by the District Judge

i.e. 26.9.2008. On 26.9.2008, the Additional

District          Judge,       FTC      IV,       Patna         had       again

adjourned the case for hearing on 29.9.2008

and on 29.9.2008 it had only after hearing the

counsel       for        the         respondents              passed        the

impugned order relevant portion whereof reads

as follows:-

              "4.        I         perused        the     above        said
       development            agreement       and       the     documents
       produced         on    behalf    of    the        applicant.        On
       careful perusal of the clause 8, 12 and 28
                        7




     of     the     aforesaid           development           agreement
     executed          and        registered           between          the
     applicant         and       the    opposite       party       it    is
     clearly       apparent            that    there     is     eminent
     danger of the property being the subject
     matter       of       arbitration          agreement        to      be
     alienated, destroyed or its nature might be
     changed by the opposite party. Thus I find
     that the applicant has been able to satisfy
     to invoke the jurisdiction under Section of
     the Arbitration and Conciliation Act. I am
     also of the view that there is prima facie
     case    and       balance         of     convenience       in      the
     favour of the applicant.
                  5. On considering the above facts
     and circumstances I direct the applicant to
     take    steps         for initiation           of   arbitration
     proceeding            in    accordance      with     law      within
     one year and in the meantime the opposite
     party is hereby restrained from interfering
     in the work of the applicant likely to be
     done         according             to      the      development
     agreement.            The     opposite         party     is      also
     restrained            from creating         and     third      party
     interest in the property by sale, transfer,
     mortgage or any agreement with stranger."
          7. Mr.       Tara       Kant       Jha,     learned        senior

counsel appearing on behalf of the appellant

while assailing the aforesaid impugned order

has submitted that the court below has been

totally     misguided            in    exercise        of     its       power

under Section 9 of the Act, inasmuch as, it

has not even cared to look into the relevant

provision      of          development           agreement              which
                       8




itself    provide         for    adjudicating        the   dispute

between the parties through an arbitration. In

this context, he has submitted that in the

whole     of    the        application,        there       was     no

averment       that        the     respondents         had       ever

communicated its intention in writing to refer

the matter to the arbitrator and therefore,

the appellant and respondents being bound by

the terms of the agreement, the respondents

could not have been favoured with the impugned

order even by way of interim relief. He has

further    submitted            that   assuming      that    power

under Section 9 can be invoked even before the

dispute has been referred to the arbitrator,

even then such exercise of power under Section

9 has to be based on some materials and an

interim    order          cannot   be       passed   merely       for

asking. Mr. Jha has also explained that when

nothing was done by the respondents even after

a lapse of a period of almost one year from

the   date     of     approval         of    the   plan    by     the

Patliputra      Cooperative            Society     despite       full

cooperation extended by the appellant to the

respondent, the appellant in the interest of

the property and requirement of the building
                     9




in question had proceeded to execute another

development       agreement          with        M/s     Apna          Awas

Construction       on       16.8.2008          after    giving          due

intimation to the respondents. He has summed

up his submission that the court below while

passing     the     impugned            order     has     virtually

allowed    the     application            of    the     respondents

under    Section        9   of    the    Act,     by    an    interim

order     itself        and       that    too      without             even

affording    an     opportunity           of     hearing      to       the

appellant         and       its         indulgence           to         the

respondents by giving them period of grace of

one year only for enabling them to invoke the

clause      of      the          arbitration            cannot           be

countenanced in law.

          8. Mr. V. Nath, learned counsel for the

respondent no.1 and Dr. K.N. Singh, learned

senior     counsel          for     the        respondent          no.2,

however,    have        submitted         that     there          is     no

infirmity in the impugned order passed by the

court below, inasmuch as, the appellant was

not     justified           in     executing           the        second

development       agreement         on     16.8.2008          without

cancelling of the subsisting first development

agreement        with       the     respondents.             In        this
                         10




context,          Mr.    Nath        has       also          defended     the

impugned order of the court below by taking a

plea that there was no way requirement in law

that   a     party       to        this      agreement          containing

clause       of    arbitrating               cannot          seek     interim

relief     under        Section          9   of        the    Act     without

invoking the arbitration clause.

           9. In the opinion of this Court, this

appeal is fit to be allowed only on the ground

that the impugned order amounts to virtually

allowing          the        application               filed        by    the

applicant-respondents as a whole even without

hearing of the appeal, inasmuch as, for one

year which the appellant has been restrained

from       interfering              in       the        work        of    the

respondents         likely         to     be      done       according        to

their development agreement and by giving this

period of one year to the respondents only for

initiation         of        the    arbitration               proceedings.

This however is against the spirit of Section

9 of the Act, which reads as follows:-

              "9.       Interim           measures,            etc.      by
       court.- A party may, before or during
       arbitral         proceedings               or    at    any     time
       after the making of the arbitral award
       but        before           it        is        enforced          in
       accordance with Section 36, apply to a
                11




court:-
(i) for the appointment of a guardian
for a minor or a person of unsound
mind     for        the     purposes      of   arbitral
proceedings; or
(ii)     for         an     interim       measure      of
protection in respect of any of the
following matters, namely:-
(a) the preservation, interim custody
or sale of any goods which are the
subject-matter              of     the     arbitration
agreement;
(b) securing the amount in dispute in
the arbitration;
(c)     the     detention,          preservation      or
inspection          of    any    property      or   thing
which    is     the       subject-matter        of    the
dispute in arbitration, or as to which
any    question           may    arise    therein     and
authorizing for any of the aforesaid
purposes any person to enter upon any
land or building in the possession of
any party, or authorizing any samples
to be taken or any observation to be
made, or experiment to be tried, which
may be necessary or expedient for the
purpose of obtaining full information
or evidence;
(d)      interim            injunction         or    the
appointment of a receiver;
(e)     such        other       interim    measure     of
protection as may appear to the court
to be just and convenient,
          And the court shall have the
                         12




      same power for making orders as it has
      for the purpose of, and in relation
      to, any proceedings before it."
            10.          From a bare reading of Section

9 of the Act, it would be clear that only by

way   of     interim          measure      of    protection,      the

court can pass an order for the preservation

of    the    property          even     by      granting    interim

injunction but it cannot choose to enforce the

agreement         nor    it    can    in     exercise      of   power

under Section 9 pass an order which may have

the effect of permanent injunction. In other

words, an interim under Section 9 can only be

by way of interim measure of protection for

preservation            and/or    interim        custody    of    the

subject matter of the arbitration agreement in

terms of Section 9(ii)(a) of the Act. Thus

when Thus, when in the impugned order, the

court below has restrained the appellants from

interfering with the work of the respondents

likely to be done according to the development

agreement,        it     has     proceeded       to   enforce     the

development agreement between the parties. It

cannot be the scope of an order under Section

9 of the Act. Moreover, when the court below

by the impugned order has granted time limit
                        13




of one year to the respondents for invoking

arbitration clause and at the same time has

restrained the appellant from interfering in

the work of the petitioner, the same no longer

remains in the domain of an interim measure or

an    interim         injunction        as     contemplated            under

Section 9 of the Act and acquired shape of

almost a permanent injunction.

            11.         This Court in fact is dismayed,

shocked      and       surprised         as     to       how    the    court

below and from which provision of law could

grant    period         of    one       year       for     allowing        the

respondents to invoke the arbitration clause

and     initiate            the     arbitration                proceeding.

Section      9    of    the       Act    does        not       say    so   and

Section          11     of        the     Act        containing            the

provision         with       regard           to     appointment            of

arbitrators by the Court also does not lay

down    a    period          of     one       year        required         for

appointment of arbitrator. Thus, the embargo

created under the impugned order for a period

of one year was wholly impermissible in law

and against the provision of Section 9 of the

Act.    An   interim          measure         as     envisaged         under

Section 9 of the Act for protection of the
                       14




property      in      question         under      the    development

agreement of the appellant and respondents did

not require a period of one year for invoking

the arbitration clause.

          12.           That      apart,       this     Court     could

have understood that if there was a case of

such emergency though there was none as per

the averments made in the application filed by

the respondents in this case, which could have

at best directed for maintaining status quo as

with regard to the land in question being the

subject      matter        of    the     development         agreement

till service of notice and appearance of the

appellant       but     an      order     directly       restraining

the appellant for a period of one year and in

fact    till       the          initiation        of     arbitration

proceeding for the purposes of such restraint

order   for       its      being       continued        in   terms   of

Section 17 of the Act was highly undesirable

and in fact wholly beyond the scope of Section

9 of the Act. The heavens was not going to

fall    if    even         a     third    party        interest      was

created      by    the         appellant,      inasmuch       as,    the

rights of the parties even in that respect

were    well       covered          by      the       provision       of
                     15




development agreement dated 1.9.2002.

         13.        The subsequent discovery of the

respondents as with regard to the memorandum

of     understanding         dated      6.6.2008        of    the

appellant with the Apna Awas Construction and

the consequential development agreement dated

16.8.2008 cannot come to the rescue of the

impugned order wherein the court below was not

even    apprised      with     regard    to     these    facts,

inasmuch as, the court below had passed the

impugned        order          without         taking        into

consideration these facts. The respondents, in

fact were themselves unaware about the same as

is clear from the reading of their application

under Section 9 of the Act. In that view of

the matter, while this Court has only noticed

such events from the counter affidavit filed

by the respondents but then they cannot be

looked into for justifying the impugned order,

inasmuch      as,   they       were   not   the    basis      for

passing its order.

         14.        As     noted      above,    the     impugned

order    in    fact      has     virtually      allowed       the

application of the petitioner and has given an

all time or a permanent protection instead of
                      16




an    interim         measure        of     protection         as

contemplated under Section 9 of the Act which

is only by way of temporary measure in the

cases in which arbitral proceeding is yet to

commence. The scope of Section 9 in fact was

gone into by the Apex Court in the case of

Firm Ashok Traders & Anr. Vs. Gurumukh Das Saluja

& Ors. reported in 2004(3)SCC 155 wherein while

holding that the reliefs which the court may

allow to a party under clause (i) & (ii) of

Section   9    of     the    Act    flow   from       the   power

vested in the court, exercisable by reference

to contemplated, pending or completed arbitral

proceeding, it has been laid down that the

Court is conferred with the same power for

making the specified orders as it has for the

purpose of and in relation to any proceeding

before it, though the venue of the proceeding

in relation to which the power under Section 9

is   sought    to     be    exercised      is   the    Arbitral

Tribunal. The law in this regard to the scope

of order under Section 9 has been explained by

the Apex Court in the following words:-

              "17. There      are    two      other    factors
      which    are    weighing      heavily     with   us   and
      which we proceed to record. As per the law
      laid down by this Court in Sundaram Finance
                   17




Ltd. an application under Section 9 seeking
interim relief is maintainable even before
commencement of arbitral proceedings. What
does that mean? In Sundaram Finance Ltd.
itself        the Court has said: (SCC p. 488,
para 19)
                   It        is     true      that       when     an
        application under Section 9 is filed
        before           the       commencement           of     the
        arbitral proceedings, there has to be
        manifest intention on the part of the
        applicant            to    take      recourse      to    the
        arbitral proceedings.
        Section          9    permits      application         being
filed in the court before the commencement
of     the        arbitral          proceedings          but     the
provision does not give any indication of
how much before. The word "before" means,
inter alia, "ahead of; in presence or sight
of; under the consideration or cognizance
of".        The        two        events      sought       to    be
interconnected by use of the term "before"
must     have          proximity      of     relationship        by
reference         to     occurrence;         the       later   event
proximately following the preceding event
as      a     foreseeable               or        "within-sight"
certainty. The party invoking Section 9 may
not    have       actually         commenced       the    arbitral
proceedings but must be able to satisfy the
court       that       the     arbitral       proceedings       are
actually           contemplated               or        manifestly
intended (as Sundaram finance Ltd. puts it)
and are positively going to commence within
a    reasonable          time.      What     is    a    reasonable
time        will        depend       on      the       facts     and
circumstances of each case and the nature
of interim relief sought for would itself
                18




give an indication thereof. The distance of
time must not be such as would destroy the
proximity of relationship of the two events
between which it exists and elapses. The
purpose of enacting Section 9, read in the
light of the Model Law and UNCITRAL Rules
is     to      provide        "interim          measures           of
protection". The order passed by the court
should      fall      within       the    meaning          of     the
expression           "an       interim          measure           of
protection" as distinguished from an all-
time or permanent protection.
              18.          Under    the       A&C    Act,       1996,
unlike      the     predecessor       Act       of    1940,       the
Arbitral Tribunal is empowered by Section
17 of the Act to make orders amounting to
interim measures. The need for Section 9,
in spite of Section 17 having been enacted,
is     that    Section       17     would       operate          only
during        the     existence          of     the        Arbitral
Tribunal and its being functional. During
that    period,       the    power       conferred          on   the
Arbitral Tribunal under Section 17 and the
power conferred on the court under Section
9 may overlap to some extent but so far as
the    period        pre-    and    post-       the        arbitral
proceedings           is     concerned,              the        party
requiring an interim measure of protection
shall have to approach only the court. The
party       having        succeeded       in        securing       an
interim        measure        of     protection              before
arbitral proceedings cannot afford to sit
and    sleep        over    the    relief,          conveniently
forgetting          the    "proximately         contemplated"
or       "manifestly               intended"               arbitral
proceedings itself. If arbitral proceedings
are not commenced within a reasonable time
                             19




        of        an     order           under        Section           9,        the
        relationship               between           the      order          under
        Section         9        and    the     arbitral          proceedings
        would stand snapped and the relief allowed
        to the party shall cease to be an order
        made       "before"            i.e.     in        contemplation            of
        arbitral proceedings. The court approached
        by     a       party       with        an     application            under
        Section 9, is justified in asking the party
        and       being      told        how    and        when    the       party
        approaching the court proposes to commence
        the        arbitral            proceedings.              Rather,          the
        scheme         in        which        Section        9     is    placed
        obligates the court to do so. The court may
        also while passing an order under Section 9
        put the party on terms and may recall the
        order if the party commits breach of the
        terms."
             15.            There is yet another compelling

reason for this Court to interfere with the

impugned order, inasmuch as, the same is also

in clear violation of the principle of natural

justice. It has to be noted that the District

Judge        by     his          order     dated           22.9.2008           while

admitting the case had already issued notice

to the appellant before transferring it to the

Additional             District           Judge,           FTC-IV        for       its

disposal          but       the        Additional          District          Judge,

FTC-IV         without             even         making            enquiry           or

recording          the       fact        as     with        regard           to    the

service           of    notice           on         the     appellant,             had
                      20




proceeded       to   pass     the       impugned       order    which

virtually has decided the whole case filed by

the respondents. The submission of Mr. Nath

that the power under Section 9 of the Act is

akin to the power of the Court under Order

XXX1X, Rule 1 & 2 of the C.P.C., inasmuch as,

Section 9 also provides for an interim measure

of    protection      by     way    of    interim        injunction

akin Section 9(ii)(d) of the Act has to be

also appreciated in the backdrop of the three

situations as contemplated under Section 9 of

the   Act.    Such        exercise      of    power      by    way   of

interim      measure       under     Section       9     in    itself

envisages that the same can be exercised by a

court        either         before           commencement            of

arbitration proceeding or during arbitration

proceeding or even at any time after making of

the arbitral award but before its enforcement

under Section 36 of the Act.

          16.         In the opinion of this Court,

whereas Section 9(ii)(b) and (c) of the Act

would only govern the cases during pendency of

arbitrary       proceeding         or    at    any     time     after

making of the arbitral award, the provision

under   Section       9(ii)(a)(d)            and   (e)    would      be
                     21




applicable        even   before   commencement       of   the

arbitral      proceeding.     A     question,       however,

would arise that when the parties are bound by

an agreement containing arbitration clause and

one of them approaches the court for an order

under Section 9 by way of interim measure even

before     invoking      arbitration      clause      and/or

commencement of the arbitral proceedings, can

the court proceed to decide the matter even

without notice to the other party?              The answer

in fact again is found under Section 9 of the

Act itself where the court has been vested

with the same power for making orders as it

has for the purposes and in relation to any

proceeding before it. In other words as even

in   other    proceedings     including    a    proceeding

for grant of ad-interim injunction an order

cannot       be    passed    without      affording       an

opportunity of hearing to the other party, the

court even for exercise of power under Section

9(ii((a)(d( & (e) of the Act is mandatorily

required to give opportunity of hearing to the

other    party     against   whom   relief     of    interim

measure has been sought under Section 9 of the

Act.
                       22




            17.        This    aspect       of     the    matter    in

fact has been settled by the Apex Court in the

case   of     Arvind       Construction      Co.    (P)     Ltd.   Vs.

Kalinga      Mining    Corporation      &    Ors.       reported    in

2007(6)SCC 798, relevant portion whereof reads

as follows:-

                   "-----The         argument           that     the
       power      under     Section     9    of     the Act        is
       independent of the Specific Relief Act
       or that the restrictions placed by the
       Specific Relief Act cannot control the
       exercise of power under Section 9 of
       the Act cannot prima facie be accepted.
       The     reliance        placed        on     Firm       Ashok
       Traders v. Gurumukh Das Saluja in that
       behalf does not also help much, since
       this Court in that case did not answer
       that question finally but prima facie
       felt       that      the     objection            based     on
       Section        69(3)    of    the     Partnership         Act
       may not stand in the way of a party to
       an     arbitration         agreement         moving       the
       court under Section 9 of the Act. The
       power under Section 9 is conferred on
       the        District          Court.         No      special
       procedure is prescribed by the Act in
       that behalf. It is also clarified that
       the    court        entertaining       an    application
       under Section 9 of the Act shall have
       the same power for making orders as it
       has for the purpose and in relation to
       any proceedings before it. Prima facie,
             23




it appears that the general rules that
governed    the        court    while     considering
the grant of an interim injunction at
the threshold are attracted even while
dealing     with        an      application           under
Section 9 of the Act. There is also the
principle        that        when     a     power       is
conferred under a special statute and
it is conferred on an ordinary court of
the    land,          without    laying      down      any
special condition for exercise of that
power, the general rules of procedure
of that court would apply. The Act does
not prima facie purport to keep out the
provisions of the Specific Relief Act
from   consideration.           No    doubt,      a    view
that exercise of power under Section 9
of    the Act       is not      controlled        by    the
Specific Relief Act has been taken by
the    Madhya       Pradesh      High     Court.        The
power under Section 9 of the Act is not
controlled       by    order     18   Rule       5of   the
Code of Civil Procedure is a view taken
by the High Court of Bombay. But, how
far     these         decisions       are        correct,
requires       to      be      considered         in    an
appropriate         case.      Suffice      it    to    say
that on the basis of the submissions
made in this case, we are not inclined
to answer that question finally. But,
we may indicate that we are prima facie
inclined to the view that exercise of
power under Section 9 of the Act must
be based on well-recognized principles
                    24




       governing        the        grant            of       interim
       injunctions and other orders of interim
       protection       or    the     appointment               of    a
       Receiver.----"
         18.       The reliance placed by Mr. Nath

on the judgment of the Apex Court in the case

of M/s Sundaram Finance Ltd. Vs. M/s NEPC India

Ltd.   reported     in       AIR    1999       SC     565      is    also

misplaced, inasmuch as, in paragraph no.20, it

has been clarified that when an application

under Section 9 of the Act is filed before the

commencement of the arbitral proceeding, there

has to be manifest intention on the part of

the applicant to take recourse to the arbitral

proceeding      if,      at        the         time         when      the

application     under        Section       9    of       the    Act   is

filed,    the   proceedings           have          not     commenced

under Section 21 of the 1996 Act.

         19.       The       concept           of     issuance         of

notice    under     Section         21         of     the      Act    is

altogether      different           than        a        notice       for

exercise of power under Section 9 of the Act

against a party against whom interim measure

is sought by the other party. Section 21 of

the Act talks with regard to the commencement

of the arbitral proceedings and in the present
                    25




case, it is an admitted position that neither

there     was      any     written    request      by     the

respondent to the appellant to take recourse

to    arbitration       proceedings   nor   such    of   the

respondents intention could be gathered from

any averment made by them in their application

under Section 9 of the Act before rushing to

the court for grant of interim protection. In

the    entire   petition     filed    before    the     court

below under Section 9 of the Act, there is no

whisper     that     the     respondents     had      either

invoked      the     arbitration      clause       of     the

arbitration or there was such an intention on

their part. Mr. Nath in fact very fairly had

also    conceded     the    absence   of    such   written

notice by the respondent to the appellant. He,

however, has tried to place his reliance on

paragraph no.16 of the application to contend

that the intention of the respondents as with

regard to invoking arbitration clause can be

inferred from the same. In fairness to the

aforesaid submission of Mr. Nath, it would be

necessary to also quote paragraph no.16 of the

application which reads as follows:-

             "16. That the applicants persuaded the
        opposite party to resolve the dispute through
                      26




       arbitration        but    some    how    or       other,      he    is
       avoiding the same. The applicants are going
       to take steps for initiation of arbitration
       proceeding and appointment of Arbitrator, so
       that the dispute be resolved amicably."


         20.            From reading of the aforesaid

paragraph,         it     would         be     clear         that         the

initiation of arbitration proceeding can only

be made when a request for the dispute to be

referred      to    arbitration          is    received             by    the

respondents        and     therefore,          such      request          for

reference      to       the     arbitrator         has       to     be    in

writing which is being capable to be received

by the another party. This Court, therefore,

is    satisfied      that       the     respondents            had       even

before    communicating            the       nature       of      dispute

muchless their intention to refer the matter

to the arbitrator had taken a hasty step by

filing an application under Section 9 of the

Act.    The   manifest          intention          of    a     party      of

taking recourse to arbitration in fact can be

gathered      only       when     there       is     a    dispute         in

existence and a demand by a party to the other

for     reference          of     the         dispute          to         the

arbitrator. In the present case, when not a

word    was   said        by    the     respondents            in    their
                     27




application under Section 9 of the Act as with

regard      to     the     execution          of     either        the

memorandum of understanding or the agreement

of    the        appellant       with        the         Apna     Awas

Construction,           there    was     in    fact        also     no

dispute     in     existence      and    as        quoted        above,

everything was only speculative in nature on

the basis of which the respondents had made

only on evasive statement as with regard to

starting     negotiation         by    the     appellant           with

other unknown persons for creating third party

interest.        Such      speculative         statement           was

therefore not capable of being translated into

an impugned order of the nature which has been

passed in this case by the court below.

          21.        That       apart,    when           this     Court

would find that the court below did not even

look into the aspect that the notice issued to

the appellants in the application filed by the

respondents        under     Section      9        had     not    been

served    and     consequently,         the    impugned           order

was   passed       by    acting       upon     the        one     sided

version of the respondent and without hearing

the   appellants,           it    would        find        it     very

difficult to sustain the impugned order. It is
                      28




quite elementary that no court would pass an

order prejudicial to the interest of a party

or    a    person    without       at        least    affording    an

opportunity of hearing. In the present case,

the       fact    that    the     whole       application        under

Section 9 was decided within a span of ten

days from the date of its being admitted by

itself would be demonstrative of the fact that

the respondents have procured the order from

the court without ensuring service of notice

on the appellants.

            22.          Thus on the basis of aforesaid

factual       and    legal       analysis,          this   Court   is

satisfied with the impugned order which has

been passed even without hearing the appellant

imposing more or less a permanent nature of

restraint         against       him,    cannot       be    sustained

being       in    excess     of        and     contrary     to     the

provisions of Section 9 of the Act.

            23.          At this stage, counsel for the

respondents have submitted that a request case

no. 4/2009 has been also recently filed by the

respondents         in    this    Court        in    the   month   of

March, 2009 for appointment of arbitrator in

terms of Section 11 of the Act and therefore
                       29




the impugned order should not be interfered

with till the disposal of the Request Case. In

the considered opinion of this Court while it

is not called upon to say any thing about the

merit    of    such        claim      of   the    respondents      in

pressing their application under Section 11 of

the    Act    in     the    aforesaid        request       case   no.

4/2009,       this    much        becomes        clear    that     the

respondents          have        invoked      the        arbitration

clause as with regard to                   the dispute in hand

relating      to     appellant         entering     into     another

development           agreement            with      Apna         Awas

Construction on 16.8.2008 which may amount to

termination of the agreement of the appellant

with the respondents. The respondents in their

application under Section 9 of the Act stated

that they had advanced certain money to the

appellant as also they had collected certain

money by way of advance from third parties for

sale    of    flats        in   the    proposed      multistoried

buildings. They had also stated that building

materials          have         been       collected       by      the

respondents for making construction.

          24.         Considering           all    these     aspects

of the matter, it would be necessary for this
                    30




Court     to     provide       some       sort   of        interim

protection       till    the      final    decision        on    the

pending request case no. 4 of 2009 is taken by

this Court, inasmuch as, if an arbitrator is

appointed on the order of this Court, he will

have thereafter sufficient powers to pass any

interim order under Section 17 of the Act. On

the     other     hand,      if     the     prayer         of    the

respondents for appointment of arbitrator is

rejected, he may take recourse under ordinary

law for claiming damage against the appellant.

          25.       This Court in the light of the

aforesaid       admitted     facts    as    also      by    taking

into account the judgment of the Kolkata High

Court in the case of Partha Sarathi Ghosh Vs.

Maa   Construction       &   Ors.   reported     in      AIR     2008

Kolkata 171 having almost similar facts as with

regard     to     situation         arising        out      of     a

development agreement between the owner of the

land and the builder, would direct the parties

to maintain status quo till the disposal of

request case no. 4 of 2009. In the aforesaid

period,        neither       the     appellant        nor        the

respondents shall change the physical nature

of the land in question in any manner which is
                                     31




                  the     subject    matter      of     their     development

                  agreement dated 1.9.2002.

                            26.      With         the       aforementioned

                  observations      and    directions,     this    appeal    is

                  allowed and the impugned order passed by the

                  court    below    is    set   aside.   There     would    be,

                  however, no order as to costs.


Patna High Court                                   (Mihir Kumar Jha, J.)
Dated 16th April, 2009

AFR/R/Rishi