Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 0]

State Consumer Disputes Redressal Commission

S.Malathy vs M/S.Metro City Foundation & 5 Others on 5 November, 2015

  	 Daily Order 	   

BEFORE THE STATE CONSUMER DISPUTES REDRESSAL COMMISSION, CHENNAI

 

BEFORE        Thiru. J.JAYARAM                  PRESIDING  JUDICIAL MEMBER 
                         Tmt. P. BAKIYAVATHI                                                 MEMBER

 

 C.C. 73/2012

 

 DATED THIS THE  5TH  DAY OF NOVEMBER 2015

 

Mrs. S.Malathy

 

w/o. G.Senthilkumar,

 

No.9, Indira Nagar 1st street

 

Back of CSI Church

 

Avinashi Road

 

Tirupur                                                                                      ..complainant

 

                                                               Vs

 

1. M/s Metro City Foundation

 

No.96, Perumal Kovil street,

 

Tiruppur 641 604 

 

Represented by its Managing Director,

 

 

 

2. D.Prabhu

 

Partner

 

M/s Metro City Foundation,

 

No.10, Deepam Complex

 

No.577, 100 Feet Road

 

Gandhipuram

 

Coimbatore-12       

 

 

 

3. Mrs.P.Jayanthi

 

Partner

 

M/s Metro City Foundation,

 

No.10, Deepam Complex

 

No.577, 100 Feet Road

 

Gandhipuram

 

Coimbatore-12    

 

 

 

4. M.P.S.Thiagarajan,

 

s/o M.P.Subramaniam,

 

49, Ramalinga Layouts

 

K.P.N colony

 

Tiruppur 641 601  

 

 

 

5.Mrs. T.Sudha

 

W/o M.P.S.Thiagarajan,

 

49, Ramalinga Layouts

 

K.P.N colony

 

Tiruppur 641 601                                                                ..opposite parties

 

Counsel for the complainant           : M/s. S.Natarajan

 

Opposite parties 1 to 5                  : Exparte

 

        This case coming before us for final hearing on 16.7.2015 and hearing the arguments of the complainant and upon perusing the material this Commission made the following order Thiru. J.JAYARAM,  PRESIDING  JUDICIAL MEMBER

1.      The Case of the complainant are as follows:-

        Flat No. G.1, with 1345 sq.ft of built up area along with 510 sq.ft of undivided share for allotted and agreed to be sold to the complainant. Accordingly a separate agreement for construction dated 28.8.2007 was executed between the complainant and the 1st opposite party as per the agreement for construction, the 1st opposite party undertook to construct the multi storied building in accordance with the development plans sanctioned by the Directorate of Town and Country Planning Authority, Local Panchayat and other statutory authorities like Coimbatore Corporation and Ministry of Local Administration. Under Article I(i) of Agreement for construction, the total sale consideration is Rs. 52,11,000/- towards the land and construction. Further under Article I(7), the first opposite party undertook to hand over the possession by January 2008. The 1st opposite party under Article 3(iii) of the construction agreement, agreed to pay 18% interest for the delay of delivery beyond January 2008.

2.           The 4th and 5th opposite parties being owners of the suit premises executed the registered sale deed of undivided share of 510 sq.ft on 13.9.2007.

 3.          The complainant paid a total sum of Rs. 49,43,000/- as per the construction agreement on 31.1.2008 itself and she performed the obligation as per construction agreement. Due to inter dispute between the opposite parties they have delayed the construction work. The 1st opposite party handed over the incomplete possession on 18.1.2010. The complainant finds following incomplete work.

i)    Proper Corporation drinking water bulk lines not provided

 

ii)   There was no access to Club House.

 
	 There are no proper play area with right equipment for children

in the complainant flat, Electrical fittings, lights, Lamps, Wardrobes, substandard tiles are used. Floor tiles are fixed by unskilled cheap labour, totally running the output.

The Door, window hinges, tower bolts, locks, handles were missing.

Parking area flooring is poorly laid with lot of undulations.

The quality of floor tiles, bathroom fittings are below the quality.

No complete wardrobe in one bedroom Swimming pool is not yet provided.

No sanctioned plan has been given.

No parental deed relating to the title of the suit proper has been given There was no proper water and sewerage connection.

No approved layout plan given Generator facility provided is highly underrated, insufficient and substandard equipment is provided resulting in high maintenance and fuel consumption.

Common toilet is not provided.

Lighting in the common areas, open areas, garden and parking area is highly insufficient.

Rain water harvesting is not provided.

Poor quality Gym equipments and AC not provided in the Gym.

Weathering course on the open terrace is substandard.

Intercom facility among the flats not provided.

Plumbing carried out by unskilled workers causing permanent worries.

    Thus there was total absence of common amenities in the project and defects in the individual project.

4.    As per the construction agreement, the 1st opposite party agreed to handover the possession by January 2008, but he handed over  possession on 18.1.2010 and hence they are liable to pay Rs. 21,23,032/-  compensation for the delay.

5.      The completion certificate given by Corporation is mandatory for multi storage building before occupation and in the event of deviation, there is a serious threat for demolition, the 1st opposite party under legal application to get completion certificate from Corporation Authority only on getting completion certificate and occupancy certificate, the complainant will enjoy of the statutory benefit. The corporation usually has given completion certificate,  only on completion of entire project  as per sanctioned plan; but the opposite party has not handed over the completion certificate till today.

6.      It is in trade practice that before handing over the possession measurement of the flat to be given by the purchaser to avoid feature dispute of area reduction. The measurement plan architect are liable to pay Rs.1,52,500/- towards the claim in receipt of unfinished work, namely Electrical fittings, lights, Lamps, Wardrobes, substandard tiles are used. Floor tiles are fixed by unskilled cheap labour, totally running the output. There was undue delay in completing the project which amounts to deficiency in service. Hence the complainant praying for direction to the opposite parties to pay a sum of Rs. 21,23,032 /- as compensation for delay in delivering the possession, to pay a sum of Rs.1,52,500/- towards incomplete work, to pay a sum of Rs. 5,00,000/- as compensation for mental agony, deficiency in service an indulging the unfair trade practice and to pay a costs of Rs.25,000/-

 7.         The opposite parties 1 to 5 remained absent before the Commission and they have set exparte.

8.      The complainant filed proof affidavit reiterating the averments complainant. 3 documents were filed and marked as Ex.A.1 to A.3 on the side of the complainant.

9.          Ex.A.1 is the construction agreement dated 28.8.2007, Ex.A.2 is the sale deed dated 13.9.2007 and Ex.A.3 is the possession certificate dated 18.1.2010.

9.      Points for consideration:-

1)       Whether the opposite parties adopted unfair trade practice and whether there is any deficiency in service on the part of the opposite parties, as alleged the complaint?
2)     Whether the complainant is entitled to claim compensation from the opposite parties?
3)      To what relief the complainant is entitled ?

 

 10. Points 1 &2 :-

 

      Ex.A.1 is the copy of construction agreement dated 28.8.2007 Ex.A.2 is       copy of sale deed dated 13.9.2007, Ex.A.3, is the copy of possession certificate dated 18.1.2010.

 

 11.            We find that Rs.52,11,000/- is the total amount of sale consideration and the cost of the construction and also we find that the stipulated period for completion of construction and handed over the possession on January 2008 and as per the agreement as per Article 1(7) of the Construction Agreement, the 1st opposite party will pay 18% p.a interest for the delayed period of delivering the possession beyond January 2008, the complainant has paid a total sum of Rs.49,43,000/- as per the construction agreement on 31.1.2008 and also we find that the 1st opposite party has delivered the possession of construction flat to the complainant on 18.1.2010.
12.          On considering the entire material records it is established that the 1st opposite party has adapted unfair trade practice and there is deficiency in service on the part of the opposite parties.
13.           We hold that the opposite parties have adapted unfair trade practice and there is deficiency in service on the part of the opposite parties and that the complainant is entitled to get compensation from the opposite parties and the points are answered accordingly.
14.    Point No.3 :
             In view of the finding of points 1 and 2, we hold that the complainant is entitled to get compensation for the delay in delivering the possession and for the incomplete works and compensation for mental agony and deficiency in service and unfair trade practice and costs and the point is answered accordingly,               The complainant has claimed Rs.21,23,032/- as compensation for the delay in handing over the possession and Rs.1,52,500/- towards the incomplete works and to pay a sum of Rs. 5 lakhs for compensation for mental agony etc., and cost of Rs.25,000/-. We feel that the claim of Rs. 5 lakhs as compensation for mental agony etc, is on the higher side and we are inclined to award Rs.2 lakhs. So and so, we are inclined to reduce the cost of Rs.10,000/- instead of Rs.25,000/-.
             In the result, the complaint is partly allowed, directing the opposite parties jointly and severally to pay a sum of Rs. 21,23,032/- as compensation for the delay in delivering  possession and to pay a sum of Rs. 1,52,500/- as compensation towards incomplete works and to pay a sum of Rs.2,00,000/- (Rupees Two Lakhs only) as compensation for mental agony, deficiency in service and unfair trade practice and to pay  costs of Rs.10,000/-(Ten Thousand Rupees only)           Time for compliance : Two months from the date of receipt of copy of this order. In case of default in compliance of the order, the amounts shall carry interest at the rate of 9% p.a. from the date of default till compliance.
        
TMT.  P. BAKIYAVATHI                                                   J. JAYARAM            

 

              MEMBER                                                PRESIDING JUDICIAL MEMBER          

 

Documents filed by the Complainant :-

 

Ex.A.1          30.11.2006    copy of construction agreement

 

Ex.A.2          13.9.2007     copy of sale deed

 

Ex.A.3          18.1.2010     copy of possession certificate

 

 

 

TMT.  P. BAKIYAVATHI                                            J. JAYARAM                       

 

    MEMBER                                            PRESIDING JUDICIAL MEMBER