Section 10(2) in The Petroleum and Natural Gas Regulatory Board (Technical Standards and Specifications including Safety Standards for Natural Gas Pipelines) Regulations, 2009

(2)The Board may at any time effect appropriate modifications in these regulations.Appendix-IList of Critical Activities in Natural Gas Pipelines
Sr. No. Critical Infrastructure/ Activity/ Processes Time period for Implementation Implementation plan
1 Test record for radiograpy, ultrasonic test orother applicable NDT methods (as carried out beforecommissioning) 6 months can be submitted in stages within 6 months
2 Hydro-test (as carried out beforecommissioning) Report 6 months can be submitted in stages within 6 months
3 Pipeline cathodic protection record 6 months can be submitted in stages within 6 months
4 Pipeline As-built records 6 months can be submitted in stages within 6 months
5 Intelligent pigging shall be carried out todetect metal loss for the pipelines of size NPS of 12 inches andabove and length of 10 Km and above. 2 years If the pigging has not been done for more than5 years for sour gas and 10 years for sweet gas pipeline, thenthe intelligent pigging shall be carried out within two years,otherwise relevant records shall be submitted.
6 HSE Management System (including fireprotection system) 6 months To be implemented
7 Height of the vent shall be minimum 3 metersabove working level 6 months Increase height of vent
8 Gas detectors shall be installed at compressorstation, gas receiving and delivery terminals 1 year Install gas detectors for SCADA backed upsystem, elsewhere hand held gas detector shall be provided
9 Environmental friendly fire extinguishingflooding system for closed space 2 years For control room, switch gear and battery room,etc. (CO2is acceptable only for unmanned station)
10 HAZOP shall be done for all the pipelinefacilities 1 year HAZOP report to be submitted along withmitigation plan