State of Tamilnadu - Subsection

Section 9(3) in Tamil Nadu Electricity Regulatory Commission Intra State Open Access Regulations, 2005

(3)Additional Surcharge: (a) An open access customer, receiving supply of electricity from a person other than the distribution Licensee of his area of supply, shall pay to the distribution Licensee an additional surcharge on the charges of wheeling, in addition to wheeling charges and surcharge, to meet out the fixed cost of such distribution Licensee arising out of his obligation to supply as provided under sub-section (4) of section 42 of the Act; This additional surcharge shall become applicable only if the obligation of the Licensee in terms of power purchase commitments has been and continues to be stranded.
(b)The distribution Licensee whose consumer intends to avail open access shall submit to the Commission within fifteen days of receipt of application, a detailed calculation statement of fixed cost which the Licensee is incurring towards his obligation to supply;
(c)The Commission shall scrutinize the statement of calculation of fixed cost submitted by the distribution Licensee and obtain objections, if any, from the open access customer and determine the amount of additional surcharge.
(d)The additional surcharge shall be levied for such period as the Commission may determine.
Note: Provided that such additional surcharges shall not be levied in case transmission access is provided to a person who has established a captive generation plant for carrying the electricity to the destination of his own use.