Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 5, Cited by 1]

Delhi High Court

Larsen And Toubro Limited vs Punatsangchhu-1 Hydroelectric ... on 11 December, 2020

Author: C. Hari Shankar

Bench: C. Hari Shankar

                            $~10
                            *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                  Decided on : 11th December, 2020
                            +      ARB.P. 461/2020
                                   LARSEN AND TOUBRO LIMITED               ..... Petitioner
                                                   Through: Mr. Gourab Banerji, Sr.
                                                            Advocate with Mr. Ananya
                                                            Kumar, Mr. Rajat Joneja and
                                                            Mr. Kartikey Gupta, Advs.

                                                       Versus


                                   PUNATSANGCHHU-1 HYDROELECTRIC
                                   PROJECT AUTHORITY                    ..... Respondent
                                                Through: Mr. Bharat Singh, Adv.

                                   CORAM:
                                   HON' BLE MR. J USTICE C .HARI SHANKAR

                                                       J UDGEMENT (ORAL)
                                   %                      11.12.2020

                                                     (Video-Conferencing)


                            1.     This petition, at the instance of the petitioner M/s. Larsen and
                            Toubro Limited, calls on this Court, to appoint an arbitrator on behalf
                            of the respondent Punatsangchhu-1 Hydroelectric Project Authority,
                            so that the arbitrator appointed by the petitioner, and the arbitrator thus
                            appointed by this Court on behalf of the respondent, could appoint a
                            presiding arbitrator, and the Arbitral Tribunal, so constituted, could
                            proceed to arbitrate on the dispute between the parties.


                            2.     Mr. Bharat Singh, learned counsel for the respondent, very
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                              Page 1 of 22
Signing Date:15.12.2020
20:44:02
                             fairly states that his client does not question the existence of an
                            arbitrable dispute between the parties, or the necessity to refer the
                            dispute to arbitration. He, however, submits that the petition is not
                            maintainable before this Court, under Section 11(6) of the Arbitration
                            and Conciliation Act, 1996 (hereinafter referred to as "1996 Act"), but
                            that the petitioner would have to approach the High Court of Thimpu,
                            Bhutan.


                            3.    A fasciculus of the dispute. A contract was executed between
                            the petitioner and the respondent on 14th April, 2009. The respondent
                            was required by the contract, to execute work relating to the
                            construction of diversion tunnel, dam, intake and de-silting
                            arrangement,       including     hydro-mechanical        works       of   the
                            Punatsangchhu-I Hydroelectric Project, located in the Wangdue
                            Phodrang District of Bhutan. The averments in the petition, setting
                            out the dispute with the respondent, may, without prejudice to the
                            right of the respondent to question the correctness thereof, be
                            reproduced thus:
                                  "(i)   The Respondent invited bids for the Construction of
                                  Diversion Tunnel, Dam, Intake and Desilting Arrangement,
                                  including Hydro-Mechanical works of the Punatsangchhu-I
                                  Hydroelectric Project (1200 MW), located in Wangdue
                                  Phodrang District of Bhutan ("Project Works").

                                  (ii)   The Petitioner submitted its bid. Upon evaluation of
                                  the techno-commercial and the price bids submitted by
                                  various bidders, the Respondent found the Petitioner's bid to
                                  be the most qualified. Accordingly, by way of a Letter of
                                  Award dated 27.03.2009 ("LoA"), the Petitioner was awarded
                                  the Project Works by the Respondent.

                                  (iii)   Subsequently, the parties entered into the Contract.
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                Page 2 of 22
Signing Date:15.12.2020
20:44:02
                                   (iv) Under the Contract, the Petitioner was required to carry
                                  out the Project Works on an item rate basis. The agreed
                                  contract price was INR 1245,51,73,905/- (Rupees Twelve
                                  Hundred Forty-Five Crore Fifty-One Lakh Seventy-Three
                                  Thousand Nine Hundred and Five only).

                                  (v)    In terms of Clause 43 of the Contract, the Petitioner
                                  was required to complete the Project Works within a period of
                                  66 months from the 30th date of issue of the LoA. The
                                  commencement date of the Project works was 26.04.2009 and
                                  the scheduled completion date was 26.10.2014.

                                  (vi) In addition to the overall completion date, the Contract
                                  stipulated certain Intermediate Milestones ("Intermediate
                                  Milestones"), which were agreed to in the construction
                                  programme in terms of Clause 14(i) of the Contract ("Work
                                  Programme").

                                  (vii) Upon issuance of the LoA, Petitioner duly mobilized the
                                  required resources for completion of the work within the
                                  agreed timelines. However, right from inception, the Project
                                  Works were delayed on account of multiple variation orders
                                  issued by the Respondent. These variation orders resulted in
                                  an increased scope of work, substantially beyond what was
                                  originally agreed by the parties.

                                  (viii) As a consequence, the timeline for achievement of the
                                  intermediate milestones was also impacted. Acknowledging
                                  the effect of the variation orders, the Respondent revised the
                                  duration for achievement of Milestone-l and the completion
                                  date for the said milestone was extended from October 2010
                                  to November 2011. The Petitioner achieved Milestone-l, in
                                  terms of the revised schedule.

                                  (ix) In terms of the requirements of the Contract, Petitioner
                                  also mobilized resources and carried out the various
                                  preparatory works required for dam concreting (forming part
                                  of Milestone-2). The Petitioner mobilized and deployed a
                                  substantial number of resources, including specialized site-
                                  specific equipment, to be able to achieve the average
                                  excavation progress required as per the agreed Work
                                  Programme.

                                  (x)   Though the Petitioner was diligently executing the
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                              Page 3 of 22
Signing Date:15.12.2020
20:44:02
                                   work as required, in July 2013 there was a slope failure on the
                                  right bank of the river. As a consequence, the right bank
                                  worksite became unavailable for excavation and / or
                                  concreting of the dam. The dam excavation work was brought
                                  to a halt and all the resources deployed by the Petitioner for
                                  excavation works, as well as the concreting equipment, were
                                  rendered idle.

                                  (xi) Acknowledging the slope failure that had taken place
                                  in July 2013, as well as the consequent non-availability of the
                                  worksite, the Engineer-in Charge issued variation orders in
                                  September 2013 for right bank stabilization works, in order to
                                  make the site available for excavation and concreting activity.

                                  (xii) The Petitioner carried out the additional work required
                                  in terms of the variation orders issued by the Engineer-in-
                                  Charge. Thereafter, in June 2014 some portion of the
                                  excavation work was re-started at the right bank, albeit in a
                                  restricted manner. However, the concreting work could not be
                                  started.

                                  (xiii) It was, however, found that the variation
                                  orders/remedial measures directed by the Engineer-in-Charge
                                  were insufficient to deal with the issue of slope failure,
                                  therefore, the excavation works at the dam pit could also not
                                  be continued after January 2015.

                                  (xiv) Based on further variation orders issued by the
                                  Engineer-In-Charge, a second phase of stabilization work was
                                  started by the Petitioner in the month of June 2015. However,
                                  even before the stabilization work could be completed and
                                  excavation and concreting work could commence, there was
                                  another right bank slope failure in August 2016, in an area
                                  where additional stabilization measures had not been carried
                                  out.

                                  (xv) Thereafter, even though further stabilization measures
                                  were ordered and executed, the Respondent could not arrive at
                                  a solution to address the slope failure issue. As a result, work
                                  at the right bank was completely suspended by the Engineer-
                                  in-Charge from May 2017 to September 2017, due to rock
                                  movement. While the excavation work resumed in October
                                  2017, it progressed at a very slow pace since rock movement
                                  at the right bank had not stopped.
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                               Page 4 of 22
Signing Date:15.12.2020
20:44:02
                                   (xvi) The Petitioner was also instructed to carry out
                                  additional cable anchors at different elevations of right bank
                                  which were subsequently suspended or abandoned midway at
                                  a few locations.

                                  (xvii) In December 2018, the Petitioner was instructed to off-
                                  load the mass that had slid in August L016. While the off-
                                  loading activity was being carried out, on 22 January 2019
                                  reactivation (slope failure) of the August 2016 slide took
                                  place at right bank.

                                  (xviii) The excavation works have come to a complete
                                  standstill since the last major slope failure that occurred in
                                  January 2019.

                                  (xix) Effectively, therefore, the Respondent has been unable
                                  to provide the Petitioner effective access to the right bank
                                  worksite, for both excavation and concreting works, right
                                  from 2013 till date. It is also unclear when the Respondent
                                  will be able to provide such access.

                                  (xx) Though the Project Works were scheduled to be
                                  completed in 66 months, more than 135 months have already
                                  elapsed. The Petitioner, for no fault of its own has, however,
                                  been able to complete less than 40% of the intended scope of
                                  the Contract. The Respondent has already accorded approval
                                  for MileStone-2 till December 2019 (which has resulted in
                                  MileStone-3 & MileStone-4 standing extended to March 2021
                                  and September 2022, respectively) and a request on behalf of
                                  the Petitioner, for further extension of time, is pending
                                  consideration.

                                  (xxi) The Respondent's inability to provide access to the
                                  Site, as detailed above, has resulted in the Petitioner's
                                  deployed resources remaining idle for substantial periods of
                                  time. Despite the Petitioner's best efforts to mitigate the losses
                                  it was suffering, on account of the location of the Project as
                                  well as the uncertainties caused by the Respondent's lack of
                                  clear instructions, these losses were substantial. All these
                                  losses were caused on account of the Respondent's inability to
                                  provide access to the site to the Petitioner; and are
                                  reimbursable by the Respondent under the Contract.
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                 Page 5 of 22
Signing Date:15.12.2020
20:44:02
                                   (xxii) In addition, the Petitioner is also entitled to payment of
                                  various amounts under different provisions of the Contract.
                                  These payments are due as reimbursements for amounts spent
                                  by the Petitioner as well as compensation for additional work
                                  executed by the Petitioner on account of Respondent's
                                  instructions."


                            5.    Clause 67 of the General Conditions of Contract (hereinafter
                            referred to as "GCC") provided for resolution of the disputes, between
                            the parties, by arbitration, and reads thus:

                                  "67.   ARBITRATION

                                         Except where otherwise provided in the Contract all
                                         questions and disputes relating to the meaning of the
                                         specifications, design, drawings and instructions here-
                                         in before mentioned and as to the quality of
                                         workmanship or materials used on the Work or as to
                                         any other question, claim, right, matter or thing
                                         whatsoever in any way arising out of or relating to the
                                         Contract, design, drawings, specifications, estimates,
                                         instructions, orders to these conditions or otherwise
                                         concerning the Works or the execution or failure to
                                         execute the same whether arising during the progress
                                         of the Work or after the cancellation, termination
                                         completion or abandonment thereof shall be dealt with
                                         as mentioned hereinafter.

                                                i)     If the Contractor considers any work
                                                demanded of him to be outside the requirements
                                                of the Contract, or considers any decision of the
                                                Engineer-in-Charge on any matter in connection
                                                with or arising out of the Contract or carrying
                                                out of Work to be unacceptable, he shall
                                                promptly ask the Engineer-in-Charge in writing,
                                                for written instructions or decision. There upon
                                                the Engineer-in-Charge shall give his written
                                                instructions or decision within a period of thirty
                                                days of such request. Upon receipt of the written
                                                instructions or decision, the Contractor shall
                                                promptly proceed without delay to comply with
                                                such instructions or decision.
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                Page 6 of 22
Signing Date:15.12.2020
20:44:02
                                               If the Engineer-in-Charge fails to give his
                                              instructions or decision in writing within a
                                              period of thirty days after being requested for or
                                              if the Contractor is dissatisfied with the
                                              instructions or decision of the Engineer-in-
                                              Charge, the Contractor may within thirty days
                                              after receiving the instructions of decision file a
                                              written appeal to the Managing Director, PHPA
                                              who will constitute a Committee of which the
                                              Director (Technical) will be convenor, to
                                              resolve the dispute. The Committee shall afford
                                              an opportunity to the Contractor to be heard and
                                              to offer evidence in support of his appeal within
                                              forty five days of the receipt of the appeal by the
                                              Director (Technical). The Director (Technical)
                                              shall give a decision on behalf of the Committee
                                              within a period of thirty days after the
                                              Contractor has been heard and the Contractor
                                              has given evidence in support of his appeal. If
                                              the Director (Technical) does not give a
                                              decision within thirty days, the Contractor will
                                              have the right to refer the dispute to arbitration.

                                              If the Contractor is dis-satisfied with the
                                              decision of the Director (Technical), the
                                              Contractor, within a period of thirty days from
                                              receipt of the decision, shall indicate his
                                              intention to refer the dispute to arbitration
                                              failing which the said decision shall be final and
                                              conclusive.

                                              ii)    Except where the decision has become
                                              final, binding and conclusive in terms of Sub
                                              Para (i) above disputes or difference shall be
                                              referred for adjudication through arbitration to
                                              an Arbitral Tribunal of three arbitrators
                                              appointed jointly by the PHPA and the
                                              Contractor. Where the mandate of an arbitrator
                                              terminates a substitute arbitrator shall be
                                              appointed according to the rules that were
                                              applicable to the appointment of the arbitrator
                                              being replaced.
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                              Page 7 of 22
Signing Date:15.12.2020
20:44:02
                                               In the absence of an Arbitration Act in Bhutan,
                                              the Arbitral Tribunal shall follow/be guided by
                                              the basic principles and procedures as contained
                                              in the Indian Arbitration and Conciliation Act
                                              1996. The parties shall be free to agree on a
                                              procedure for appointing the Arbitrators. Failing
                                              any agreement for appointment of Arbitrators,
                                              each party shall appoint one Arbitrator and the
                                              two appointed Arbitrators shall appoint the third
                                              Arbitrator, who shall act as the presiding
                                              Arbitrator.

                                              iii)  The said arbitrators shall have full power
                                              to open up, revise and review any decision,
                                              opinion, direction, certificate of valuation of the
                                              PHPA.

                                              iv)     If either of the parties fail to appoint its
                                              arbitrators in pursuance of sub-clause (ii) above,
                                              within 30 days after receipt of the notice of the
                                              appointment of its arbitrators or the two
                                              appointed Arbitrators fail to agree on third
                                              Arbitrator within thirty days from the date of
                                              their appointment then the appointment shall be
                                              made, upon request of a party, by the Chief
                                              Justice, Delhi High Court, India/Thimphu High
                                              Court, Bhutan or any person or institutions
                                              designated by him.

                                              v)      Neither party shall be limited in the
                                              proceedings before such arbitrators to the
                                              evidence or arguments put before any authority
                                              herein above for the purpose of obtaining its
                                              said decision. No decision given by any
                                              authority in accordance with the foregoing
                                              provisions shall disqualify it from being called
                                              as a witness and giving evidence before the
                                              arbitrators on any matter what-so-ever relevant
                                              to the dispute or difference referred to the
                                              arbitrators as aforesaid.

                                              vi)   The reference to arbitration may proceed
                                              notwithstanding that the works shall not then be
                                              or be alleged to be complete, provided always
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                               Page 8 of 22
Signing Date:15.12.2020
20:44:02
                                                 that the obligations of the PHPA, and the
                                                Contractor shall not be altered by reason of the
                                                arbitration being conducted during the progress
                                                of the Works. Neither party shall be entitled to
                                                suspend such Work to which the dispute relates
                                                and payment to the Contractor shall be
                                                continued to be made in terms of the Contract.

                                                vii)a) All arbitration shall be held at New
                                                Delhi, India/Thimphu, Bhutan.

                                                b)    The language of the arbitration
                                                proceedings and that of all documents and
                                                communications between the parties shall be
                                                English.

                                                viii) The decision of         the    majority   of
                                                arbitrators shall prevail.

                                                ix)     The cost of the arbitration as fixed by the
                                                arbitrators shall be borne equally by the parties
                                                unless the settlement agreement provides for a
                                                different apportionment. However, the expenses
                                                incurred by a party in connection with the
                                                preparation, presentation etc. of its cases prior
                                                to, during and after the arbitration proceedings
                                                shall be borne by that party.

                                                x)     All awards of arbitration shall be in
                                                writing and shall state reasons for the amount
                                                awarded."
                                                                            (Emphasis supplied)


                            6.    Additionally, Clause 5 of the GCC, on which Mr. Bharat Singh
                            places great reliance, reads as under:

                                  "5.    Language and Law

                                         i)a) The Contract documents shall be drawn up in
                                         English. All correspondence and documents relating to
                                         the bid, exchanged by the bidder and the PHPA, shall
                                         be submitted in the prescribed form in English. All
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                Page 9 of 22
Signing Date:15.12.2020
20:44:02
                                            supporting documents and printed literature in
                                           connection with the bid shall be preferably in English.

                                           b)     The law to which the Contract is to be subject
                                           and according to which the Contract is to be construed
                                           shall be the law for the time being in force in Bhutan
                                           and within the jurisdiction of Thimphu courts.

                                           ii)   Documents Mutually Explanatory

                                           Several documents forming the Contract are to be
                                           taken as mutually explanatory of one another, but in
                                           case of ambiguities or discrepancies, the documents
                                           shall take precedence in the order in which they are set
                                           out in the Proforma of Agreement (Annex-III)."

                            7.    As is apparent from the reading of Clause 67 of the GCC, any
                            claim was, at the first instance, required to be raised before the
                            Engineer-In-Charge of the project. Dissatisfaction, with the decision
                            of the Engineer-In-Charge, entitled the petitioner to represent to the
                            Managing Director of the respondent, who was required to constitute a
                            Committee, with the Director (Technical), as its convenor. Rejection
                            of the claim by the said Committee entitled the petitioner to seek
                            recourse to arbitration.


                            8.    The petition avers, and the respondent does not dispute, that the
                            petitioner's claims were submitted to, and successively rejected by the
                            Engineer-In-Charge as well as the Committee constituted by the
                            Managing Director of the respondent. The petitioner has, thus,
                            undisputedly become entitled to seek reference of the dispute to
                            arbitration.


                            9.    On 28th July, 2020, a notice invoking arbitration was issued by
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                 Page 10 of 22
Signing Date:15.12.2020
20:44:02
                             the petitioner to the respondent, in which the petitioner suggested the
                            name of Hon'ble Mr. Justice Deepak Verma, a retired Judge of the
                            Supreme Court, as its arbitrator. The respondent was requested to
                            appoint its nominee arbitrator within 30 days from the said notice.


                            10.   In its response, dated 4th August, 2020, the respondent while
                            agreeing to reference of the dispute to arbitration, asserted that the
                            arbitration would be covered not by the 1996 Act, but by the
                            Alternative Dispute Resolution Act of Bhutan, 2013 (hereinafter
                            referred to as "the 2013 Bhutan Act"), and that the place of arbitration
                            would be Thimphu. The respondent called upon the petitioner to
                            agree with these covenants and register for arbitration with the Bhutan
                            Alternative Dispute Resolution Centre.


                            11.   The petitioner wrote back to the respondent on 7th August,
                            2020, disagreeing with the contention of the respondent that the
                            arbitration would abide by the 2013 Bhutan Act or that it would be
                            conducted at Thimphu. The petitioner asserted that the covenants of
                            the GCC clearly make the 1996 Act applicable to the arbitral
                            proceedings, and fixed the seat of arbitration at New Delhi.


                            12.   As the situation between the petitioner and the respondent has,
                            thus, reached an impasse, the petitioner has invoked the jurisdiction of
                            this Court under Section 11(6) of the 1996 Act. Mr. Bharat Singh
                            would, however, submit that this Court does not possess any such
                            jurisdiction in the facts of the present case.


Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                           Page 11 of 22
Signing Date:15.12.2020
20:44:02
                             13.   The contest by Mr. Bharat Singh, to the jurisdiction of this
                            Court to entertain the present petition, is essentially founded on what
                            he perceives to be the correct interpretation of Clauses 5 and 67(ii) of
                            the GCC, when seen in conjunction. Mr Bharat Singh contends thus:


                                  (i)    Clause 67(ii) of the GCC made the basic principles and
                                  procedures, contained in the 1996 Act, applicable in the absence
                                  of an Arbitration Act in Bhutan. In the first place, therefore, the
                                  1996 Act has not bodily, or by reference, been incorporated into
                                  Clause 67(ii) of the GCC, which merely applies the "basic
                                  principles and procedures", contained in the said Act. The basic
                                  principles and procedures contained in the 2013 Bhutan Act,
                                  were the same as those contained in the 1996 Act. As such,
                                  applying the 2013 Bhutan Act would not infract, in any manner,
                                  Clause 67(ii) of the GCC.


                                  (ii)   Besides, Clause 67(ii) of the GCC made the basic
                                  principles and procedures of the 1996 Act applicable only "in
                                  the absence of an Arbitration Act in Bhutan". This covenant, in
                                  order to be correctly understood and interpreted, would have to
                                  be read in juxtaposition with Clause 5 of the GCC, which made
                                  "the law for the time being in force in Bhutan and within the
                                  jurisdiction of Thimphu Courts", applicable to the contract. As
                                  such, the very enactment of 2013 Bhutan Act, resulted in the
                                  entire contract, ipso facto, being made subject thereto, and the
                                  application of the 1996 Act stood, thereby, completely ousted.


Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                            Page 12 of 22
Signing Date:15.12.2020
20:44:02
                                       (iii)   The applicable law would also be Bhutanese law. As
                                      such, the 1996 Act, being an Indian statute, would not apply for
                                      appointment of an arbitrator.


                                      (iv)    The project was located at Bhutan, and the parties are
                                      located at Bhutan. The entire cause of action has arisen within
                                      the jurisdiction of the Bhutan Court and, as such, this Court
                                      ought not to exercise jurisdiction, even for appointment of an
                                      arbitrator.


                                      (v)     Reliance has also been placed on the judgment of the
                                      Supreme Court in Radha Sunder Dutta v. Mohd. Jahadur
                                      Rahim 1 to assert that, where there is a conflict between two
                                      provisions in a contractual instrument, the provision which
                                      occurs earlier in the contract would have precedence. As such,
                                      Mr. Bharat Singh submits that the issue of jurisdiction of this
                                      Court, to entertain the present petition, would have to be gauged
                                      on the anvil of Clause 5 of the GCC.


                            14.       Mr. Gourab Banerji, learned Senior Counsel for the petitioner,
                            responded by submitting that the arguments of Mr. Bharat Singh were
                            completely tangential to the actual issue at hand.          He drew my
                            attention to Clause 67(iv) of the GCC, which specifically entitles the
                            parties to approach either the Chief Justice of this Court or the High
                            Court of Thimphu, for appointment of the arbitrator. As such, he
                            submits, there being a specific dispensation, in the contract, allowing

                            1
                                AIR 1959 SC 24
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                               Page 13 of 22
Signing Date:15.12.2020
20:44:02
                             either party to approach this Court for appointment of an arbitrator, all
                            other covenants in the contract pale into insignificance. Reliance is
                            placed, in this context, on the recent judgment of this Court in Cars24
                            Services Pvt. Ltd v. Cyber Approach Workspace LLP 2.


                            15.       Mr. Gourab Banerji also points out that the seat of arbitration is
                            not Thimphu, but New Delhi, India/ Thimphu, Bhutan, as per Clause
                            67(vii)(a) of the GCC. Even on the basis of the "seat of arbitration
                            test", therefore, Mr. Gourab Banerji would submit that this Court has
                            jurisdiction to adjudicate the present dispute and appoint the arbitrator
                            on behalf of the respondent.


                            16.       Apropos the submission of Mr. Bharat Singh that Clause 67 was
                            to be read in juxtaposition with Clause 5 of the GCC, Mr. Banerji
                            submits that this argument loses sight of the fundamental distinction
                            between the substantive law governing the dispute and the curial law.
                            Clause 5, he points out, relates to the substantive law governing the
                            dispute, whereas Clause 67 deals with the curial law, and it would be
                            completely fallacious to confuse these two aspects. He draws my
                            attention to the following observations of the Supreme Court in
                            Government of India vs. Vedanta Ltd. & Ors. 3

                                      "We will now briefly touch upon the four types of laws which
                                      are applicable in an international commercial arbitration, and
                                      court proceedings arising therefrom. These are:

                                             a)     The governing law determines the substantive
                                             rights and obligations of the parties in the underlying

                            2
                                MANU/DE/2017/2020
                            3
                                2020 SCC OnLine SC 749
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                  Page 14 of 22
Signing Date:15.12.2020
20:44:02
                                         commercial contract. The parties normally make a
                                        choice of the governing law of the substantive contract;
                                        in the absence of a choice of the governing law, it
                                        would be determined by the tribunal in accordance
                                        with the conflict of law rules, which are considered to
                                        be applicable.

                                        b)     The law governing the arbitration agreement
                                        must be determined separately from the law applicable
                                        to the substantive contract. The arbitration determine
                                        the validity and extent of the arbitration agreement;
                                        limits of party autonomy, the jurisdiction of the
                                        tribunal, etc.

                                        c)      The curial law of the arbitration is determined
                                        by the seat of arbitration. In an international
                                        commercial arbitration, it is necessary that the conduct
                                        of the arbitral proceedings are connected with the law
                                        of the seat of arbitration, which would regulate the
                                        various aspects of the arbitral proceedings. The parties
                                        have the autonomy to determine the choice of law,
                                        which would govern the arbitral procedure, which is
                                        referred to as the lex arbitri, and is expressed in the
                                        choice of the seat of arbitration. The curial law governs
                                        the procedure of the arbitration, the commencement of
                                        the arbitration, appointment of arbitrator/s in exercise
                                        of the default power by the court, grant of provisional
                                        measures, collection of evidence, hearings, and
                                        challenge to the award. The courts at the seat of
                                        arbitration exercise supervisory or "primary"
                                        jurisdiction over the arbitral proceedings, except if the
                                        parties have made an express and effective choice of a
                                        different lex arbitri, in which event, the role of the
                                        courts at the seat will be limited to those matters which
                                        are specified to be internationally mandatory and of a
                                        nonderogable nature.

                                        d)     The lex fori governs the proceedings for
                                        recognition and enforcement of the award in other
                                        jurisdictions. Article III of the New York Convention
                                        provides that the national courts apply their respective
                                        lex fori regarding limitation periods applicable for
                                        recognition and enforcement proceedings; the date
                                        from which the limitation period would commence,
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                              Page 15 of 22
Signing Date:15.12.2020
20:44:02
                                               whether there is power to extend the period of
                                              limitation. The lex fori determines the court which is
                                              competent and has the jurisdiction to decide the issue
                                              of recognition and enforcement of the foreign award,
                                              and the legal remedies available to the parties for
                                              enforcement of the foreign award."

                            14.       Even without entering into the fine niceties of "conflict of
                            jurisdiction" law, the controversy, to my mind, is elementary. Clause
                            67(iv) of the GCC is clear and categorical. It specifically states that,
                            on failure of the arbitral mechanism provided in the contract, either
                            party could approach the Chief Justice of this Court or the High Court
                            of Thimphu, to appoint the arbitrator.              Where such a specific
                            contractual dispensation exists, this Court has already taken a view in
                            its recent decision in Cars242, that such specific dispensation would
                            take precedence over other contractual covenants. As in the present
                            case, this Court was seized, in the said case, with a similar situation,
                            wherein though the seat of the arbitration was fixed at New Delhi,
                            India, specific jurisdiction for appointment of the arbitrator was vested
                            in the Court of competent jurisdiction at Haryana. Following the
                            judgment of the Supreme Court in Mankastu Impex Pvt. Ltd. v.
                            Airvisual Ltd. 4, which accorded pre-eminence to such contractual
                            covenants, catering to specific exigencies contemplated by the 1996
                            Act, it was held that, once the contract permitted the parties to
                            approach the Courts at Haryana for appointment of the arbitrator, the
                            jurisdiction in that regard, would be possessed by that Court alone.
                            Para 53 of the judgement in Cars242 may, in this context, be
                            reproduced thus:


                            4
                                (2015) 12 SCC 225
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                  Page 16 of 22
Signing Date:15.12.2020
20:44:02
                                   "As already observed hereinabove, I am not inclined to agree
                                  with this submission. Once the agreement between the parties
                                  specifically confers Section 11 jurisdiction, for appointment of
                                  an arbitrator, on courts at Haryana, this Court, in my view,
                                  would be doing violence to the contractual covenant, if it were
                                  to exercise such jurisdiction. There is no judgment of the
                                  Supreme Court, to which my attention has been invited, which
                                  permits a Court to exercise jurisdiction contrary to the
                                  exclusive jurisdiction clause in the agreement between the
                                  parties. Rather, the decisions in Swastik Gases Pvt. Ltd.,
                                  (2013) 9 SCC 32 and Brahmani River Pellets Ltd. - both of
                                  which have been approvingly cited in BGS SGS Soma JV,
                                  (2020) 4 SCC 234 - emphasised the need to adhere to the
                                  exclusive jurisdiction clause. At the cost of repetition yet
                                  again, all decisions, which decide the question of territorial
                                  jurisdiction on the basis of the seat of arbitration as delineated
                                  in the agreement, deal with contracts in which there is no
                                  separate exclusive jurisdiction clause, fixing jurisdiction
                                  elsewhere. Where such a clause exists, and, especially, where
                                  such a clause fixes Section 11 jurisdiction with courts located
                                  elsewhere, I am not inclined to hold that this Court can,
                                  contrary to the explicit words and intent of said clause,
                                  exercise Section 11 jurisdiction and appoint an arbitrator."
                                                                               (Emphasis supplied)


                            15.   In the present case, too, Clause 67(iv) of the GCC entitles either
                            party, on failure of the arbitral mechanism provided in the GCC, to
                            approach this Court or the High Court of Thimphu, for appointment of
                            the arbitrator.   Section 11 jurisdiction, thereby, stands specifically
                            conferred on this Court, by contract between the parties, and I fail to
                            understand how the respondent could contend otherwise. The choice,
                            between this Court and the High Court of Bhutan at Thimphu has been
                            left to the party who seeks to approach the court for appointment of
                            the arbitrator. Either which way, it cannot be gainsaid that this Court
                            does not possess the jurisdiction to entertain the prayer of the
                            petitioner for appointment of the arbitrator on behalf of the
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                                 Page 17 of 22
Signing Date:15.12.2020
20:44:02
                             respondent. Even on this sole ground, therefore, the present petition
                            under Section 11(6) of the 1996 Act, would be maintainable before
                            this Court.


                            16.   Significantly, Mr. Bharat Singh did not choose to advance any
                            submission regarding Clause 67(iv) of the GCC.


                            17.   Mr. Bharat Singh has, instead, sought to question the very
                            applicability of the 1996 Act. According to him, a conjoint reading of
                            Clauses 5 and 67(ii) of the GCC would result in the applicability of
                            the 1996 Act being entirely eviscerated, on the enactment of the 2013
                            Bhutan Act. According to Mr. Bharat Singh, the 1996 Act was
                            applicable only till the enactment of 2013 Bhutan Act. This, in his
                            submission, would also accord with Clause 5(b), which makes the
                            contract subject to the law applicable in Bhutan.


                            16.   I am unable to agree. Acceptance of this submission of Mr.
                            Bharat Singh, in my view, would, in fact, require this Court to rewrite
                            Clause 67(ii) of the GCC. There is nothing in the said Clause, which
                            indicates that the applicability of the 1996 Act, is by way of an ad hoc
                            arrangement, to subsist only till the enactment of an Arbitration Act in
                            Bhutan. Mr. Bharat Singh, in my view, is seeking to read far too
                            much into the expression "in the absence of an Arbitration Act in
                            Bhutan", as contained in Clause 67(ii). All that, this phrase indicates
                            is that there was no Arbitration Act in Bhutan at the time when the
                            contract was executed and that the Arbitral Tribunal would be guided
                            by the principles and procedures contained in the 1996 Act. There is
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                            Page 18 of 22
Signing Date:15.12.2020
20:44:02
                             not even the hint of a suggestion, in Clause 67(ii), that the 1996 Act
                            would cease to apply, on an arbitration statute coming into effect in
                            Bhutan. The words used in Clause 67(ii) cannot, by any stretch of
                            imagination, be extrapolated to mean that, immediately on enactment
                            of an Arbitration Act in Bhutan, the 1996 Act would vanish into thin
                            air, insofar as the contract was concerned, and that the Bhutan Act
                            would stand substituted in place of the 1996 Act, in Clause 67(ii).
                            This, essentially, would require rewriting of the contractual provision,
                            which no Court can do.


                            17.   To reiterate, there is nothing in Clause 67(ii) which indicates
                            that the stipulation, therein, that the Arbitral Tribunal would be guided
                            by the principles and procedures contained in the 1996 Act, would
                            subsist only till the enactment of the Arbitration Act in Bhutan, or that
                            until there is an enactment of the Arbitration Act in Bhutan, or that,
                            immediately on enactment of 2013 Bhutan Act, the procedure for
                            appointment of arbitrator under the said Act would come into
                            application and the 1996 Act would cease, pro tanto, to apply.


                            18.   Mr. Bharat Singh also sought to submit that Clause 67(ii) of the
                            GCC merely applied the "basic principles and procedures" contained
                            in the 1996 Act, and did not bodily incorporate the Act into the
                            Clause. He has advanced a somewhat ingenious submission that, as
                            the principles and procedures contained in the 2013 Bhutan Act are
                            similar to those contained in the 1996 Act, those principles and
                            procedures should apply, once the 2013 Bhutan Act come into being,
                            as application of the principles and procedures stipulated in the 2013
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                            Page 19 of 22
Signing Date:15.12.2020
20:44:02
                             Bhutan Act would also be in accordance with Clause 67(ii) of the
                            GCC. The argument is not only unacceptable, but is largely difficult
                            to understand, even on first principles. To my mind, Clause 67(ii) of
                            the GCC clearly stipulates that the Arbitral Tribunal would be guided
                            by the principles and procedures contained in the 1996 Act, without
                            altering this dispensation at any future point of time, either upon
                            enactment of the 2013 Bhutan Act, or otherwise.          Whether the
                            principles and procedures for appointment of the arbitrator, under the
                            2013 Bhutan Act are, or are not, similar, or even identical, to those
                            contained in the 1996 Act is, to my mind, wholly irrelevant. The point
                            for determination is as to which Act would apply, and has obviously to
                            be answered as per the contractual covenants which, in any
                            relationship governed by contract, are supreme.       Seen thus, the
                            procedure for appointment of the arbitrator, which also finds mention
                            in the same covenant, would necessarily abide by the 1996 Act. The
                            enactment of the 2013 Bhutan Act cannot result in rewriting of Clause
                            67(ii) of the GCC, making the 2013 Bhutan Act applicable to the
                            procedure to be followed by the Arbitral Tribunal as well as to the
                            exercise of appointment of the arbitrator, consequent on the arbitral
                            mechanism in the contract having failed.


                            20.   I do not deem it necessary to enter any specific observation
                            regarding the applicability of the judgment of the Supreme Court in
                            Radha Sunder Dutta1, on which Mr. Bharat Singh has relied. It is
                            axiomatic, in law, that, if two covenants in a contractual instrument
                            are in conflict with each other, and are irreconcilable, the former
                            would have precedence over the latter. No such occasion, however,
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                          Page 20 of 22
Signing Date:15.12.2020
20:44:02
                             arises in the present case. There is no conflict between Clauses 5 and
                            67(ii) of the GCC. As Mr. Banerji has correctly pointed out, and as
                            enunciated most recently by the Supreme Court in Vedanta Ltd.3,
                            Clauses 5 and 67(ii) of the GCC deal with two separate dispensations,
                            the former dealing with the substantive law governing resolution of
                            the dispute between the parties under the contract, and the latter
                            relating to the applicable curial law.     These provisions, therefore,
                            operate in different spheres, and there is no conflict between the two,
                            nor, for that matter, is there even occasion for any such conflict. As
                            such, no occasion arises to seek recourse to the principles enunciated
                            in Radha Sunder Dutta1.


                            21.   To my mind, therefore, the objection, of Mr. Bharat Singh,
                            regarding the lack of territorial jurisdiction of this Court to entertain
                            the present petition has necessarily to be rejected.


                            22.   The arbitral procedure, as set out in the GCC, has failed,
                            inasmuch as, though the petitioner suggested the name of Hon'ble Mr.
                            Justice Deepak Verma, as its arbitrator, the respondent failed to
                            appoint its arbitrator within the time stipulated in the GCC, thereby
                            necessitating the appointment of an arbitrator, on behalf of the
                            respondent, by this Court.


                            23.   Accordingly, this Court appoints Hon'ble Ms Gita Mittal,
                            former Chief Justice of the High Court of Jammu and Kashmir and
                            Acting Chief Justice of this Court, as the arbitrator on behalf of the
                            respondent. Her contract details are as follows:
Signature Not Verified
Digitally Signed By:SUNIL
SINGH NEGI                  ARB.P. 461/2020                                            Page 21 of 22
Signing Date:15.12.2020
20:44:02
                                   Hon'ble Ms Justice Gita Mittal (Retired),
                                  Former Chief Justice of the High Court of Jammu & Kashmir,
                                  (Address : E-327, Greater Kailash Part - I, New Delhi - 110048
                                  Email id : [email protected]
                                  Tel. No.: +91 98113 22190 )

                            24.   The respondent is directed to contact the learned arbitrator, as
                            per the details furnished hereinabove, within a period of three days
                            from the forwarding of a copy of this judgement to Mr Bharat Singh
                            by e-mail by the Registry or the uploading of this judgement on the
                            website of this Court, whichever is later, so as to obtain the
                            concurrence of the learned arbitrator, to arbitrate on the disputes
                            between the parties.


                            25.   The learned Arbitrator would be entitled to fees in accordance
                            with the Fourth Schedule to the 1996 Act.


                            26.   The two arbitrators would, thereafter, proceed to appoint a
                            presiding arbitrator, in accordance with the dispensation to that effect
                            as contained in the GCC, and the arbitral proceedings would,
                            thereafter, take off, in accordance with the provisions of the 1996 Act.


                            27.   The petition stands disposed of in the aforesaid terms with no
                            orders as to costs.




                                                                          C. HARI SHANKAR, J.

DECEMBER 11, 2020 r.bararia Signature Not Verified Digitally Signed By:SUNIL SINGH NEGI ARB.P. 461/2020 Page 22 of 22 Signing Date:15.12.2020 20:44:02