[Cites 0, Cited by 0] [Section 12] [Entire Act]

Union of India - Subsection

Section 12(2) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(2)The "uncontrollable factors" shall include but shall not be limited to the following:
(i)Force Majeure events.; and
(ii)Change in law.
Provided that no additional impact of time overrun or cost over-run shall be allowed on account of non-commissioning of the generating station or associated transmission system by SCOD, as the same should be recovered through Implementation Agreement between the generating company and the transmission licensee:Provided further that if the generating station is not commissioned on the SCOD of the associated transmission system, the generating company shall bear the IDC or transmission charges if the transmission system is declared under commercial operation by the Commission in accordance with second proviso of Clause 3 of Regulation 4 of these regulations till the generating station is commissioned:Provided also that if the transmission system is not commissioned on SCOD of the generating station, the transmission licensee shall arrange the evacuation from the generating station at its own arrangement and cost till the associated transmission system is commissioned.