Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Calcutta High Court (Appellete Side)

Amit Chandra & Ors vs Panihati Municipality & Ors on 12 September, 2014

Author: Debasish Kar Gupta

Bench: Debasish Kar Gupta

                                                            1


 12.09.2014 
    srm 
                                            W.P. No. 19648 (W) of 2014 

                                               Amit Chandra & Ors. 

                                                        Versus 

                                           Panihati Municipality & Ors. 
                                                             
                                                             



                      Mr. Pratik Dhar, 
                      Mr. Ritwik Pattanayak, 
                
                                                                                 ...For the Petitioners. 
                      Mr. Prity Bhusan Chakraborty, 
                      Mr. Bikash Kumar Chattopadhyay 
                                                                               ...For the Municipality. 
                      Mr. Prantick Ghosh 
                                                               ...For the Respondent Nos.5 & 6. 
 

Let affidavit‐in‐opposition filed by the respondent Nos.1, 2, 3 and 4 and  replies thereto filed by the petitioners be kept on record.  

This  writ  application  is  directed  against  an  order/notice  passed  by  the  respondent  No.3  under  Memo  No.PM/Genl./OSD/Illegal  Const./2014‐15/87/1  dated April 23, 2014. The above order/notice was served upon the petitioners  invoking  the  provisions  of  Section  218  of  the  West  Bengal  Municipality  Act,  1993  (hereinafter  referred  to  as  the  said  Act,  1993)  for  demolition  of  building  and  removal  of  the  illegal  construction  from  the  encroached  area  of  common  passage  within  one  month  from  date  and  failure  of  which  the  appropriate  steps would be taken by the respondent‐Municipality.  2 It is submitted by Mr. Pratik Dhar, learned Senior Advocate appearing  on behalf of the petitioners, that the above notice cannot be sustained in law on  the following grounds: 

(1) Though a reply of a communication dated February 27, 2014 was submitted  by  the  petitioners  it  was  alleged  in  the  impugned  communication  that  no  explanation in reply to the same had been given by the petitioners.  
(2) The  communication  dated  March  8,  2014  was  not  served  upon  the  petitioners  at  any  point  of  time.  Therefore,  the  question  of  giving  explanation to the above communication does not arise. 
(3) The above order was passed under the provisions of Section 214 of the said  Act, 1993. The above section prescribes the entire procedure for demolition  of unauthorised construction but from the above notice nothing is evident  in  the  impugned  notice/order  to  give  opportunity  to  the  petitioners  with  regard to the alleged unauthorised construction. 
(4) The  above  order  was  passed  without  jurisdiction  in  view  of  the  admitted  fact  that  the  above  section  prescribes  the  procedure  to  be  adopted  by  the  Board  of  Councillors  of  a  Municipality  in  a  case  of  unauthorised  construction.  Admittedly  the  impugned  order  was  passed  under  the  provisions  of  Section  218  of  the  said  Act  but  it  was  passed  by  the  3 respondent No.3 having no jurisdiction to take any action under the above  provisions.  
(5) A  civil  suit  bearing  Suit  No.476  of  2013  is  pending  before  the  1st  Court  of  Civil  Judge,  Senior  Division  at  Barasat  and  the  alleged  encroached  area  concerned is the subject matter of declaration of title and ownership of that  area concerned. Therefore, the action of the Municipality to take a decision  with regard to the title, ownership of the area under reference was bad in  law during the pendency of the above suit. 

It is submitted by Mr. Prantick Ghosh, learned Advocate appearing on  behalf of the respondent Nos.5 and 6, that assuming but not admitting that the  impugned  notice  cannot  be  sustained  in  law.  There  is  no  bar  and/or  impediment  to  proceed  afresh  in  the  matter  by  the  respondent‐Municipality  notwithstanding the fact of pendency of the suit under reference. According to  him,  the  subject  matter  involved  in  the  above  suit  has  no  nexus  with  the  encroached area in respect of which the impugned order was passed. 

In  compliance  of  the  order  dated  August  22,  2014,  the  Secretary  of  Panihati Municipality is present before this Court today with relevant records.  

Mr.  Prity  Bhusan  Chakraborty,  learned  Advocate  appearing  on  behalf  of  the  respondent‐Municipality,  submits,  on  instruction,  that  the  impugned  order/notice was issued in exercise of power conferred under sub‐section (5) of  4 Section  218  of  the  said  Act,  1993.  According  to  him,  this  writ  application  is  premature  and  a  final  decision  has  yet  to  be  taken  by  the  Municipality  adhering to the other provisions of the above section. 

I have heard the learned Counsel appearing for the respective parties as  also I have considered the facts and circumstance of this case. 

Considering  the  records  of  the  respondent‐Municipality  produced  before this Court I find no record that the reply of the petitioners dated March  5, 2014 submitted by the petitioners in respect of the notice dated February 27,  2014 was taken into consideration. It appears that the claim of the respondent  No.3  that  there  was  no  explanation  with  regard  to  the  above  notice  dated  February  27,  2014  is  not  correct.  No  material  is  produced  to  show  that  the  notice  dated  March  18,  2014  was  served  at  any  point  of  time  upon  the  petitioners.  

With  regard  to  the  jurisdiction  to  pass  the  impugned  order  the  provisions of Section 218 of the said Act, 1993, the above provisions are quoted  below: 

"218. Order for demolition or alteration of buildings in certain cases. -  (1) If the Board of Councillors is satisfied - 
(a) that the erect of any building -  
(i) has  been  commenced  without  obtaining  sanction  or  premises  under the law, or 
(ii) is  being  carried  on  or  has  been  completed  otherwise  than  in  accordance  with  the  particulars  on  which  such  sanction  or  5 permission  was  based,  or  after  such  sanction  or  permission  has  been lawfully withdrawn, or 
(iii) is  being  carried  on  or  has  been  completed  in  breach  of  any  provision contained in this Act or in the Schedule or in any rules  or regulations in this behalf, or 
(b) that  any  building  or  projection  exists  in  violation  of  any  condition,  direction or requisition lawfully given or made under this Act or the  rules or the regulations made thereunder, or 
(c) that any material alteration of, or addition to, any building has been  commenced or is being carried on or has been completed in breach  of any provision contained in this Act or the Schedule or in any rules  or regulations in this behalf,  it may, after giving the owner of the building a reasonable opportunity  of  being  heard,  make  an  order  directing  that  such  erection,  alteration,  addition  or  projection,  as  the  case  may  be,  or  so  much  thereof  as  has  been  executive  unlawfully,  be  demolished  or  altered  and,  upon  such  order,  it  shall  be  the  duly  of  the  owner  to  cause  such  demolition  or  alternation  to  the  satisfaction  of  the  Board  of  Councillors  within  such  period  as  may  be  fixed  in  this  behalf.  In  default,  such  erection,  alteration,  addition  or  projection,  as  the  case  may  be,  may  be  demolished or altered by the Board of Councillors at the expense of the  said owner. 
(2) The procedure relating to the opportunity of hearing to be given to  the owner of the building under sub‐section (1) shall be such as may be  prescribed. 
(3) An appeal against an order made by the Board of Councillors in this  behalf o shall lie with the [Court having jurisdiction].  [(4). *  *  *]. 
(5) Notwithstanding anything contained in the foregoing provisions  of  this section or elsewhere in this Chapter, if the Chairman‐in‐Council is  of opinion that immediate action is necessary in respect of any building  being constructed, or any work being carried on, in contravention of the  provisions'  of  this  Act,  it  may,  for  reasons  to  be  recorded  in  writing,  cause such building or work to be demolished forthwith."  
 

After  considering  the  above  provisions,  I  find  that  the  Board  of  Councillors of a Municipality is entitled to proceed under the provisions of the  6 above section. The respondent No.3 had no jurisdiction to take any decision or  to issue any notice in absence of a decision taken by the Board of Councillors  of a Municipality. No material is produced before this Court to show that any  decision was taken in the matter by the Board of Councillors with regard to the  issue involves in this writ application.  

For  determining  the  rival  claim  of  the  petitioners  and  the  respondent‐ Municipality  as  to  whether  the  impugned  communication  is  an  order  or  a  notice the last paragraph of the impugned notice/order is quoted below: 

"You are therefore given this notice u/s 218 of the W.B.M. Act, 1993 for  demolition of building and removal of the illegal construction from the  encroached  area  of  common  passage  within  1(one)  month  from  this  date, otherwise legal action will follow." 
 

After considering the above paragraph, I have no hesitation to hold that  it  was  not  a  notice  to  show  cause  or  a  notice  for  giving  an  opportunity  of  hearing to the petitioners. This was an order for removal of illegal construction  on the encroached area. 

After  considering  the  subject  matter  involved  in  the  above  suit,  I  find  that  the  same  was  filed  by  the  petitioners  for  a  declaration  of  right  and  title  over  "B"  and  "C"  schedule  property  of  the  premises  under  reference.  After  considering  the  sketch  map  of  "B"  schedule  property  which  is  a  part  of  the  plaint  of  the  above  suit,  I  find  that  "B"  schedule  property  was  the  common  7 passage.  Therefore,  after  considering  the  order  impugned,  I  find  that  it  does  not lie on the mouth of the respondent Nos.5 and 6 that there is no nexus with  the impugned order and the title suit under reference. The right and title of an  immovable property  can be determined in a civil suit. Admittedly, the above  suit is still pending. Therefore, the impugned order is liable to be set aside on  that ground. 

In  accordance  with  the  provisions  of  Section  218  of  the  said  Act,  1993,  there  was  an  obligation  on  the  part  of  the  respondent‐Municipality  to  give  reasonable  opportunity  of  being  heard  to  the  petitioners.  No  material  is  produced  before  this  Court  to  show  that  the  above  formality  has  been  complied with. 

In  view  of  the  discussions  and  observations  made  hereinabove,  the  impugned order dated April 23, 2014 is quashed and set aside. 

The  respondents  are  restrained  from  proceeding  further  in  the  above  matter till the disposal of the suit under reference.  

This writ application is, thus, disposed of. 

There will be, however, no order as to costs. 

Urgent photostat certified copy of this order be supplied to the parties,  if applied for, subject to compliance with all necessary formalities.        

( Debasish Kar Gupta, J. )