Union of India - Section

Section 20 in The Central Electricity Regulatory Commission (Terms And Conditions For Tariff Determination From Renewable Energy Sources) Regulations, 2009

20. Late payment surcharge

.-In case the payment of any bill for charges payable under these regulations is delayed beyond a period of 60 days from the date of billing, a late payment surcharge at the rate of 1.25% per month shall be levied by the generating company.