State of Maharashtra - Subsection

Section 7(7) in Maharashtra Electricity Regulatory Commission (Transmission Open Access) Regulations, 2005

7.2Where two or more applications are received on the same day an application for longer duration shall take precedence over an application for a shorter duration of access to the intra-State transmission system:Provided that two or more applications for the same duration of access received on the same day shall be treated pari passu for allotment of transmission capacity rights and in case of insufficient available capacity to accommodate all applications, the applicants shall be allotted a pro rata share in the available capacity proportionate to the capacities applied for.