Section 11N(1) in Haryana Urban Development Authority (Erection of Buildings) Regulations, 1979
(1)The Authority shall necessarily issue an occupation certificate in form BRS VI within three working days of receipt of the form BRS-III A/B, duly complete in all respects and accompanied with the required completion drawings, forms and affidavits. The occupation certificate shall be issued provided that the documents submitted along with form BRS-III A/B are in order. Violations, if found at any subsequent stage, shall result in cancellation of the occupation certificate issued and the same may be restored only after removal of violations. Further, action against the Architect shall also be taken for furnishing a wrong certificate/affidavit.