Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 17, Cited by 0]

Gujarat High Court

East West Marine Engineering Works vs Shree Ram Streel Co on 9 January, 2015

Author: Akil Kureshi

Bench: Akil Kureshi

        O/IAAP/85/2014                                    JUDGMENT




         IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

           PETN. UNDER ARBITRATION ACT NO. 85 of 2014



FOR APPROVAL AND SIGNATURE:



HONOURABLE MR.JUSTICE AKIL KURESHI

================================================================

1   Whether Reporters of Local Papers may be allowed to see
    the judgment ?

2   To be referred to the Reporter or not ?

3   Whether their Lordships wish to see the fair copy of the
    judgment ?

4   Whether this case involves a substantial question of law as
    to the interpretation of the Constitution of India, 1950 or any
    order made thereunder ?

5   Whether it is to be circulated to the civil judge ?

================================================================
       EAST WEST MARINE ENGINEERING WORKS....Petitioner(s)
                           Versus
             SHREE RAM STREEL CO.....Respondent(s)
================================================================
Appearance:
MR AR GUPTA, ADVOCATE for the Petitioner(s) No. 1
================================================================

        CORAM: HONOURABLE MR.JUSTICE AKIL KURESHI

                           Date : 09/01/2015


                           ORAL JUDGMENT
Page 1 of 13

O/IAAP/85/2014 JUDGMENT

1. The   petitioner   seeks   appointment   of   an   arbitrator   under  section 11(6) of the Arbitration and Conciliation Act, 1996  ("the   Act"   for   short)   to   resolve   the   disputes   between   the  petitioner and the respondent arising out of an agreement  titled as MOU dated 15.7.2009. 

 2. Brief facts are as under :

 2.1. Under   the   said   MOU   the   respondent   had   to   lift  approximately   6000   metric   tonnes   of   scrap   from   the  petitioner at its site at Kakinada office, Andhra Pradesh  on   payment   of   an   agreed   sum.   The   agreed   price   was  Rs.11/­   per   kg   or   Rs.11000/­   per   metric   tonnes.   An  advance of Rs.50 lakhs was to be paid. First installment  of   such   advance   of   Rs.   25   lakhs   was   paid   by   the  respondent to the petitioner. It was further agreed that :
"The PARTY OF THE SECOND PART is making advance  payment   of   Rs.25.00   lakhs   in   the   first   phase   as  mentioned in the foregoing paragraphs. THE PARTY OF  THE   SECOND   PART   has   also   agreed   to   pay   the  remaining   advance   amount   of   Rs.25.00   lakhs   after  getting   all   necessary   clearances   and   documents  satisfying   the   conscious   of   THE   PARTY   OF   THE  SECOND  PART that the material  which  the PARTY OF  THE   FIRST   PART   is   selling   to   THE   PARTY   OF   THE  SECOND  PART is free from all encumbrances,  without  any   lien,   without   any   charge,   without   any   attachment  either from any court of law or from any Government or  Semi­Government   Authorities   or   any   financial  institutions or from the Port Authorities.
Page 2 of 13
O/IAAP/85/2014 JUDGMENT AS   THE   PARTY   OF   THE   SECOND   PART   is   making  advance   payment   towards   the   purchase   price   of   the  material, all necessary documents and clearances are to  be obtained by THE PARTY OF THE FIRST PART and all  formalities   are   to   be   observed   by   the   PARTY   OF   THE  FIRST PART for getting clearances of the material. THE  PARTY OF THE FIRST PART will secure interest of the  PARTY   OF   THE   SECOND   PART   by   giving   Post­dated  Cheques from the account of the PARTY OF THE FIRST  PART   bearing   No.369010200009980   with   AXIS   Bank,  Dwarka   Nagar   branch,   Visakhapatnam.   In   addition  thereto,   THE   PARTY   OF   THE   FIRST   PART   will   also  execute a Promissory Note that if the  PARTY OF THE FIRST PART is not able to adhere to  the terms and conditions of this  Contract within 30  days of its execution, the PARTY OF THE FIRST PART  will pay back the advance amount of Rs.25.00 lakhs  plus   Rs.3.00   lakhs  towards   damages   to  THE   PARTY  OF THE SECOND PART forthwith."

 2.2. MOU   also   contained   an   arbitration   clause   in   the  following terms :

"IT   IS   AGREED   BY   AND   BETWEEN   PARTY   OF   THE  FIRST PART AND PARTY OF THE SECOND PART that in  case of any disputes, the resolution  of disputes will be  done   out   of   Court   under   the   provisions   of   The  Arbitration and  Conciliation Act, 1996 and only Courts  at   Ahmedabad   in   the   State   of   Gujarat   will   have  jurisdiction.   It   is   expressly   agreed   by   and   between  PARTY   OF   THE   FIRST   PART   AND   PARTY   O   THE  SECOND   PART   that   only   the   Courts   in   the   city   of  Ahmedabad in the State of Gujarat will have jurisdiction  to entertain  any dispute.  It is further  expressly  agreed  by   and   between   PARTY   OF   THE   FIRST   PART   AND  PARTY OF THE SECOND PART that Arbitral proceedings  Page 3 of 13 O/IAAP/85/2014 JUDGMENT will also be conducted in the City of Ahmedabad in the  State of Gujarat only."

2.3. On   the   allegation   that   the   respondent   though   had  paid   a   sum   of   Rs.25   lakhs   to   the   petitioner,   the  petitioner   failed   to   supply   the   necessary   material,   the  respondent   filed   a   Summary   Suit   No.559/2010   before  the     City   Civil   Court,   Ahmedabad.   In   such   pending  proceedings,   the   petitioner   filed   an   application   dated  6.9.2010 raising an issue that in view of the arbitration  clause contained in the said MOU, the proceedings are  required to be referred for arbitration in terms of section  8 of the Act. The City Civil Court passed an order dated  27.4.2011   disposing   such   an   application   on   the  following reasons :

"Advocate  for  the   defendant   has  not   remained   present  for the hearing of the chamber summons.
Advocate for the plaintiff referring to his reply at Exh.23  submitted that there is no scope for arbitration in view  of the clause  on page no.4 sheet no.4 of Memorandum  of Understanding the defendant has to pay forthwith the  amount Rs. Referred; any other disputes other than this  can be the matter for arbitration. 
The   summary   suit   without   any   leave   for   defence   from  the   defendant   will   take   longer   time   merely   by   this  Chamber summons which the defendant can adhere to,  even at the time of leave to defence.
Hence as there is no cause for the present application,  the chamber summons  is dismissed for No order as to  cost."
Page 4 of 13
O/IAAP/85/2014 JUDGMENT  2.4. The  petitioner  challenged  such  an  order  of  the  City  Civil Court  before the High Court by filing Special Civil  Application   No.9685/2011.   Learned   Single   Judge  dismissed the petition observing as under :
"8. Having heard learned advocates for the parties and  on perusal of the record of the case, it transpires that,  before the summary suit was filed, as per the settlement  arrived between the parties, petitioners­defendants had  decided to return the amount of Rs.25 lakhs by issuing  a cheque which was deposited by the plaintiff. However,  it   was   dishonoured   on   the   ground   of   `stop   payment'.  Thus,  having  received  the draft  of Rs.25  lakhs,  as per  the terms of Memorandum of Understanding, admittedly  the   petitioners   did   not   deliver   the   scrap   material,   and  therefore, by way of settlement, a cheque of Rs.25 lakhs  was given to the purchaser­respondent­original plaintiff,  which   was   dishonoured   on   the   ground   of   `stop  payment'. This shows  that the plaintiff was justified in  filing summary suit for quick recovery of its money and  any attempt on the part of the defendants on the ground  of existence of arbitration clause would result into delay.  Not   only   that,   but   while   passing   the   impugned   order,  the   Trial   Court   has   observed   that,   "the   summary   suit   without any leave for defence from the defendant will take   long time and merely by this Chamber summons which the   defendant   can   adhere   to,   even   at   the   time   of   leave   to   defence, hence no cause of action had arisen at the said   stage and dismissed the chamber summons". 

9. Considering the nature of dispute and contents of the  clause   of   arbitration   in   Sheet   5   of   the   agreement,   the  jurisdiction  of City Civil Court to decide  the dispute  is  not ousted, and therefore, the decision of this Court in  Rupal   Textile   and   Partners   of   Partnership   Firm  Madhubhai G. [supra] relied by the learned advocate for  the petitioners - defendants, which was based on facts  and   circumstances   of   that   case   arising   out   of   suit   for  Page 5 of 13 O/IAAP/85/2014 JUDGMENT permanent  injunction,  is not  applicable  to  the  facts  of  the present case. The dishonest plea on the part of the  defendants,   who   have   pocketed   Rs.25   lakhs   by  accepting demand draft from the plaintiff, but failed to  deliver   the   goods,  would   otherwise  preclude   this   court  from   exercising   discretionary   powers   in   favour   of   the  petitioners.

In view of the above, the impugned order passed by the  learned Judge cannot be said to be in any manner illegal  or   arbitrary,   which   calls   for   any   interference   of   this  Court in exercise of powers under Articles 226 and 227  of the Constitution of India. 

In absence of any merit, this petition is dismissed with  costs of Rs.10,000/­.

Notice is discharged."

3. It is not in dispute that the petitioner has not carried the  matter  further  and  thus  the order  of the  High  Court  has  become final. The petition thereafter, filed this arbitration  petition   urging   the   designatee   of   the     Chief   Justice   to  appoint an arbitrator to resolve the disputes pertaining the  breach   of   the   agreement   and   recovery   of   outstanding  amount, compensation along with interest. 

 4. First question with which I confronted the advocate of the  petitioner   was,   in   view   of   the   order   passed   by   City   Civil  Court, Ahmedabad and upheld by the High Court, would  it  now be possible to appoint arbitrator under section 11  to  resolve   the   very   same   dispute.   The   counsel   strenuously  urged   that   the   order   passed   by   the   City   Civil   Court   was  summary in nature and the question of jurisdiction of the  arbitrator should be allowed to be decided by the arbitrator  himself in terms of section 16 of the Act. He submitted that  Page 6 of 13 O/IAAP/85/2014 JUDGMENT the   very   fact   that   the   order   passed   by   the     Court   under  section 8 is not made appealable would demonstrate that  any consideration under such application is only tentative.  He   alternatively   submitted   that   in   view   of   arbitration  clause   contained   in   the   agreement   and   the   mandatory  provision of section 8(1) of the Act, the Courts committed  an error in not referring the dispute to the arbitrator. This  being   an   order   which   suffers   jurisdictional   error,   can   be  challenged in any collateral proceedings. In support of his  contentions,   counsel   relied   on   certain   decisions   which   I  would refer to at a later stage.

5. As noted earlier, facts are not in dispute. An MOU between  the petitioner and the respondent contained an arbitration  clause.   When   therefore,   the   respondent   filed   a   Summary  Suit against the petitioner for having failed to repay a sum  of Rs.25 lakhs  upon the petitioner's inability to supply the  scrap   material,   the   petitioner   pressed   in   service   such  arbitration clause and urged the  Court that entire dispute  be   referred   to   arbitration.   Such   application   came   to   be  dismissed by the Civil Court. Such order was also upheld  by the High Court. In view of such developments, the entire  dispute is now being examined by the  Court of competent  jurisdiction.   At   that   stage,   there   would   be   no   scope   for  appointment   of   an   arbitrator   to   look   into   the   very   same  disputes.   This   would   be   so   for   multiple   reasons.   Firstly,  law   does   not   recognise   the   concept   of   the   same   dispute  being dealt with and decided by parallel fora. In absence of  such  policy,  there  would  be a possible  conflict  of judicial  opinions. In this very case, if the request of the petitioner  for appointment of an arbitrator is accepted, the  arbitrator  Page 7 of 13 O/IAAP/85/2014 JUDGMENT would pass his award. The Civil Court also would proceed  with summary suit and pass its judgement and decree. In  case   of   divergent   view,   which   one   would   prevail   is   the  fundamental question.

 6. Secondly, the judgement of the learned Single Judge of this  Court cannot be questioned before me. The view expressed  by   the   learned   Single   Judge   having   achieved   finality,   for  want of further appeal, would bind the petitioner with all  its force. In essence, such judgement confirmed the view of  the   Civil   Court   that   the   disputes   are   not   required   to   be  referred   for   arbitration.   Whatever   be   the   logic   and   the  reasoning  of  such  view  expressed  by the  Civil  Court  and  this     Court,   I   simply   cannot   go   behind   such   orders,  Accepting the request of the petitioner for appointment  of  an arbitrator would disregard such binding decision which  binds not only me but more importantly the petitioner who  was party to such litigation. 

7. There is a fundamental difference between the reference of  a dispute for arbitration under section 8(1) of the Act and  appointment of an arbitrator under section 11(6) of the Act.  Various   parameters   for   examining   power  of   Chief   Justice  and his designatee under section 11(6) of the Act have been  discussed   and   decided   by   the   Constitutional   Bench  Judgement of the Supreme Court in case of  SBP & Co. v.  Patel Engineering Ltd and another  reported  in  (2005)  8  Supreme Court Cases 618.

 8. On the other hand in case of   Booz Allen and Hamilton  Inc v. SBI Home Finance Ltd & ors. reported in AIR 2011  Page 8 of 13 O/IAAP/85/2014 JUDGMENT Supreme Court 2507, in context of provisions contained in  section 8 of the Act, Supreme Court observed as under :

"20.   The   nature   and   scope   of   issues   arising   for  consideration in an application under section 11 of the Act  for appointment of arbitrators, are far narrower than those  arising   in   an   application   under   section   8   of   the   Act,  seeking   reference   of   the   parties   to   a   suit   to   arbitration.  While  considering  an application  under  section  11 of the  Act, the Chief Justice or his designate would not embark  upon   an   examination   of   the   issue   of   `arbitrability'   or  appropriateness  of adjudication  by a private  forum,  once  he finds that there was an arbitration agreement between  or   among   the   parties,   and   would   leave   the   issue   of  arbitrability for the decision of the arbitral Tribunal. If the  arbitrator wrongly holds that the dispute is arbitrable, the  aggrieved  party will have to challenge the award by filing  an  application  under  section  34  of  the  Act,  relying  upon  sub­section  2(b)(i) of that section.  But where the issue of  `arbitrability' arises in the context of an application under  section   8   of   the   Act   in   a   pending   suit,   all   aspects   of  arbitrability have to be decided by the court seized of the  suit, and cannot be left to the decision of the Arbitrator.  Even   if   there   is   an   arbitration   agreement   between   the  parties,   and   even   if   the   dispute   is   covered   by   the  arbitration   agreement,   the   court   where   the   civil   suit   is  pending, will refuse an application under Section 8 of the  Act, to refer the parties to arbitration, if the subject matter  of   the   suit   is   capable   of   adjudication   only   by   a   public  forum or the relief claimed can only be granted by a special  court or Tribunal. 
21. The   term   `arbitrability'   has   different   meanings   in  different contexts. The three facets of arbitrability, relating  to the jurisdiction of the arbitral   tribunal, are as under : 
(i)   whether   the   disputes   are   capable   of   adjudication   and  settlement  by arbitration?  That  is,  whether  the  disputes,  having   regard   to   their   nature,   could   be   resolved   by   a  Page 9 of 13 O/IAAP/85/2014 JUDGMENT private forum chosen by the parties (the arbitral tribunal)  or whether they would exclusively fall within the domain of  public fora (courts). (ii) Whether the disputes are covered  by   the   arbitration   agreement?   That   is,   whether   the  disputes   are   enumerated   or   described   in   the   arbitration  agreement   as   matters   to   be   decided   by   arbitration   or  whether   the   disputes   fall   under   the   `excepted   matters'  excluded   from   the   purview   of   the   arbitration   agreement. 
(iii)   Whether   the   parties   have   referred   the   disputes   to  arbitration?   That   is,  whether   the  disputes   fall  under  the  scope   of   the   submission   to   the   arbitral   tribunal,   or  whether   they   do   not   arise   out   of   the   statement   of   claim  and the counter claim filed before the arbitral tribunal. A  dispute, even if it is capable of being decided by arbitration  and falling within the scope of arbitration agreement, will  not be `arbitrable' if it is not enumerated in the joint list of  disputes referred to arbitration, or in the absence of such  joint   list   of   disputes,   does   not   form   part   of   the   disputes  raised in the pleadings before the arbitral tribunal. 

22. Arbitral tribunals are private fora chosen voluntarily by  the parties to the dispute,  to adjudicate their disputes in  place   of   courts   and   tribunals     which   are   public   fora  constituted   under  the  laws  of  the  country.  Every  civil   or  commercial dispute, either contractual or non­contractual,  which can be decided by a court, is in principle capable of  being   adjudicated   and   resolved   by  arbitration   unless   the  jurisdiction   of   arbitral   tribunals   is   excluded   either  expressly   or   by   necessary   implication.   Adjudication   of  certain   categories   of   proceedings   are   reserved   by   the  Legislature exclusively for public fora as a matter of public  policy.   Certain   other   categories   of   cases,   though   not  expressly reserved for adjudication by a public fora (courts  and   Tribunals),   may   by   necessary   implication   stand  excluded  from  the  purview  of  private  fora.  Consequently,  where the cause/dispute is inarbitrable, the court where a  suit   is   pending,   will   refuse   to   refer   the   parties   to  arbitration, under section 8 of the Act, even if the parties  might   have   agreed   upon   arbitration   as   the   forum   for  Page 10 of 13 O/IAAP/85/2014 JUDGMENT settlement of such disputes. The well recognized examples  of   non­arbitrable   disputes   are   :   (i)   disputes   relating   to  rights   and   liabilities   which   give   rise   to   or   arise   out   of  criminal   offences;   (ii)   matrimonial   disputes   relating   to  divorce, judicial separation,  restitution  of conjugal rights,  child   custody;   (iii)   guardianship   matters;   (iv)   insolvency  and winding up matters; (v) testamentary matters (grant of  probate,   letters   of   administration   and   succession  certificate);  and  (vi)  eviction  or tenancy  matters  governed  by   special   statutes   where   the   tenant   enjoys   statutory  protection   against   eviction   and   only   the   specified   courts  are   conferred   jurisdiction   to   grant   eviction   or   decide   the  disputes." 

 9. If   the     Civil   Court   had   accepted   the   reference   of   the  petitioner   for   referring   the   disputes   to   arbitrator,   the  question of such a decision being summary and, therefore,  not   having   achieved   finality   would   perhaps   be   open   to  further  debate  before  the  arbitrator  in terms  of  section  8  read with section 16 of the Act. But when the Civil  Court  passes an order refusing to refer the matter for arbitration  in the pending civil proceedings rejecting application of the  defendant,   such   decision   achieves   finality.   Such   decision  cannot  be allowed  to be tested  before  an arbitrator  upon  seeking   reference   under   section   11(6)   of   the   Act,   urging  him to go into the question of his own jurisdiction  under  section 16 of the Act. Any such view, as noted above, would  give   rise   to   two   parallel   proceedings   with   respect   to   the  same subject matter. 

 10. One   may   now   refer   to   the   decisions   cited   by   the  counsel for the petitioner :

Page 11 of 13
      O/IAAP/85/2014                                      JUDGMENT




1)        In   case   of  Hindustan   Petroleum   Corpn.   Ltd.   v. 

Pinkcity   Midway   Petroleums  reported   in   (2003)   6  Supreme Court Cases 503 , it was held and observed that  if   there   is   any   objection   as   to   the   applicability   of   the  arbitration  clause,  the same  will have to be raised  before  the   Arbitral   Tribunal.   The   Supreme   Court   relied   on   the  decision   in   case   of  Konkan   Rly.   Corpn.   Ltd   v.   Rani  Construction (P) ltd. reported in (2002) 2 SCC 388 which  was reversed by a later decision in case of   SBP & Co. v.  Patel Engineering Ltd and another  (supra). In paragraph  24 of the judgement  on which  reliance  was placed  for by  the counsel  for the  petitioner,  all that was  held  was that  the High  Court ought to have exercised jurisdiction under  section 115 of the CPC considering the error committed by  the Court below. 

2) In case of  Havels India Limited v. Electrium Sales  Ltd  reported  in  (2013)  204  DLT  (CN  B)  1,  learned  Single  Judge of Delhi High Court observed that a conjoint reading  of sections 58 and 16 of the Act stipulate that upon being  satisfied   of   the   prima   facie   existence   of   an   arbitration  agreement, it is imperative for a Court to refer the parties  to   arbitration.   These   observations   however,   may   have  bearing   on   the   question   of   accepting   the   request   of   the  petitioner   for   referring   the   pending   civil   dispute   to  arbitrator. In view of the fact that such issue has achieved  finality,   would   have   no   application   on   the   present  proceedings.  

3)  In   case   of  Amrit   Bhikaji   Kale   and   others   v.  Kashinath   Janardhan   Trade   and   another  reported   in  Page 12 of 13 O/IAAP/85/2014 JUDGMENT (1983)  3 Supreme  Court  Cases  437,    the  Supreme  Court  upheld the view of the High  Court that order passed by the  Tribunal   was   null   and   void,   proceeding   on   an   erroneous  assumption of a jurisdictional fact. On such basis, counsel  tried   to   canvas   that   the   order   for   non   reference   to   the  arbitrator should be ignored since it lacks any jurisdiction.  For the same purpose, reliance was also placed on decision  in   case   of  Sushil   Kumar   Mehta   v.   Gobind   Ram  Bohra(dead)   through   his   Lrs.  reported   in   (1990)   1  Supreme   Court   Cases   193.   However,   such   orders   have  been passed by the Courts of competent  jurisdiction.  The  petitioner   having   not   carried   the   matter   further,   cannot  wish away the effect of such orders by simply requesting to  ignore them.

 11. In the result, arbitration petition is dismissed.

(AKIL KURESHI, J.) raghu Page 13 of 13