Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 9, Cited by 0]

Bombay High Court

Gurukripa Communications Private ... vs Nutan Gupta And 2 Ors on 18 June, 2019

Author: G.S.Kulkarni

Bench: G.S. Kulkarni

  pvr                                    1                34arbap60-19.doc


                IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                      ORDINARY ORIGINAL CIVIL JURISDICTION

                        Arbitration Application NO. 60 OF 2019


 Gurukripa Communications Pvt.Ltd.                  ...Applicant
      Versus
 Nutan Gupta & Anr.                                 ...Respondents
                                    ----
 Ms.Shruti Sardesai with Prashant Beri I/b. Beri & Co., for the Applicant.

 Mr.Akash Rebello I/b. Pariket Shah, for Respondent Nos.1 and 2.
                                    -----
                                CORAM : G.S. KULKARNI, J.

                                     DATE :      18 June 2019
                                        ---
 P.C.;

 1.       Heard the learned Counsel for the applicant and the learned

 Counsel for the respondents.



 2.       This is an application filed under Section 11 of the Arbitration and

 Conciliation Act,1996 whereby the applicant has prayed for appointment

 of a sole arbitrator to adjudicate the disputes and differences between the

 parties, which have arisen under the Sellers' Deed of Indemnity dated 13

 April 2010 (for short the 'Deed of Indemnity'). The arbitration agreement

 between the parties is contained in clause 14 of the Deed of Indemnity

 which incorporates clause 8 of another agreement namely the Binding




::: Uploaded on - 04/07/2019                    ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                          2                  34arbap60-19.doc


 Memorandum of Understanding (for short 'the Binding MOU') being made

 applicable. Clause 14 of the Sellers Deed of Indemnity reads thus:-

                  "14.     Governing Law and Dispute Resolution.
                  The provisions of clause 8 of the Binding MOU shall apply mutatis
                  mutandis to this Deed."



 3.       Clause 8 as contained in Binding Memorandum Of Understanding

 (for short "the Binding MOU") to which the applicant is a party reads

 thus:-

                  "8.     This Binding MOU is subject to Indian law and subject to
                  the provisions for arbitration, the courts of Mumbai will have
                  exclusive jurisdiction thereon. Any dispute, disagreement or
                  difference arising between the parties hereto touching or
                  concerning this Binding MOU in any manner shall be referred to the
                  arbitration of a sole arbitrator to be appointed by the parties jointly,
                  failing which the sole arbitrator shall be appointed in accordance
                  with the Arbitration & Conciliation Act,1996. Such arbitration will
                  be held in accordance with the Arbitration & Conciliation Act,1996
                  or any statutory modification thereof for the time being in force.
                  Arbitration shall be held in Mumbai and shall be held in the English
                  language. The arbitrator shall have power to direct specific
                  performance."



 4.       It is the applicant's case that a show cause notice was issued by the

 Income Tax authorities stating that the applicant has failed to deposit TDS

 for the A.Y. 2009-10. Another show cause notice was issued for the A.Y.

 2010-11.          In September 2013 the applicant filed a compounding

 application under Section 279(2) of the Income Tax Act for the said

 assessment years. Thereafter on 2 August 2017 another notice was issued




::: Uploaded on - 04/07/2019                            ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                         3                 34arbap60-19.doc


 by the Income Tax officer making tax claims in relation to financial years

 2007-08, 2008-09 and 2009-10 against the applicant, which was replied

 by the applicant. Again a notice dated 6 October 2017 was issued to the

 applicant on the compounding application, proposing to levy fees on the

 applicant. The applicant ultimately paid the compounding fees in

 November 2017.

          On the above backdrop the applicant's advocates issued a notice to

 the respondent dated 30 November 2018 making a claim for an amount of

 Rs.21,17,239/- being the amount of the aggregate tax claim alongwith

 interest at the rate of 18% p.a. The relevant paragraphs of this notice read

 thus:-

                  "6.      As the Aggregate Tax Claim relates to the taxable period
                  prior to the BTA Closing, pursuant to the provisions of the aforesaid
                  Sellers's Indemnity, you are liable to indemnify our Client for the
                  same, together with all and any other losses, liabilities, damages,
                  claims, fines, fees, penalties, interest obligations and expenses (as
                  detailed in the Sellers' Indemnity) that have been incurred by our
                  Client in connection with the Aggregate Tax Claim. In spite of
                  receiving the Notice of Claim, you have failed to replay the
                  Aggregate Tax Claim within the time period stipulated in the
                  Sellers' Indemnity.

                  7.       Additionally, kindly note that while the amount held in the
                  escrow account created pursuant to the Escrow Agreement dated
                  June 10, 2010 between yourselves, Turmeric Advisory Private
                  Limited and our Client, has been released to Nutan Gupta, the
                  Aggregate Tax Claim is pending satisfaction and the escrow amount
                  was also released as a good faith gesture with the condition that
                  any future assessment of taxes/penalties will be duly satisfied b
                  you. Further, the rights and obligations of the parties under the
                  Seller's Indemnity continue to subsist.




::: Uploaded on - 04/07/2019                          ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                         4                  34arbap60-19.doc

                  8.       Accordingly, we are instructed to call upon you to repay our
                  Client the total sum of Rs.21,17,239 (Rupees Twenty One lakhs
                  Seventeen Thousand Two Hundred and thirty Nine), along with
                  interest at the rate of 18% per annum, within 7 (seven) days of
                  receipt of this notice, failing which our Client will be constrained to
                  initiate such legal proceedings (including arbitration), as deemed fit
                  for recovery of the amount together with the said interest, at your
                  sole risk as to the costs and consequences thereof, which you may
                  please note.

                  9.      You also remain liable to our Client for payment of any
                  other losses, liabilities, damages, claims, fines, fees, penalties,
                  interest obligations and expenses (as detailed in the Sellers'
                  Indemnity) that have been or may be incurred in connection with
                  the Aggregate Tax Claim or any other tax claims for the period prior
                  to and up to the BTA Closing and our Client reserves their right to
                  claim the same from you.

                  10.     Additionally, kindly note that certain compounding fee
                  related demands relating to the taxable period prior to the BTA
                  Closing, are pending final assessment by the tax authorities, as on
                  date. Therefore, you will be liable, pursuant to the provisions of the
                  aforesaid Sellers' Indemnity, to indemnify us for such further
                  amounts, if any, paid by us going forward.

                  11.     Further, please note that this notice has been issued without
                  prejudice to the rights and contentions of our Client under
                  applicable law or the Sellers' Indemnity. Our client expressly
                  reserves all their rights in the matter.



 5.       As the above advocates' notice was not responded, the applicant's by

 their advocate's notice dated 2 January 2019 invoked the arbitration

 agreement and called upon the respondent to appoint an arbital tribunal

 to adjudicate the disputes between the parties. As the respondents failed

 to respond to the said invocation notice, the present application has been

 filed.




::: Uploaded on - 04/07/2019                           ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                        5                 34arbap60-19.doc


 6.       Learned Counsel for the respondents at the outset has opposed

 appointment of a sole arbitrator to arbitrate the disputes between the

 parties referring to clause 4(b) of the Sellers Indemnity Agreement, which

 reads thus:-

                   "4.    Time Limit for Claims
                          The right of the Buyer to claim indemnity in terms of this
                   Deed will be available in relation to all claims made under the
                   Binding MOU or the Letter of Assignment and notified to the
                   Indemnifying Parties:
                   (a)    .............
                   (b)    for any claim relating to tax, within eight years and 3
                   months from the Closing Date under the Binding MOU; and
                   (c)    ............           "                   (emphasis supplied)


 7.       The principal contention as urged by the learned Counsel for the

 respondent is that the Sellers Indemnity Agreement itself ceases to exist in

 view of the clause 4(b) above, and hence, the arbitration agreement as

 contained therein, would also cease to exist. In support of this contention,

 learned Counsel for the respondents has placed reliance on the decision in

 "Union of India Vs. Kishorilal Gupta & Bros."1



 8.       On a reading of clause 4(b), I am not persuaded to accept the

 submission as made on behalf of the respondents. Clause 4(b) of Sellers'

 Deed of Indemnity provides for a right of the buyer to claim indemnity in

 terms of the deed, to be available in relation to all claims made under the

 1    AIR 1959 SC 1362




::: Uploaded on - 04/07/2019                         ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                  6                34arbap60-19.doc


 Binding MOU or the Letter of Assignment and notified to the indemnifying

 parties, for any claim relating to tax within eight years and three months,

 from the closing date which was extended to 30 June,2010 under the

 binding MOU. It appears from the record that the disputes between the

 parties under these agreements in question have arisen on account of the

 tax liability, which was ultimately met by the applicant on 18 November

 2018 and thereafter the applicant had made a claim against the

 respondent. Thus the contention as urged on behalf of the respondent

 referring to clause 4(b) (supra) to oppose this application, prima facie

 appears to be not well founded. At the most this can be a defence of the

 respondents to deny liability to make any payment and indemnify the

 applicant under the Deed of Indemnity. An interpretation that the said

 clause extinguishes the existence of the arbitration agreement between the

 parties, cannot be accepted, and more so considering the plain language of

 the said clause.


 9.       It is now well settled that when a contract contains an arbitration

 agreement, it is a collateral term whereby the parties agree to resolution

 of dispute under the contract by taking recourse to arbitration. The

 arbitration agreement is required to be considered as a stand-alone

 agreement independent from its underlying contract. In Reva Electric Car




::: Uploaded on - 04/07/2019                  ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                         7                  34arbap60-19.doc


 Co.(P) Ltd. Vs. Green Mobil2 the Supreme court held that the arbitration

 agreement continues to be enforceable notwithstanding a declaration of

 the contract being held to be null and void. In Today Homes &

 Infrastructure Pvt.Ltd. Vs. Ludhiana Improvement Trust and Anr. 3 the

 Supreme Court reiterating the above principles observed thus:-

                  "14.    The same reasoning was adopted by a member of this Bench
                  (S.S.Nijjar, J.), while deciding Reva Electric Car Co.(P)Ltd vs. Green
                  Mobil, wherein the provisions of Section 16(1) in the backdrop of
                  the doctrine of kompetenz kompetenz were considered and it was
                  inter alia held that under Section 16(1), the legislature makes it
                  clear that while considering any objection with regard to the
                  existence or validity of the arbitration agreement, the arbitration
                  clause, which formed part of the contract, had to be treated as an
                  agreement independent of the other terms of the contract.
                  Reference was made in the said judgment to the provisions of
                  Section 16(1)(b) of the 1996 Act, which provides that even if the
                  Arbitral Tribunal concludes that the contract is null and void, it
                  should not result, as a matter of law, in an automatic invalidation of
                  the arbitration clause. It was also held that Section 16(1)(a) of the
                  1996 Act presumes the existence of a valid arbitration clause and
                  mandates the same to be treated as an agreement independent of
                  the other terms of the contract. By virtue of Section 16(1)(b) of the
                  1996 Act, the arbitration clause continues to be enforceable,
                  notwithstanding a declaration that the contract was null and void.


 10.      In "Enercon (India) Limited V. EnerconGmbh"4 the Supreme Court

 in this context has observed as under:-

                  "83.     The concept of separability of the arbitration clause/
                  agreement from the underlying contract is a necessity to ensure that
                  the intention of the parties to resolve the disputes by arbitration
                  does not evaporate into thin air with every challenge to the legality,
                  validity, finality or breach of the underlying contract. The Indian
                  Arbitration Act,1996, as noticed above under Section 16 accepts the

 2   (2012)2 SCC 93
 3   (2014)5 SCC 68
 4   (2014)5 SCC 1




::: Uploaded on - 04/07/2019                           ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                         8                    34arbap60-19.doc

                  concept that the main contract and the arbitration agreement form
                  two independent contracts. Commercial rights and obligations are
                  contained in the underlying, substantive, or the main contract. It is
                  followed by a second contract, which expresses the agreement and
                  the intention of the parties to resolve the disputes relating to the
                  underlying contract through arbitration. A remedy is elected by
                  parties outside the normal civil court remedy. It is true that support
                  of the national courts would be required to ensure the success of
                  arbitration, but this would not detract from the legitimacy or
                  independence of the collateral arbitration agreement, even if it is
                  contained in a contract, which is claimed to be void or voidable or
                  unconcluded by one of the parties."



 11.       In   "Ashapura      Mine-Chem    Ltd.   Vs.     Gujarat      Mineral     Development

 Corporation"5 in paragraphs 21 and 27 the Supreme Court has observed thus:-

                  "21.    In Today Homes and Infrastructure (p) Ltd., this Court
                  approved the statement of law stated by the learned Judge of this
                  Court in Reva Electric Car Co. (P) Ltd., para 14 can be usefully
                  referred to which reads as under:
                  (Today Homes and Infrastructure (P) Ltd. Vase, SCC p.73)
                  "14.    The same reasoning was adopted by a member of this Bench
                  (S.S.Nijjar, J.), while deciding Reva Electric Car Co.(P)Ltd vs. Green
                  Mobil, wherein the provisions of Section 16(1) in the backdrop of
                  the doctrine of kompetenz kompetenz were considered and it was
                  inter alia held that under Section 16(1), the legislature makes it
                  clear that while considering any objection with regard to the
                  existence or validity of the arbitration agreement, the arbitration
                  clause, which formed part of the contract, had to be treated as an
                  agreement independent of the other terms of the contract. Reference
                  was made in the said judgment to the provisions of Section 16(1)
                  (b) of the 1996 Act, which provides that even if the Arbitral
                  Tribunal concludes that the contract is null and void, it should not
                  result, as a matter of law, in an automatic invalidation of the
                  arbitration clause. It was also held that Section 16(1)(a) of the
                  1996 Act presumes the existence of a valid arbitration clause and
                  mandates the same to be treated as an agreement independent of
                  the other terms of the contract. By virtue of Section 16(1)(b) of the
                  1996 Act, the arbitration clause continues to be enforceable,
                  notwithstanding a declaration that the contract was null and void.
                  ...............

                  27.      Having gone through the said paragraphs, we do not find any

 5     (2015)8 SCC 193




::: Uploaded on - 04/07/2019                             ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                        9                 34arbap60-19.doc

                  position in law contrary to what has been stated in Today Homes and
                  Infrastructure (P) Ltd., Reva Electric Car Co.(P) Ltd. And Enercon
                  (India) Ltd."


 12.      The decision of the Supreme Court in Union of India Vs. Kishorilal

 Gupta & Bros. (supra) as relied on behalf of the respondents, in the facts

 of the case is not applicable inasmuch as the present case is not a case

 where the Sellers Deed of Indemnity is superseded by the parties by

 entering into a fresh agreement and which would give rise to a situation

 that the original agreement itself is not in existence. In fact in paragraph

 10 of the said decision, the Supreme Court has clearly recognised that the

 arbitration clause is a collateral term in a contract as distinguished from

 its substantive terms, although it is an integral part of the contract.



 13.      Considering the clear position that both the agreements namely

 binding MOU and Sellers Deed indemnity are required to be read together

 in view of the incorporation of the arbitration agreement as contained in

 Clause 8 of the MOU in Clause 14 of the Deed of Indemnity, I am clearly

 of the opinion that there exists an arbitration agreement between the

 parties. The applicant has lawfully invoked the arbitration agreement by

 its advocate's notice dated 2 January 2019, however, unsuccessfully. In

 these circumstances arbitral tribunal needs to be appointed by allowing




::: Uploaded on - 04/07/2019                         ::: Downloaded on - 14/07/2019 04:45:52 :::
   pvr                                  10                 34arbap60-19.doc


 this application.



 14.      At this stage, Mr.Rebello, learned Counsel for the respondents

 makes suggestion that already an arbitration between the parties under

 another agreement between the parties (EMGEE Communications Pvt.Ltd.

 And Gurukripa Communications Pvt.Ltd.) is already in progress before a

 learned sole arbitrator and considering the facts and circumstances, it is

 his suggestion that the disputes between the parties under the present

 proceedings be also referred to the same arbitrator for effective

 adjudication of the disputes. Learned Counsel for the applicant would also

 fairly concede to this suggestion as urged on behalf of the respondents.

 The application is therefore, required to be disposed of in the following

 terms:-

                                     ORDER

(i) Ms.Gulnar Mistry, Advocate of this Court is appointed as a prospective sole arbitrator to arbitrate the disputes and differences between the parties under the Sellers' Deed of Indemnity dated 13 April 2010;

(ii) The learned prospective sole Arbitrator, fifteen days before entering the arbitration reference, shall forward a statement of disclosure as per ::: Uploaded on - 04/07/2019 ::: Downloaded on - 14/07/2019 04:45:52 ::: pvr 11 34arbap60-19.doc the requirement of Section 11(8) read with Section 12(1) of the Arbitration and Conciliation Act,1996, to the Prothonotary & Senior Master of this Court, to be placed on record of this application with a copy to be forwarded to both the parties;

(iii) The fees payable to the arbitral tribunal shall be governed in accordance with the fees prescribed under the Bombay High Court (Fees Payable to Arbitrators) Rules,2018;

(iv) At the first instance, the parties shall appear before the prospective sole arbitrator within 10 days from today on a date which may be mutually fixed by the prospective sole arbitrator;

(v) All contentions of the parties are expressly kept open;

(vi) The application is disposed of in the above terms. No costs.

(vii) Office to forward a copy of this order to the learned Arbitrator on the following address:-

First Floor, Ramnimi, Fort, Cawasji Patel Streel, Mumbai.
Mobile: 9820776272 E-mail: [email protected] (G.S.Kulkarni, J.) ::: Uploaded on - 04/07/2019 ::: Downloaded on - 14/07/2019 04:45:52 :::