Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 0]

Calcutta High Court

Coal India Ltd vs M/S. Paul Builders on 1 December, 2016

Author: Soumen Sen

Bench: Soumen Sen

                                ORDER SHEET
                              AP No.1385 of 2013
                      IN THE HIGH COURT AT CALCUTTA
                       Ordinary Original Civil Jurisdiction
                                ORIGINAL SIDE


                               COAL INDIA LTD.
                                    Versus
                             M/S. PAUL BUILDERS

  BEFORE:
  The Hon'ble JUSTICE SOUMEN SEN
  Date : 1st December, 2016.

                                                                     Appearance:
                                                       Mr. Abhrajit Mitra, Sr. Adv.
                                                               Mr. A. Mitra, Adv.
                                                                Mr. P. Basu, Adv.
                                                              Mr. S. Prasad, Adv.
                                                                Mr. P. Bose, Adv,

                                                       Mr. Goutam Brahma, Adv.
                                                         Mrs. Pompa Saha, Adv.
                                                             Mr. Arijit Dey, Adv.



      The Court : The respondent was awarded a contract for construction of B

type, C-1 type and Sub-Station building at VIP Road Housing Complex. The claimant submitted his offer of Rs.11576634.00/- for the aforesaid job which was revised to Rs.11363421.80/-. The petitioner issued the letter of intent on 20th February, 1987 for the said work having an aggregate value of Rs.11249787.59/- after allowing 1% rebate on all items on the revised total quoted amount of Rs.11363421.80/-. The dispute between the parties arose after the respondent had received payment under the final bill.

The respondent alleged that a sum of Rs.640991.85/- was received under duress as the petitioner was not willing to release the said payment unless the 2 respondent signed four pre-receipted documents showing acceptance of the said amounts in full and final settlement of its claim under the work order.

It is alleged that the respondent was made to sign on dotted lines inasmuch as the petitioner being in a position to dominate the Will of the respondent compelled the respondent to accept the said amount, notwithstanding the fact that other legitimate claims of the petitioner, although pending prior to the settlement of the final bill were not considered.

The arbitrator has considered the matter on merits and on consideration of the evidence and on examination of oral and documentary evidence as well as pleadings has passed an award in favour of the respondent under the following heads:

Sl. No.                              Item                                 Award
1.           Claim for compensation for price hike of                    Rs.667693.76
             materials and increase in the labour wages -
             Rs.667693.76 (Para 9.1.1)
2.           Claim for losses suffered consequent upon the                RS.16100.00
             failures of the Respondent to supply cement at
             material time. Rs.16100.00 (Para 9.1.2)
3.           Claim for losses suffered for making inordinate              Rs.29200.00
             delay by the Respondent in allowing the
             Claimant for casting RCC slabs. Rs.29200.00
             (Para 9.1.3)
4.           Claim for infructuous expenditures incurred on              Rs.221133.33
             off-site & on-site establishments for execution of
             the works in the extended period of completion.
             Rs.221133.33 (Para 9.1.4)
5.           Claim for interest for blockage of working                  Rs.203670.87
             capitals of the Claimant from time to time by the
             Respondent. Rs.203670.87 (Para 9.1.5(1)(a))
6.           Claim for interest on Rs.1137797.96 with effect       At the rate of 8
             from 03.10.1991 to the date of entering on the        percent
             reference by the Arbitrator on 06.10.1993 (Para
             9.1.5(1)(b))
7.           Claim for interest at the rate of 18% (eighteen       As will accrue at
             percent) per annum on the sum to be awarded           the   rate  of  8
             with effect from the date of making and               percent
             publishing of the award to the date of payment
                                          3


           or Decree of the Court, whichever is earlier.
           (Para 9.1.5(1)(c))
8.         Claim for cost of Arbitration                             Rs.200000.00


Mr. Abhrajit Mitra, learned senior counsel appearing on behalf of the petitioner submits that the said award suffers from non-application of mind inasmuch as some of the claims are clearly barred under the contract and the arbitrator being a creature of the agreement cannot travel beyond the terms of the contract.

The main challenge to the said award is in respect of allowing a claim on account of escalation.

Mr. Mitra has referred to Clause 3.02 of the letter of intent which reads "no claim on account of escalation on material and labour will be allowed" and submits that in view of such clear prohibition the arbitrator could not have allowed a claim on account of escalation for a sum of Rs.667693.76/- . Mr. Mitra has also argued that there is an accord and satisfaction between the parties which would be evident from the conduct of the respondent in accepting the said sum of Rs. 640991.85/- in full and final settlement and, accordingly, the arbitrator could not have allowed any of the claims of the petitioners.

Mr. Mitra has also referred to the decision of the Hon'ble Supreme Court in 'M/s. Rashtriya Chemicals & Fertilizers Ltd. vs. M/s. Chowgule Brothers & Ors.' reported at AIR 2010 Supreme Court 3543, 'Videsh Sanchar Nigam Ltd. vs. Shapoorji Pallonji &Company Ltd.' reported at (2008)1 CHN 721 and Union of India vs. Raman Iron Foundry reported at AIR 1974 SC 1265 in support of his submission that even if there is a breach of contract, the damage may not follow automatically and the claimant would be required to lead some 4 evidence of damage sustained by him by reason of such breach. In short, it is submitted that the arbitrator would be required to quantify the damage, which according to Mr. Mitra, the arbitrator has failed to do and thereby the awarding of damage in favour of the petitioner is based on no evidence.

The learned counsel appearing on behalf of the respondent on the other hand has referred to the various documents forming part of the materials which the arbitrator had considered including the letter dated 20th November, 1991 which goes to show that even at the time when the final bill was being processed certain issues had remain outstanding which, inter alia, included escalation.

The learned counsel has also referred to a letter dated 2nd January, 1987 in which the respondent has deferred settling of the claim with regard to shuttering works which were required to be done as the earlier contractor appears to have abandoned the work and there were certain defects which were required to be removed. These apparently were not taken into consideration in the final bill.

The final bill should be final in all respect. There cannot be any dispute that the so-called final bill does not take into consideration the claim on account of escalation and shuttering works as the petitioner has postponed all such claims to be considered at a later time. The concept of accord and satisfaction has been lucidly explained by the Supreme Court in National Insurance Co. Ltd. Vs. Boghara Polyfab (P) Ltd. reported at (2009) 1 SCC 267 in Paragraph 10 of the said decision which reads:-

"10. Where one of the parties to the contract issues a full and final discharge voucher (or no due certificate as the case may be) confirming that he has received the payment in full and final satisfaction of all claims, and he has no outstanding claim, that amounts to discharge of 5 the contract by acceptance of performance and the party issuing the discharge voucher/certificate cannot thereafter make any fresh claim or revive any settled claim. Nor can he seek reference to arbitration in respect of any claim. When we refer to a discharge of contract by an agreement signed by both parties or by execution of a full and final discharge voucher/receipt by one of the parties, we refer to an agreement or discharge voucher which is validly and voluntarily executed. If the party who has executed the discharge agreement or discharge voucher, alleges that the execution of such discharge agreement or voucher was on account of fraud/coercion/undue influence practiced by the other party and is able to establish the same, then obviously the discharge of the contract by such agreement/voucher is rendered void and cannot be acted upon. Consequently, any dispute raised by such party would be arbitrable."

In Chairman and MD, NTPC Ltd. Vs. Reshmi Constructions, Builders & Contracotrs reported at (2004) 2 SCC 663 this aspect of the matter was considered and the Hon'ble Supreme Court has dealt with the matter in Paragraphs 27, 28 and 29 report wherein the Supreme Court held:-

"Necessitas non habet legem is an age-old maxim which means necessity knows no law. A person may sometimes have to succumb to the pressure of the other party to the bargain, who is in a stronger position. Although it may not be strictly in place but the court cannot shut its eyes to the ground reality that in a case where a contractor has made a huge investment, he cannot afford not to take from the employer the amount due under the bills, for various reasons, which may include discharge of his liability towards banks, financial institutions and other persons. In such a situation, public sector undertakings would have an upper hand. They would not ordinarily release the money unless a "No-Demand Certificate" is signed. Each case, therefore, is required to be considered on its own facts. A case, where a party has had to succumb to the pressure of the other party 6 to the bargain who is in a stronger position, has to be made out and proved before the arbitrator for obtaining an award. Even correspondences marked as "without prejudice" may have to be interpreted differently in different situations."

Moreover, it is not the case of the petitioner that while accepting the final bill, the respondent had unequivocally stated that he would not raise any further claim. In absence of such a declaration coupled with the fact that the final bill did not take into consideration the other claims which the petitioner was obliged to consider and had agreed to consider in various correspondence. It cannot be contended that the respondent is estopped or precluded from raising any claim. (See Bharat Coking Coal Ltd. Vs. Annapurna Construction; (2003) 8 SCC

154) In Asian Techs Ltd. Vs. Union of India & Ors. reported at (2009) 10 SCC 354 the Hon'ble Supreme Court held that even in the case of issuance of full and final discharge/settlement voucher/no-dues certificate the arbitrator or Court can go into the question whether the liability has been satisfied or not.

On the issue of accord and satisfaction the arbitrator has discussed the issue in detail and the factors that were taken into consideration in my opinion does not call for any further investigation. The arbitrator is the master of his own proceeding and the final authority on facts. This Court is not exercising the appellate jurisdiction nor could re-appreciate the evidence unless it appears to the Court that it is manifestly perverse and it shocks the conscience of the Court.

A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be lied upon when he delivers his arbitral award. Thus, an award based on little 7 evidence or on evidence which does not measure up in quality to a trained legal mind would not be invalid on this score. Once it is found that the arbitrators approach is not arbitrator or capricious, and then he is the last word on facts.

The arbitrator has given detail reason for not accepting the argument of the petitioner that the acceptances of a sum of Rs.640991.85/- is not full and final settlement of claims and cannot discharge the petitioner from its liability to make payment.

The argument of Mr. Mitra that the escalation clause would continue even for the extended period of almost 10 months is not acceptable and, in my view, has correctly been rejected by the arbitrator. The said clause only operates during the existence of the contract. The contract could not be completed within a period of 18 months. The petitioner extended the said contract without imposing any penalty. The contractor agreed to carry out the balance work during the extended period on a clear representation that such extension of time would not be considered to be sufficient consideration for execution of the work beyond the stipulated period of completion and reserved its right to claim damages for the extended period which respondent appears to have accepted. There cannot be any dispute that there was a delay and finally the work was completed on 30th June 1989 instead of 22nd September 1988. The materials disclosed before the arbitrator clearly show that the petitioner was responsible for the delay. The contractor after 18 months had an option to quit and claim compensation or complete the work on terms and conditions clearly spelt out for completing the balance work. The contractor, on a clear representation made by the petitioner that they would be compensated for the work during the period of 8 extension, had completed the job and, accordingly, in my view, is entitled to escalation and such claim on account of escalation could not be denied by referring to the clause in the tender which can only operate during the period of the contract and not for the extended period. There cannot be any dispute that there has been prolongation of the work beyond original contractual stipulated period.

The question essentially is the quantification of compensation, if any, payable to the contractor by reason of delay in performance of the contract. This aspect of the matter was considered in General Manager, Northern Railway Vs. Sarvesh Chopra reported at (2002) 4 SCC 45 in paragraph 15 which reads:-

"15. In our country question of delay in performance of the contract is governed by Sections 55 and 56 of the Indian Contract Act, 1872. If there is an abnormal rise in prices of material and labour, it may frustrate the contract and then the innocent party need not perform the contract. So also, if time is of the essence of the contract, failure of the employer to perform a mutual obligation would enable the contractor to avoid the contract as the contract becomes voidable at his option, where time is "of the essence" of an obligation. Chitty on Contracts (28th Edn., 1999 at p.1106, para 22-015) states:
"a failure to perform by the stipulated time will entitle the innocent party to (a) terminate performance of the contract and thereby put an end to all the primary obligations of both parties remaining unperformed; and (b) claim damages from the contract-breaker on the basis that he has committed a fundamental breach of the contract ('a breach going to the root of the contract') depriving the innocent party of the benefit of the contract ('damages for loss of the whole transaction')".

In this regard, it would also be fruitful to refer to the observation of Lord Ackner in Fercometal SARL (supra) with regard to the innocent party's option in 9 such a situation. The observation made at page 747 of the said report which reads:-

"When one party wrongly refuses to perform obligations, this will not automatically bring the contract to an end. The innocent party has an option. He may either accept the wrongful repudiation as determining the contract and sue for damages or he may ignore or reject the attempt to determine the contract and affirm its continued existence. Cockburn CJ in Frost v Knight (1872) LR7 Ex Ch III at 112-113, [1861-73] All ER Rep 22 I at 223-224 put the matter thus:
"The law with reference to a contract to be performed at a future time, where the party bound to performance announces prior to the time his intention not to perform it, as established by the cases of Hochster v. De la Tour (1853) 2 E & B 678, [1843-60] All ER rep 12) and The Danube and Black Sea Co. v. Xenox (1863) 13 CBNS 825, 143 ER 325) on the one hand, and Avery v. Bowden (1855) 5 E & B 714, 119 ER 647), Reid v. Hoskins (1856) 6 E & B 953, 119 ER 1119), and Barwick v. Buba (1857) 2 CBNS 563, 140 ER 536) on the other, may be thus stated. The promise, if he pleases, may treat the notice of intention as inoperative, and await the time when the contract is to be executed, and then hold the other party responsible for all the consequences of non-performance; but in that case he keeps the contract alive for the benefit of the other party as well as his own; he remains subject to all his own obligations and liabilities under it, and enables the other party not only to complete the contract, if so advised, notwithstanding his previous repudiation of it, but also to take advantage of any supervening circumstance which would justify him in declining to complete it. On the other hand, the promise may, if he thinks proper, treat the repudiation of the other party as a wrongful putting an end to the contract, and may at once bring his action as on a breach of it; and in such action he will be entitled to such damages as would have arisen from the non-performance of the contract at the appointed time, subject, however, to abatement in respect of any 10 circumstances which may have afforded him the means of mitigating his loss.' This passage was adopted by Cotton LJ in Johnstone v Milling (1886) 16 QBD 460 at 470. In that case Lord Esher MR described the situation thus (at
467):-
'...a renunciation of a contract or, in other words, a total refusal to perform it by one party before the time for performance arrives, does not, by itself, amount to a breach of contract but may be so acted upon and adopted by the other party as a rescission of a contract as to give an immediate right of action. When one party assumes to renounce the contract, that is, by anticipation refuses to perform it, he thereby, so far as he is concerned, declares his intention then and there to rescind the contract... The other party may adopt such renunciation of the contract by so acting upon it as in effect to declare that he too treats the contract as at an end, except for purpose of bringing an action upon it for the damages sustained by him in consequences of such renunciation'.
The petitioner was put to notice of the breach and thereafter on the request of the petitioner, the respondent commenced work. The respondent reserved its right to claim compensation.
The damage is a compensation for the injury sustained that some of money to be given for reparation of damages suffered should be, as nearly as possible be the sum which will put to injured party in the same position as he would have been if he had not sustained the wrong for which he is getting the damages. (B.R. Herman & Mohatta v. Asiatic Steam Navigation Co. Ltd., AIR 1941 Sind 146) Where the work was completed beyond the stipulated date of completion on account of delay caused by the Department, consequential effects of delay have to be to the account of the Department. The court has to assess damages as best 11 as it could on the materials available and would not decline to assume that merely because the claimant could not adduce the best evidence. Even in a case where nominal damages are only to be awarded, the extent of the sum should be assumed with reference to the facts and circumstances involved. The general principle to be borne in mind that the injured may be put in the same position as the he would have been if he had not sustained the wrong.
A Division Bench judgment of this Court in State of West Bengal & Anr.
Vs. M/s. N. Bhakat & Co. & Anr. being A.P.O. No.241 of 2012 with A.P. No.435 of 2008 reported at MANU/WB/0894/2012, relying upon P.M. Paul (supra) considered escalation clauses which are:-
"(I) No claim for idle labour will be entertained under any circumstances.

42. No escalation of rate within the period of execution of the work is admissible".

Clause -7.

".....It should be clearly understood that no claim whatsoever shall be entertained by the Government on account of delay in supplying materials".

The Division Bench relying upon P.M. Paul (supra) and General Manager, Northern Railways (supra) held that those clauses would not absolve the State from their liability to pay damage due to their fault in delaying the process of work. In the former case the Hon'ble Division Bench observed that escalation is a normal incident arising out of gap of time in this inflationary age in performing any contract. The Arbitrator has held that there was delay. The Arbitrator found that it was evident that there was escalation and, therefore, he came to the conclusion that it was reasonable to allow the claim on account of price escalation. This was a matter, which was within the jurisdiction of the 12 Arbitrator. Hence, the Arbitrator had not mis-conducted in awarding the said amount as he has done.

The arbitrator is a Judge chosen by the parties and his decision is final. It is well-settled that the Court is precluded from reappraising the evidence. Even in a case where the award contains reasons, the interference therewith would still be not available within the jurisdiction of the Court unless, of course, the reasons are totally perverse or the judgment is based on a wrong proposition of law or the arbitrator exceeds the terms of the agreement or passes an award in absence of any evidence. An error apparent on the face of records would not imply closer scrutiny of the merits of documents and materials on record. Once it is found that the view of the arbitrator is plausible one, the Court will refrain itself from interfering. The said proposition can be found in Bharat Coking Coal Ltd. vs. L.K. Ahuja reported at (2004) 5 SCC 109 and in State of U.P. Vs. Allied Constructions reported at (2003) 7 SCC 396 and followed in subsequent decisions.

The Court will not judge the reasonableness of a particular interpretation accorded by the arbitrator to the terms of the contract. Even an error in interpretation, unless patently illegal, will only amount to an error within the jurisdiction of the arbitrator.

In Bharat Coking Coal Ltd. (supra) the Hon'ble Supreme Court observed as follows:-

"11. There are limitations upon the scope of interference in awards passed by an arbitrator. When the arbitrator has applied his mind to the pleadings, the evidence adduced before him and the terms of the contract, there is no scope for the court to reappraise the matter as if 13 this were an appeal and even if two views are possible, the view taken by the arbitrator would prevail. So long as an award made by an arbitrator can be said to be one by a reasonable person no interference is called for. However, in cases where an arbitrator exceeds the terms of agreement or passes an award in the absence of any evidence, which is apparent on the face of the award, the same could be set aside."

In KV Mohd. Zakir v. Regional Sports Centre reported at AIR 2009 SC (Supp) 2517 it held that the courts should not interfere unless reasons given are outrageous in their defiance of logic or if the arbitrator has acted beyond his/her jurisdiction.

In P.R. Shah Shares & Stock Brothers v. M/s. B.H.H. Securities (P) Ltd. reported at 2012 (1) SCC 594 it states that a court does not sit in appeal over the award of an arbitral tribunal by re-assessing or re-approaching the evidence. An award can be challenged only on the grounds mentioned in S.34(2) of the Act.

The claimant has produced evidence before the arbitrator with regard to escalation. Primary books were produced. There has been no cross-examination on such documents. The petitioner is unable to place any material to show that evidence of the respondnt in this regard was demolished as questioned. The only defence was clause no.3.02 of the tender. In absence of any effective cross- examination coupled with oral and documentary evidence the award for escalation for a sum of Rs.6,67,693.76 cannot be questioned in this proceeding. Similarly, the claim for losses suffered due to non-supply of cement for a sum of Rs.16,100/- cannot be disputed. The third claim was on account of losses 14 suffered due to inordinate delay by the petitioner in allowing casting of RCC slabs.

The arbitrator considered the materials on record and found that the claimant made representation for payment towards loss suffered for holes made in the shuttering planks and disturbing the reinforcement works (as completed by the respondent contractor) by the electrical contractor of the Department, for cleaning and disposal of the chased materials and for relaying the reinforcement after completion of the connected electrical works. The petitioner had clarified that damage cost if payable will be settled considering several factors after completion of the structural work. Even though the petitioner had assured to consider, the same was overlooked when claimant had established its claim. The contractors engaged to lay the conduits for concealed wiring and concealed tele- cables delayed in their performance. In the process the slab casting was delayed and claimant had to incur damage. The arbitrator considered the evidence produced regarding damage to the shuttering materials, clearing the refugees generated by the electrical contractor, delay in laying the slab and allowed the said claim for a sum of Rs.29,200/-. The petitioner agreed to have the said issue addressed on completion of the work which appears to have not been considered at the time of preparation of the final bill. In my view, the arbitrator was justified in allowing the said claim. However, Claim No.4 which relates to expenditure incurred for off-site and on-site establishment, in my view, it is covered in Claim Nos. 1 and 2 and the same is accordingly disallowed.

Mr. Mitra has produced before this Court a detailed chart showing payments. Mr. Mitra cannot dispute and does not dispute that Rs.6,40,991.85 15 was paid after 19 months when the said amount was due and payable but would contend that payment was released after six months from the date of submission of final bill. Taking into consideration the delays made earlier as well as the fact that the petitioner was required to pay interest @ 17% on the borrowed capital, in my view, the respondent would be entitled to interest @ 17% on Rs.6.40 lakh for a period of two years.

The cost of Rs.2 lacs being realistic is upheld. In fact this claim has not been seriously disputed.

The modified award shall carry interest @ 10% per annum from the date of reference till this date and shall carry future interest @ 18% per annum. However, in the event the petitioner pays the awarded sum as modified by this order within a period of thirty days along with Rs. 2 lacs as consolidated amount towards interest to the respondent, the petitioner would not be required to pay interest payable during reference and post award stage.

AP No. 1385 of 2013 accordingly stands disposed of.

(SOUMEN SEN, J.) B.Pal/sp/S.kumar