Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 1]

Income Tax Appellate Tribunal - Mumbai

Ito-1(1)(1), Mumbai vs M/S Aristo Shelters Pvt. Ltd., Mumbai on 6 February, 2023

              IN THE INCOME TAX APPELLATE TRIBUNAL
                    MUMBAI BENCH "A", MUMBAI

BEFORE SHRI S. RIFAUR RAHMAN, HON'BLE ACCOUNTANT MEMBER AND
    SHRI SANDEEP SINGH KARHAIL, HON'BLE JUDICIAL MEMBER

               ITA.NO.1931/MUM/2019 (A.Y: 2013-14)

    Income Tax Office -1(1)(1)       v.   M/s Aristo Shelters Pvt. Ltd
    579, 5th Floor, Aayakar Bhavan        43/11, Rajabahadur building
    M.K. Road, Mumbai- 400020             Tamrind Lane, Fort
                                          Mumbai- 400001

                                          PAN: AAHCA7596F
    (Appellant)                           (Respondent)

               ITA.NO.5181/MUM/2019 (A.Y: 2014-15)

    Income Tax Office -1(1)(1)       v.   M/s Aristo Shelters Pvt. Ltd
    579, 5th Floor, Aayakar Bhavan        8th Floor, Aristo House
    M.K. Road, Mumbai- 400020             N.S. Phadke Road
                                          Near E/W Flyover, Andheri (E)
                                          Mumbai- 400069

                                          PAN: AAHCA7596F
    (Appellant)                           (Respondent)


    Assessee Represented by           :   Shri V. G. Ginde &
                                          Shri Kumar Kale
    Department Represented by         :   Shri R. S. Srivastav


    Date of Hearing                   :   15.11.2022
    Date of Pronouncement             :   06.02.2023
                                     2
                                                   ITA.NO.1931 & 5181/MUM/2019
                                                      M/s Aristo Shelters Pvt. Ltd

PER S. RIFAUR RAHMAN (AM)

1.   These appeals are filed by the revenue against different orders of

the Learned Commissioner of Income Tax (Appeals)-2, Mumbai

[hereinafter in short "Ld.CIT(A)"] dated 03.01.2019 and 09.05.2019 for

the A.Ys.2013-14 and 2014-15 respectively.



2.   Since the issues raised in both these appeals are identical, therefore,

for the sake of convenience, these appeals are clubbed, heard and

disposed off by this consolidated order. We are taking Appeal in ITA.No.

1931/MUM/2019 for Assessment Year 2013-14 as a lead appeal.



3.   Brief facts of the case are, assessee filed its return of income on

30.09.2013 declaring total income of ₹.NIL. The case was selected for

scrutiny and notices u/s.143 (2) and 142(1) of Income-tax Act, 1961

(in short "Act") were issued and served on the assessee along with

questionnaire. In response to the notices, AR of the assessee attended

and submitted the relevant information as called for.



4.   During the assessment proceedings, while verifying the details

submitted by the assessee, Assessing Officer observed that in the

F.Y.2011-12 assessee has transferred its land purchased at a cost of
                                     3
                                                  ITA.NO.1931 & 5181/MUM/2019
                                                     M/s Aristo Shelters Pvt. Ltd

₹.201 Crores from M/s. Bombay Industrial Corporation in F.Y.2009-10 to

Slum Rehabilitation Authority ("SRA") for a consideration in terms of

Transferable Development Rights (TDR) of 16,86,083 sq. ft. The assessee

has made a multipartite agreement between M/s Bombay Industrial

Corporation, Assessee and SRA on 30.04.2011. As per the agreement, the

project is proposed as per Clause 3.11 [under regulation 33(10)] of

Development Control Regulation for Greater Mumbai, as per which

assessee will convey the land to SRA and then construct tenements for

Project Affected People as per Government directive and hand-over the

constructed tenements to the Project Implementing Authority, viz. Slum

Rehabilitation Authority. Assessing Officer observed that, in lieu of the

above, the company will receive TDR in the ratio of 1:1 for land portion

surrendered to SRA and in the ratio of 1:1.33 (1.33 times) for constructed

area which can be sold to other developers in the open market to generate

revenue.



5.   Further, Assessing Officer observed that Assessee has to construct

59 buildings (G+24) (having 8582 Tenements) and other buildings

comprising of one (1) school, one (1) Primary Health Care Centre & one

(1) Dispensary, with a total construction area of 83,55,246 sq.ft. and is
                                           4
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

entitled to receive a total of 1,27,98,560 sq.ft. of TDR. Out of the Total

land TDR 16,86,083 sq.ft receivable, the assessee has received Land TDR

of 1264561.93 sq. ft till 27.07.2012. The said land TDR received was sold

by assessee company in the open market as under: -


             Assessment Year            TDR              Amount
                AY. 2012-13         1,78,790sqft    Rs. 39,72,94,104/-
               A. Y. 2013-14       10,85,664 sq ft Rs. 2,19,52,15,898/-


6.     Further, Assessing Officer observed that the stages of release of

TDR as under: -

       (A) Land TDR is to be released in the following tranches:

                                                   Land TDR
                                                                      Land
                                                      to be
       Sr. No.               Stages                                    TDR
                                                    released
                                                                     (Sq. ft.)
                                                    Sq. Mtr.
          1.   For the Land under PAP Tenement 89061.89              9,58,662
               buildings
          2.   For the area kept as Buffer Zone as 28418.78          3,05,900
               per the directions issued in the
               hearing, under no SRA/Eng/Destk-
               1/563 dated 23/04/2012
          3.   Against Amenity space CL. 57(4)(C)   39160.23         4,21,521
               Sub-Total (A): TOTAL LAND TDR                        16,86,083

       (B)   Construction TDR is to be released in the following tranches:-

                                                      % of Cons.
 Sr.                                                                    Cons. TDR
                                                      TDR to be
 No.                     Items                                           (Sq.ft.)
                                                       released
  1. On completion of Plinth                             18%             20,00,246
  2. On completion of RCC Work upto 12m slab             31%             34,44,868
     (Mesonry Work, Internal & External Plaster will
     be carried out proportionately with the slab due
     to aluminum from work system)
                                          5
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

                                                          % of Cons.
 Sr.                                                                    Cons. TDR
                                                          TDR to be
 No.                         Items                                       (Sq.ft.)
                                                           released
  3.   On completion of RCC Work upto 24 slab     th         31%         34,44,868
       (Mesonry Work, Internal & External Plaster will
       be carried out proportionately with the slab due
       to aluminum from work system)
  4.   Building external CPVC Vertical lines                  2%         2,22,249
  5.   On completion Flooring & Internal Plumbing             8%         8,88,998
       Work (Except sanitary ware, Drainage, Water,
       Electricity, Doors, Windows, Painting, Polishings,
       Lifts, Balance RCC Work etc.)
  6.   On completion the building & obtaining O.C.            8%-        8,88,998
  7.   Retention at the time of occupation to be             2% -        2,22,250
       released only defect liability period of 2Years is
       over.
       Sub - Total (B): TOTAL CONSTRUCTION TDR               100%      1,11,12,477
       GRAND TOTAL (A+ B) TOTAL TDR                                    1,27,98,560


7.     On verification of Balance Sheet and Profit and Loss account and its

schedules filed by the assessee, it was observed by the Assessing Officer

that the assessee has not recorded any transactions in Profit and Loss

Account and declared ₹.NIL profit of the business. On verification of the

balance sheet, it was observed that the assessee has increased its WIP

Account for Chembur site by debiting direct expenses such as purchases,

labour charges, and by debiting administrative expenses such as financial

expenses, selling and distribution expenses. The WIP for the year was

declared by the assessee at ₹.21,75,00,546/-. The above said sum of WIP

along with brought forward WIP of ₹.23,07,302,814/- has been reduced

from the TDR sale declared at ₹.2,19,52,15,898/- and thus the closing

WIP was declared at ₹.32,95,87.461/- Assessing Officer observed that
                                           6
                                                           ITA.NO.1931 & 5181/MUM/2019
                                                              M/s Aristo Shelters Pvt. Ltd

since the assessee has sold the TDR received in lieu of transfer of land to

SRA and the income from sale of TDR so received constitutes the income

of the assessee for the year under consideration and thus by reducing the

amount received as against sale of TDR the assessee has not followed

correct method of accounting. Accordingly, a show-cause notice was

issued asking for clarification.



8.    In response, assessee vide letter dated 18.03.2015 submitted as

under: -

      "With reference to above subject, we submit as under-

      We have perused your aforesaid letter dated 10/02/2016.

      1.     We find that your office would like to follow Method of
      Accounting for transactions on Transfer of Development rights'
      (TDR) available from project at Chembur, Mumbai as devised by your
      office and referred to while passing Assessment Order for the A.Y.
      2012-13.

      2.     At outset, we submit that we have preferred Appeal before
      CIT(A) against above referred Asst Order for AY 2012-13 AND do not
      agree with Department's Stand. We submit that method of
      Accounting followed by us is correct method of Accounting per
      attached detailed explanatory note (Exhibit-1).

      Note explaining method of accounting employed by the
      company

      1.     Facts:

      Briefly stated, the material facts of the case are as under.

      i)     The assessee company is engaged in the business of real
      estate development. During the course of its business, the company
                                     7
                                                   ITA.NO.1931 & 5181/MUM/2019
                                                      M/s Aristo Shelters Pvt. Ltd

 vide Agreement for Sale dated 5.2.2010 entered into with M/s.
 Bombay Industrial Corporation purchased land admeasuring
 approximately 1,56,640 sq. meters situate at CTS No. 619/A, 619/B,
 620/A, 621/A, 621/B, 621/C, 623/A1, 623/A2 and 623/B at Village
 Mahul, Chembur, Mumbai ("said land") for purchase of price of
 Rs.201 crores with a view to develop the same.

 ii)    The company had given a rehabilitation proposal to the Slum
 Rehabilitation Authority ("SRA") for development of the said land
 under provisions of Clause 3.11 read with Clause 3.5 & 3.9 (ii) of
 Appendix-IV of Development (Control & Regulations) Rule 33(10),
 by constructing certain number of tenements at its own cost to be
 handed over the Municipal Corporation of Greater Mumbai
 ("MCGM"), free of cost, which in turn would allot these tenements to
 the slum dwellers removed from hutments along water mains of
 MCGM. In lieu of this our company would get Transferable
 Development Rights ("TDR") from MCGM. This rehabilitation project
 was declared as a Vital Public Project by the Government of
 Maharashtra.

 iii)   By Letter of Intent ("LOP") dated 31.3.2011 issued by SRA,
 our company is to construct 9002 tenements and other amenities to
 be handed over to MCGM through SRA free of cost for which
 following TDR would be allotted to the company:-

(A) Land TDR                              Sq. Meters Sq. Ft
                      1. Project Affected   89,061.89    9,58,662
                      People Tenements
                      2. Buffer Zone Area   28,418.78    3,05,900
                      3. Amenity Portion    39,160.23    4,21,521
                      Total                            16,86,083
(B)   Construction                                    1,11,12,477
      TDR
                      Total                                 1,27,98,560

 iv)    Simultaneous with the issue LOI dated 31.3.2011, a
 multipartite Agreement ("the Agreement") was executed between
 M/s. Bombay Industrial Corporation (as "Vendors"), our company (as
 "Developers") and the SRA (as 'Purchaser') and the SRA (as "Project
 Implementing Authority") setting out the terms and conditions for
 development of the said land in accordance with the LOI dated
 31.3.2011. Clause (3) and (4) of the Agreement provide for
 consideration in the form of TDR to be allotted to our company
                                          8
                                                          ITA.NO.1931 & 5181/MUM/2019
                                                             M/s Aristo Shelters Pvt. Ltd

     described as "Rehabilitation Component and Land Component"
     respectively for the obligations undertaken by the company in
     implementing the rehabilitation scheme at the said land

     v)     The aforesaid LOI was amended from time to time by several
     supplementary LOIS, the last being LOI dated 16.6.2012, which
     modified the no. of tenements to be constructed by the company to
     8,399 and also other amenity tenements as per Clause (21) thereof.

     vi)    Clause (7) of the Agreement provides that the company shall
     be entitled to the benefit of TDR in the ratio of 1:1 in respect of the
     Land Component from the SRA, and the SRA will cause the MCGM of
     issue TDR in the form of Development Right Certificate ("DRC") in
     the name of the company in stages after the said land is transferred
     to SRA as specified in the Agreement. Clause (17) of the Agreement
     provides the time when the company will be entitled to the Land
     Component of TDR; while clause (18) of the Agreement provides the
     time when the company will be entitled to the Rehabilitation, Le.
     Construction Component of TDR. Clause (15) of the Agreement
     stipulates the compensation to be paid by the company to the SRA
     in case of default committed by the company in delaying the
     construction work.

     vii)  The company received the following TDR in respect of the
     Land Component:

Date of        Date of         Nature of TDR    TDR in Sq.             TDR in Sq.
Release        Receipt                          Meters                 Ft.
18.5.2011       16.9.2011      PAP Tenements- 17,810.00                1,91,706.84
                               part
18.6.2012        16.7.2012     Buffer Zone Area 28,418.78              3,05,899.75
26.6.2012        27.7.2012     PAP Tenements - 71,251.89               7,66,955.34
                               Balance
                               Total            1,17,480.67            12,64,561.93

     viii) The company has been consistently following project
     completion method for recognising revenue from this project.
     Consequently, all the expenses incurred on this project have been
     accumulated under the head "Work-in-Progress" till the completion
     thereof. The sales proceeds realized on sale of TDR during the
     construction period has been reduced from the cost of WIP, and the
     balance cost carried forward.
                                        9
                                                          ITA.NO.1931 & 5181/MUM/2019
                                                             M/s Aristo Shelters Pvt. Ltd

ix)     It is important to state that after 27.07.2012, the company
has not received any TDR. The said land being situated near HPCL
and BPCL Refineries, they have taken serious objections to our
project. Further, Public Interest Litigation involving our project is
pending before the Hon'ble Bombay High Court. In view of these
facts, the said project is couched in significant uncertainties at the
moment. The copies of litigation filed by f) HPCL V/s. The Slum
Rehabilitation Authority and Others including us is enclosed and (ii)
Public Interest Litigation No. 140 of 2006 filed by Janhit Munch &
Others V/s. MCGM, us and others - Volume-I & II enclosed.

2.    Issue:

In the letter dated 10/02/2016, you have raised the issue of method
of accounting qua this project. While our company did not recognise
any profit or loss during the year ended 31.3.2013, you have
proposed to invoke section 145(3) to compute profit of Rs.52.58
crores, as worked out in the said letter. We seriously object to this
proposal on the principles of accounting, among others, for the
following reasons:

3.    Submissions:

3.1 We have followed correct method of accounting:

We respectfully submit that there can be no issue about the method
of accounting followed by our company for this project. The Project
Completion Method ("PCM") is a recognised method accounting that
is followed by many enterprises operating in real estate business as
it is a scientific method that has stood the judicial scrutiny in a
number of precedents a few of which are mentioned as under:

(a)   CIT us. V. S. Dempo & Co. Pvt. Ltd. (1996) 131 CTR 203 (Bom)

(b)   Shapoorji Pallonji (Rajkot) Put. Ltd. vs. CIT (1994) 49 ITD 479 (Bom)

(c)   Nandi Housing Pvt. Ltd. vs. DCIT (2004) 2 SOT 395 (Bang)

(d)   DCIT vs. Ranka Developers (2006) 6 SOT 815 (Bang)

(e)   Haware Constructions (P) Ltd. vs. ПO (2011) 64 DTR
      (Mumbai) (Trib) 251

(f)   DCIT vs. Ankit Chirag Developers Pvt. Ltd. (2014) 40 CCH 018
      JodhTrib
                                    10
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

As per PCM, profit/loss of a project is recognised only on completion
of the given project, and until then the costs are accumulated as WIP
and advances received on account of any sales are carried forward
as liability in the balance sheet

In accordance with this method, our company has consistently, year
after year, taken all the costs to the WIP, and the proceeds realized
on sale of TDR deducted from the cost of WIP, there was no question
of recognising any profit or loss during the construction period until
the project is completed.

3.2 Land Component of TDR cannot be considered de hors
the total project:

The project under consideration is to develop/construct certain
number of tenements and other amenity tenements on the said land
to be given free of cost to MCGM, through the SRA, in lieu of the TDR
in the form of DRC to be issue by the MCGM Though there are two
components of the TDR, namely, the Land TDR and Construction
TDR, they both form an integral and inseparable part of the project
revenue, and cannot be separated and considered in isolation.

It is only a mechanism to provide the consideration to the developer,
but the basic and fundamental obligation of the developer is to
construct the required number of tenements and other infrastructure
amenities as per the Agreement as a part of Rehabilitation Scheme
of the SRA. Therefore, we submit that no profit or loss can be
considered only in respect of the Land Component of TDR, when the
project is still under construction.

Even the objective underlying the rehabilitation scheme is to create
additional housing stock of rehabilitation tenements, which is to be
utilized for rehabilitating project affected persons of vital public
projects of the Government or its agencies (please refer Recital
Clause (C) of the Agreement]. The arrangement between our
company and the SRA is therefore for creating additional tenements
for housing for project affected people. Transfer of the said land to
the SRA is only a preliminary step in that direction; and not the end
in it. Hence, the Land Component of the TDR cannot be separated
from the main construction project for measuring any profit or loss
from the same.
                                     11
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

Further, and more importantly, as per Clause (17)(a) we are entitled
to only 20% of the total Land TDR on execution of the Agreement,
while as per Clause 17(b) & (c), the balance 80% is linked to
construction of tenements. This clearly demonstrates that both these
components are inseparable and cannot be considered in isolation
independent of each other.

Therefore, any profit or loss of this project should be recognised only
upon completion of the project as a whole when our company fulfils
all its obligations under the Agreement.

3.3 Accounting Standard-9 (AS-9) on Revenue Recognition:

AS-9 pronounced by the Institute of Chartered Accountants of India
lays down the accounting standard for recognising revenue by an
enterprise. As per AS-9, revenue in case of sale is to be recognised
when significant risks and rewards stand transferred between the
parties. Further, the revenue can be recognised only when there is
no significant uncertainty about its ultimate collectability.

Having regard to the nature of project under execution, it cannot be
said that our company has transferred any significant risks of the
project to the SRA when land is transferred to it while the
construction of tenements, which is the basic obligation, is still in
progress. It is only after handing over of the constructed tenements
with occupation certificate obtained for the same, that one can say
the company has transferred the associated risk and reward of the
same to the SRA.

Further, the accrual of TDR in the form of DRC is also doubtful until
construction is completed as stipulated. The stage-wise allotment of
TDR is for the purpose of enabling the developer to raise finance
required for the implementation of the project. This is provided in
Clause (16) of the Agreement.

In any event, recognising revenue at every stage of allotment of TDR
would mean adoptionof percentage completion method; while our
company follows PCM. It is legally well settled that it is the choice of
the assessee to adopt a particular method of accounting; the only
requirements are that (a) it should be a recognised method of
accounting, and (b) the same method once adopted should be
followed consistently. Thus, the method of accounting adopted by
our company cannot be rejected, and a new method, i.e. percentage
completion method thrust upon us by recognising profit/loss on sale
of TDR receivable at different stages of the project.
                                    12
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

3.4   Judicial Precedent supports our stand:

i.     We would like to submit that our case is saucrely covered by
our sister concern's case of M/s. Atithi Builders And Constructors
Private Limited (ITA No. 4047 & 4048/Mum/2009) for A.Y. 2004-05
and 2005-06 by Hon'ble Mumbai ITAT-A Bench (the copy of decision
is enclosed) where CIT (A)'s decision is confirmed upending Project
Completion Method for TDR sales. It was held as follows:

"We have heard the rival submissions and perused the relevant
material on record. The only issue before us is whether TDRs should
be taxed on receipt basis as has been done by the Assessing officer
or in the year in which the project is completed. The assessee is
admittedly following mercantile system of accounting and the project
completion method has been approved by the Ld. CIT(A) as well. The
Mumbai Bench of the Tribunal in Chembur Trading Corporation
(supra) vide its order dated 21.01.2009 has held that when the
assessee is following project completion method, sale proceeds of
TDRs should be included in the year in which the project is
completed. Similar view has been taken by another Bench of the
Tribunal in ITO Vs. Sudhir V.Shetty in ITA No.4687/Mum/2006,
copies of these two orders have been placed on record. The Ld. DR,
after going through the above orders candidly admitted that the facts
and circumstances of the instant appeals were mutatis mutandis
similar. In view of these decisions it has become apparent that the
sale of TDRs is to be accounted for in the year in which the project
is completed and not when the work is going on. As the four
assessment years under consideration are the years in which the
project was unfinished, naturally the sale of TDRs cannot be included
in the income of the assessee. However it is made clear that the sale
proceeds of TDRS would be included in the total income of the
assessee in the assessment year 2008-2009, subject to the
availability of other deductions, as per law. The learned A.R. has
stated at Bar that the assessee voluntarily included such amount in
the income for the assessment year 2008-2009, assessment of which
is still in progress and the assessment order has not yet been passed.
We, therefore, hold that the amount of sale of TDRS in the years in
question should not be taxed but the same are accounted for in the
year of completion of project, that is A.Y. 2008- 09. We, therefore,
uphold the impugned order on this issue."

ii.    The accounting treatment given by our company is also
supported by the judgment of the Appellate Tribunal in ACIT vs.
Skylark Build [2011] 48 SOT 306 (Mumbai), wherein on identical facts
and circumstances of the case, it was held as follows:
                                  13
                                                  ITA.NO.1931 & 5181/MUM/2019
                                                     M/s Aristo Shelters Pvt. Ltd

"8...... The assessee has been following project
completion method which is an accepted method of
accounting in construction business and also
recommended as per accounting standard AS-7 of ICAL
Therefore, in such cases the income from the project has
to be computed in the year of completion. The TDRS
received are directly linked to the execution of the project
and therefore, before the completion of the project the
income from TDR or any other receipt inextricably linked
to the project will only go to reduce costs of the project.
Therefore, in our view the assessee had rightly set off
TDR received against WIP. The addition made by the AO
in 2006-07 on account of TDR receipt is not
justified............ The cost of the buildings is claimed to be
more than income from TDR, full details of which were
given to the CIT(A) and therefore, even on this ground
no income can be assessed in case of the assessee. In
the asst. yr. 2006-07, the project was not complete and
there is no dispute about this fact. Therefore, in asst. yr.
2006-07, TDR received has to be set off against WIP and
cannot be assessed separately as income. We therefore,
confirm order of CITYA) deleting the addition made in
asst. yr. 2006-07. The position regarding asst. yr. 2007-
08 is not clear. The AO has not given any finding
regarding the year of completion of the project. Though
the CIT(A) has held that the project was completed in
asst. yr. 2007- 08, he has not given any basis of such
finding not any such specific plea was taken by the
assessee before CIT(A). This aspect therefore requires
verification. The construction of the transit buildings was
only a part of the project. The actual year of completion
of the project is required to be verified. We therefore,
restore this aspect to the file of the AO for fresh order. In
case on verification it is found that the project was
completed in 2007-08, AO will compute the income from
project after taking into account entire expenditure and
the receipts from the beginning of the year including the
TDRs as directed by CIT(A). However, in case the project
is not found complete, the AO will set off TDR receipts
against work in progress and no income will be assessed
                                         14
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

        on account of TDR receipts separately. We direct
        accordingly."

                                                       [Emphasis supplied]

     5. In view of above discussion, we respectfully submit that the
     accounting treatment given by our company to the sales proceeds of
     Land TDR by deducting the same from the cost of WIP is correct and,
     therefore, it should be accepted. We, therefore, pray that in our case
     provisions of section 145(3) should not be invoked. The assessee
     further submitted that, without prejudice to above,

     A) your goodself may note that, for Builders & Developers, who
     follows Project Completion Method, while computing net profit of the
     particular Project, financial figures of more than one year needs to
     be considered to arrive at profitability of such Project. Your goodself
     may note that we have borrowed funds of 90,00,00,000/- from IL&FS
     TRUST COMPANY LIMITED (ILFS) vide Debenture Subscription
     Agreement (copy placed as Exhibit-2). The Principal amount of
     Rs:30,00,00,000/- was repaid in FY 2012- 13. Balance Principal
     amount of Rs: 60,00,00,000/- and interest of Rs: 64,20,61,040/- was
     paid in F.Y. 2014-15. We enclose herewith (i) copy of Ledger A/c of
     ILFS(Exhibit-3): (ii) our Audited Accounts, both for FY 2011-12;2012-
     13;2013-14 & 2014-15.(Exhibit-4)

     B) After debiting interest as referred to in para 4(A) above, we have
     prepared Profit/Loss A/c of the Chembur Project with Total cost
     incurred vis a vis Revenue generated from sales of TDR for the period
     1-4-2011 to 31-03-2015 per method of accounting denied by your
     office and also for valuation of closing stock as on 31.03.2015(the
     copy as Exhibit- 5). The result of the Project period till 31.03.2015
     shows net loss of Rs. 24,01, 73,617/- So taxing Income in particular
     year ignoring total life of the Project would give absurd results. Your
     goodself may note that Project is at halt due to litigation and stay by
     H'ble Bombay High court since 17/01/2013 (copies of two documents
     on litigation and stay are placed as Exhibit-6). These documents were
     also submitted during the course of assessment proceedings for A.Y.
     2012-13.

     So, in our humble view, Net Profit as stated in your letter can not be
     assessed as Income for F.Y.12-13 (A.Y.13-14)."


9.   After considering the submissions of the assessee, Assessing Officer

rejected the same and came to the conclusion that the TDR consists of
                                          15
                                                          ITA.NO.1931 & 5181/MUM/2019
                                                             M/s Aristo Shelters Pvt. Ltd

20% of the total TDR on execution of the agreement and balance 80% is

linked to the construction of the tenements.             Therefore, he is of the

opinion that as per the tripartite agreement, the assessee has transferred

the land with all its rights acquired on purchase of such land to the SRA.

In return, assessee has received TDR from SRA. The cost of Land TDR is

the cost of land purchased and expenses incurred on development of land.

On acquisition of Land TDR, it can be said to be held as stock in trade and

the cost of said TDR is the cost of land and the cost incurred on

development of such land. By selling the TDR held as stock in trade, the

assessee is acting just like a trader and he proceeded to treat the profit

sale of TDR as income of the assessee after adjusting the cost of land and

observed as under: -

     "7.3 As per the multipartite agreement, the assessee got privilege and
     the right in construction of rehabilitation component. Such construction
     of buildings in the project commenced as per the direction of the SRA.
     In lieu of expenses incurred on construction of tenements/building of
     the project, the assessee will get TDR for sale in open market after
     commencement of work of construction of building in phased manner.
     In this process, the assessee is acting like a contractor and not a
     developer. As such, the assessee is not having any control over
     commencement of construction, allotment of residential tenements and
     the completion of whole project.

     7.4    As per the multipartite agreement, the assessee has got privilege
     and right in construction of 9002 tenements. In the said agreement,
     there is a clause to construct a building by the assessee within 5 years
     of issue of commencement certificate. The project in question,
     comprising of 59 buildings for residential tenements and 3 other
     buildings for amenities. Since the project is so large and there is no time
     bound completion of the 'whole project, the method followed by the
                                         16
                                                        ITA.NO.1931 & 5181/MUM/2019
                                                           M/s Aristo Shelters Pvt. Ltd

     assessee itself is questionable. During the course of assessment
     proceedings the assessee has never come forward with any proposal
     that when the said project will be completed and when it will offered the
     income generated from such project. The assessee by claiming that it
     has followed project completion method and the income will offered
     after the completion of project raises doubts about the intention of the
     assessee.

     8.      Since the assessee failed to determine profit of the business on
     sale of land TDR, the book result of the assessee are considered not
     reliable and accordingly stands rejected within the meaning of provisions
     of section 145(3) of the Act and the assessment is completed in the
     manner provided u/s 144 of the Act, on discussion hereinbelow.

     9.    While issue of the show cause regarding rejection of books of
     accounts, inadvertently closing stock balance has been taken at Rs.
     32,95,87,461/-, representing figure as per capital work in progress
     shown by the assessee company instead of Rs. 50,26,28,147/-, cost of
     balance land TDR (421629 1192.11).

     10. Considering the facts narrated above, evolution of evidences,
     references of facts and discussion, the correct method to determine
     profit on sale of land TDR is given here under:-

Opening Stock               1,78,14,63,752     Sale of TDR          2,19,52,15,898
Direct Expenses                   16,31,263
Administrative Expenses       14,91,85,667
Financial Expenses              6,20,75,907
Selling & Distribution            46,07,709
Expenses
Profit                        69,88,79,747     Closing Stock          50,26,28,147
Total:                    2,69,78,44,045       Total             2,69,78,44,045


     Note on closing stock
     1.    Total land TDR receivable                               16,86,083 sq ft.
     2.    Cost of land TDR as opening stock                       Rs. 201,00,00,000/-
     3.    Cost of 1sq ft and land TDR                             Rs. 1192.11/-
     4.    Land TDR sold during the year                           10,85,664 sq ft.
     5.    Sale price of land TDR for the year                     2,19,52,15,898/-
     6.    Balance land TDR with the assessee company              4,21,629 sq ft.
     7.    Cost of balance land TDR                                Rs. 50,26,28,147/-
                                                                   (421629* 1192.11)
                                         17
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

     Accordingly profit on sale of land TDR is determined at
     Rs.69,88,78,747/- and same is treated as income of the
     assessee for the AY. 2013-14."


10. Further, Assessing Officer observed that assessee has debited

interest expenses under the head "Financial Expenses" and adjusted in

work-in-progress account as under: -

              Finance expenses:
              Interest account               ₹.62222922/-
              Interest received on FD        ₹.1832412
                                             ₹.,60390507

11. He observed that interest payments were made to secured loan

from bank, convertible debenture and to unsecured loans from parties not

related to the assessee. Further, he observed that assessee has utilized

the interest bearing fund/business fund for advancing it to its associate

concern. The closing balance of advances given to associates concern is

as under: -


              To Director                              ₹.4,57,950/-
              To M/s. Aristo Realtors Pvt. Ltd.,       ₹. 167,36,35,000/-

12. Since the assessee utilized its business/interest bearing funds for

non-business and non interest generated advance, in order to verify the

assessee was show caused as to why the proportionate interest expenses
                                         18
                                                           ITA.NO.1931 & 5181/MUM/2019
                                                              M/s Aristo Shelters Pvt. Ltd

debited on interest bearing fund not utilized for business purpose should

not be disallowed.


13. In response, assessee submitted that assessee has interest free

funds available in the business and as per the presumption the interest

free funds are applied which for such other purposes. However, Assessing

Officer rejected the same by disallowing the proportionate interest as

under: -

     "13.3. Considering the above facts and as per statement given by
     the assessee, interest free find available with the assessee and
     interest free advances given is worked out as under: -

           A.     Interest free loans received from Director & related parties:

                     1. From Director          Rs. 10,68,852/-

                     2. From related parties Rs. 41.02,36,335/-

           Interest fund available with assessee total Rs.41,13,05,187/-

           B.     Interest free loan/advances given to director and related parties:

                     1.      To Director                      Rs. 4,57,950/-

                     2. To Aristo Realtors Pvt. Ltd           Rs.167,36,35,000/-

                     3. Investment in related parties         Rs. 18,00,00,000/-

                     4. Total                                 Rs. 1,85,40,92,950/-

     13.4 From the above working, it is seen that the assessee has given
     interest free loans/investment to related parties over and above
     interest free fund available with it.

     13.5 Thus the assessee has given advances and made investments
     to related parties from the interest bearing fund meant for business
     amounting to Rs. 144,27,87,763/- so as to enhance its work in
     progress and thereby reduce its tax liability.
                                         19
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

     13.6 Since, the assessee has utilized its interest bearing business
     fund amounting to Rs. 144,27,87,763/- for interest free advance to
     its related parties, the interest paid on interest bearing fund taken
     from bank (secured) and from other parties (unsecured) amounting
     to Rs. 6,22,22,922/- is not allowable as business expenses as
     provided u/s 36(1)(iii) of the IT Act, 1961.

     13.7 As regards to the reliance placed on in the case of CIT v/s
     Reliance Utilities & Power Ltd, the facts of the assessee case to the
     case relied upon are distinguishable and not identical as discussed in
     above paras. In the assessee case, advances given to its related
     parties and investment made is over and above of interest free fund
     available with the assessee. Hence, the decision relied upon does not
     help the assessee.

     13.8 Considering the above facts, interest paid and
     debited/claimed against income amounting to Rs. 6,22,22,922/- is
     disallowed and added back to total income of the assessee. Since the
     assessee filed inaccurate particulars of income and thereby
     concealed particulars of income, penalty proceedings u/s 271(1)(c)
     is hereby initiated."


14. Aggrieved assessee preferred an appeal before the Ld.CIT(A) and

filed detailed submissions before him.          After considering the detailed

submissions Ld.CIT(A) allowed the appeal of the assessee, observing as

under: -

     "4.3 I have considered the A.O's order and the submissions made
     by the appellant. I find that the appellant has followed the project
     completion method which is a recognized method of accounting.
     Further, the appellant has entered into agreement with Slum
     Rehabilitation Authority (SRA) to construct certain numbers of
     residential tenements, balwadis, welfare centres, and other
     amenities as approved by SRA in consideration of Transfer of
     Development Rights (TDR). The TDRS are to be received for the land
     component i.e. land to be transferred by the appellant/developer to
     the SRA and construction TDR in respect of the construction of
     various buildings in the SRA project. The release of TDR in the form
     of Development Rights Certificates (DRCs) is to be done in stages to
                                     20
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

enable the developer/appellant to raise finance and construct and
complete the buildings/tenements within the time agreed between
the SRA and Developer. Even the land TDR is to be released, as per
clause 17 of the agreement dated 30.4.2011, in following manner:

       i)    20% on the execution thereof and lodging the
       conveyance with the registrar in respect of land agreed to be
       conveyed in favour of PIA i.e. Project implementing authority.

       ii)    65% upon developer constructing 50% of the plinth of
       the tenements

       iii)   Balance 15% upon           developer    completing    the
       construction of tenements.

Therefore, I am inclined to agree with the appellant's contention that
the sale proceeds of land TDR is part of the project undertaken and
cannot be considered independently of the total project, for the
computation of income for A.Y.2013-14.Reliance is placed on the
following decisions, as cited by the appellant in its submissions:

       i)    CIT vs. M/s Chembur Trading Corporation (Bombay
       High Court - IT Appeal No. 3179 of 2009)

       ii)   ACIT vs. M/s. Atithi Builders & Constructors p. Ltd. (ITA
       No. 4047 & 4048/MUM/2009)

4.3.1 Further, I find that the issue raised in Grounds 1, 2 & 3 of
Appeal has been decided in favour of the appellant by the CIT(A)-2,
Mumbai for the A.Y. 2012-13, vide the Order dated 06.02.2017, in
Appeal No.: CIT(A)-2/IT-120/2015-16. In the said order dated
06.02.2017, the decision of the jurisdictional Hon'ble Bombay High
Court in CIT vs. Chembur Trading Corporation (IT Appeal No. 3179
of 2009), which upheld the decision of the Hon'ble Tribunal in CIT
vs. Chembur Trading Corporation (ITA No.2593/Mum/2009), has
been followed and the AO has been directed to accept the method
of accounting followed by the appellant company i.e project
completion method. Since the facts of the case remains the same for
A.Y.2013-14 and the AO has followed the findings of AO in A.Y.2012-
13, following the decision of the CIT(A) in A.Y.2012-13, it is held that
the AO was not correct in rejecting the method of accounting
followed by the assessee and making an assessment u/s.144 r.w.s
145(3) of the Act. It follows that the profit on sale of TDR is to be
assessed in the year of completion of the project. Accordingly, the
addition of Rs.69,88,79,747/-, made by the AO by treating the profit
on sale of TDR as income for A.Y. 2013-14, is deleted. The AO is
                                           21
                                                           ITA.NO.1931 & 5181/MUM/2019
                                                              M/s Aristo Shelters Pvt. Ltd

      directed to compute the income for A.Y.2013-14 by following the
      project completion method as done by the appellant. Ground No.1,
      2, & 3 taken by the appellant are Allowed.

      ....

      5.2. I have considered the AO's order and the submissions of the
      appellant. The AO has held that the TDR advances was in the nature
      of business fund and could not be treated as interest free fund mainly
      on the ground that if the assessee was not able to arrange the TDR,
      then it has to pay heavy compensation and the same was claimed as
      a business loss. This view of the AO is not found to be correct since
      the nature of TDR advance is like any other advance received in the
      course of business and since interest is not chargeable on such
      advance, it has rightly been considered as part of interest free funds
      available with the appellant. The appellant's claim of compensation
      paid on non delivery of TDRS as a business expenditure has to be
      considered on its own merit and the claim of such expense would
      not decide if the advance received is interest free or not. Therefore,
      I am of the considered opinion that TDR advances available with the
      appellant should be treated as part of the interest free funds.

      5.2.1. The AO has considered the advances and investments made
      to related parties from interest bearing funds, meant for business,
      amounting to Rs.144,27,87,763/-, by excluding the TDR advances
      available with the appellant of Rs. 1,56,44,69,461. However, as
      noted above, the TDR advance has rightly been considered by the
      appellant as part of interest free fund and on that basis, the interest
      free advances and investment with related concerns/ Director are
      out of interest free funds. Thus, no disallowance of interest is called
      for u/s 36(1)(ii) of the Act, in view of the decision in the case of CIT
      vs. Reliance Utilities & Power Ltd. [2009] 313 ITR 340. In view of
      above discussion, the addition of Rs.6,22,22,922/-,made to total
      income on account of disallowance of interest paid is deleted. Ground
      no. 4 is allowed and ground no. 5 is dismissed as academic and
      infructuous.


15. Aggrieved revenue is in appeal before us raising following grounds

in its appeal: -

      "1.    Whether On the facts and in the circumstances of the case
      and in law, the ld. CIT(A) has erred in deleting the addition of Rs.
                                         22
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

     69.88 Crore made by the AO on account of sale of Transferable
     Development Right (TDR) received on transfer of land to Slum
     Rehabilitation Authority (SRA), by holding that the TDR is part of the
     project work. in-progress; without appreciating the fact that sale of
     sand to SRA has no nexus with the contract awarded for construction
     of free homes to Project Affected Persons (PAP) for which TDR is
     receivable on different stages of construction."

     2.     "Whether On the facts and in the circumstances of the case
     and in law, the ld. CIT(A) has erred in deleting the disallowance of
     Rs. 6.22 crore made by the AO being the proportionate interest on
     the interest free loan advanced out of the interest bearing loans, by
     holding that TDR advances are in the nature of interest free loan
     without appreciating the fact that the assessee has no adequate free
     funds available and that no evidences was furnished to prove the
     nexus of advance out of TDR advance."


16. At the time of hearing, Ld. DR brought to our notice findings of the

Ld.CIT(A) at Page No. 17 of his order and he submitted that assessee has

received two types of TDRs as per the Tripartite agreement. Assessee

has transferred all the rights over the land to the SRA, accordingly, TDR

received on the land has to be recognized as income of the assessee and

with regard to TDR received for construction of the property, the assessee

is following the of project completion method of accounting, accordingly,

it can follow the procedure. Therefore, he submitted that the land TDR

received by the assessee which has reached finality i.e. 20% of the TDR

amount. Ld. DR submitted that Assessing Officer has treated the entire

TDR as income of the assessee. However, Ld.CIT(A) has come up with

the proposition that the TDR received by the assessee for land is separate
                                      23
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

and for construction is separate which itself is not proper. Therefore, he

submitted that the above finding of the Ld.CIT(A) is against the

accounting principle followed by the assessee. He submitted that TDR

are accrued to the assessee based on the project completion status. He

strongly supported the findings of the Assessing Officer and prayed that

Assessment Order may be restored.



17. With regard to, interest disallowance he brought to our notice Page

No. 15 of the Assessment Order and supported the findings of the

Assessing Officer. Further, he brought to our notice Page No. 19 and 22

of the Ld.CIT(A) order, to brought to our notice the interest free funds

available in the balance sheet to the extent of ₹.1,97,57,74,648/- the

utilization of non business purpose extent of ₹.1,88,05,85,350/-.              He

submitted that the balance sheet clearly shows that assessee has

deployed the interest bearing funds for the non business purposes.

Accordingly, he prayed that the findings given by the Assessing Officer in

the Assessment Order may be restored.



18. On the other hand, Ld. AR submitted as under: -

          The Respondent-assessee is engaged in the business of real
     estate development. During the course of its business, the
     Respondent vide Agreement for Sale dated 05.02.2010 entered into
     with M/s. Bombay Industrial Corporation, purchased land
                                         24
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

      admeasuring approximately 1,56,640 sq. meters situate at CTS No.
      619/A, 619/B, 620/A, 620/B, 621/A, 621/B, 621/C, 623/A1, 623/A2
      and 623/B at Village Mahul, Chembur, Mumbai ("said land") for
      purchase price of Rs. 201 crores, with a view to develop the same
      under Slum Rehabilitation Scheme

            The Respondent had given a rehabilitation proposal to the
      Slum Rehabilitation Authority ("SRA") for development of the said
      land under provisions of Clause 3.11 read with Clause 3.5 & 3.9 (ii)
      of Appendix-IV of Development (Control & Regulations) Rule 33(10),
      by constructing certain number of tenements at its own cost to be
      handed over the Municipal Corporation of Greater Mumbai
      ("MCGM"), free of cost, which in turn would allot these tenements to
      the slum dwellers removed from hutments along water mains of
      MCGM. In lieu of this the Respondent would get Transferable
      Development Rights ("TDR") from MCGM. This rehabilitation project
      was declared as a Vital Public Project by the Government of
      Maharashtra.

            By Letter of Intent ("LOI") dated 31.3.2011 issued by SRA,
      the Respondent is to construct 9002 tenements and other amenities
      to be handed over to MCGM through SRA free of cost for which
      following TDR would be allotted to the Respondent:

(A)       Land TDR                               Sq. Meters           Sq.Ft
          Project Affected People Tenements      89,061.89            9,58,662
          Buffer Zone Area                       28,418.78            3,05,900
          Amenity Portion                        39,160.23            4,21,521
                                         Total                        16,86,083
(B)               Construction TDR                                    1,11,12,477
                                         Total                        1,27,98,560

            Pursuant to the LOI dated 31.3.2011, a Multipartite
      Agreement ("the Agreement") was executed on 30.4.2011 between
      M/s. Bombay Industrial Corporation (as "Vendors"), the Respondent
      (as "Developers") and the SRA (as "Purchaser') and the SRA (as
      "Project Implementing Authority") setting out the terms and
      conditions for development of the said land in accordance with the
      LOI dated 31.3.2011. Clause (3) and (4) of the Agreement provide
      for consideration in the form of TDR to be allotted to the Respondent
      described "Rehabilitation Component" and "Land Component" as
      respectively for the obligations undertaken by the Respondent in
      implementing the rehabilitation scheme at the said land.
                                        25
                                                        ITA.NO.1931 & 5181/MUM/2019
                                                           M/s Aristo Shelters Pvt. Ltd

          The aforesaid LOI was amended from time to time by several
    supplementary LOIS, the last being LOI dated 16.6.2012, which
    modified the no. of tenements to be constructed by the Respondent
    to 8,399 and also other amenity tenements as per Clause (21)
    thereof.

          Clause (7) of the Agreement provides that the Respondent
    shall be entitled to the benefit of TDR in the ratio of 1:1 in respect
    of the Land Component from the SRA, and the SRA will cause the
    MCGM of issue TDR in the form of Development Right Certificate
    ("DRC") in the name of the Respondent in stages after the said land
    is transferred to SRA as specified in the Agreement. Clause (17) of
    the Agreement provides the time when the Respondent will be
    entitled to the Land Component of TDR; while clause (18) of the
    Agreement provides the time when the Respondent will be entitled
    to the Rehabilitation, i.e. Construction Component of TDR. Clause
    (15) of the Agreement stipulates the compensation to be paid by the
    Respondent to the SRA in case of default committed by the
    Respondent in the construction work.

         The Respondent received the following TDR in respect of the
    Land Component:

Date of       Date of        Nature of TDR         TDR in Sq.       TDR in Sq.
Release       Receipt                              Meters           Ft.
18.5.2011     16.9.2011      PAP Tenements-        17,810.00        1,91,706.84
                             part
18.6.2012     16.7.2012      Buffer Zone Area      28,418.78        3,05,899.75
26.6.2012     27.7.2012      PAP Tenements-        71,251.89        7,66,955.34
                             Balance
                             Total                 1,17,480.67      12,64,561.93

          The Respondent has been consistently following project
    completion method for recognizing revenue from this project.
    Consequently, all the expenses incurred on this project have been
    accumulated under the head "Work-in- Progress" till the completion
    thereof. The sales proceeds realized on sale of TDR during the
    construction period has been reduced from the cost of WIP, and the
    balance cost carried forward from year to year.

          It is important to state that after 27.07.2012, the Respondent
    has not received any TDR. The said land being situated near HPCL
    and BPCL Refineries, they have taken serious objections to this
    project. Further, Public Interest Litigation involving this project is
    pending before the Hon'ble Bombay High Court. HPCL filed W.P. No.
                                    26
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

2107 of 2013 before Hon'ble Bombay High Court against the SRA,
Respondent-assessee and Ors., against sanction of development of
this project. Vide Order dated 30.03.2016 passed by Hon'ble High
Court this Writ Petition has been clubbed with Notice of Motion No.
19 of 2013 filed by Respondent-assessee in PIL. No. 140 of 2006
pending before the High Court. All these matters are pending. In
view of these facts, the said project is couched in significant
uncertainties even at present.

       In the immediately preceding year, i.e. A.Y.2012-13, the then
Ld. AO had rejected the method of accounting employed by the
Respondent and after invoking Section 145(3) of the Act, determined
business loss of Rs. 38,01,13,034/- as against 'Nil' total income
declared by the Respondent. The Respondent had carried the matter
in appeal before the Ld. CIT(A)-2, Mumbai, who vide the Order dated
06.02.2017, upheld the Respondent's stand. No further appeal was
filed against this order of CIT(A) before the Hon'ble ITAT.

Submissions:

1.   Project Completion Method (PCM) is a recognized
method of accounting:

1.1 PCM is a recognized and scientific method that has stood the test
of judicial scrutiny in a number of cases, reference to which has been
made in the written submissions filed before the Ld. CIT(A), a copy
of which is placed at pp.187-204 of Paper Book (PB) field by
Respondent. The assessee has choice of the method of accounting
to be followed, which method once adopted, should be consistently
followed year after year, which the Respondent has done.

1.2     Assessing Officer can invoke section 145(3) if he is not
satisfied about the correctness or completeness of the accounts of
the assessee, or where the method of accounting referred to in sub-
section (1) or accounting standards notified under sub-section (2),
have not been regularly followed by the assessee. The Ld. AO has
not given any reason to discredit the accounts maintained by the
Respondent, which are duly audited by a firm of Chartered
Accountants under the provisions of the Companies Act, 1956.
Further, no reasons are adduced to show that generally accepted
accounting principle were not adopted by the Respondent in
preparation of its financial statements. The Ld. AO's only case is that
the Respondent ought to have recognized revenue from sale of TDR
even though the project did not take off.

1.3   In Respondent's case, PCM is the most appropriate method of
accounting because the approach adopted by the Ld. AO has resulted
                                    27
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

in distorted profit/loss from year-to-year as under, even though the
project has not yet taken off due to the pending litigation:

                                                          Assessment
                     Income             Income               Order
                   declared by        computed by         u/s.145(3)
      A.Y.
                       the             the Ld.AO           r.w.s 144
                   Respondent             Rs.                dated
    2012-13             NIL             (38,01,13,034)     31.03.2015
    2013-14             NIL              76,11,02,669      30.03.2016
    2014-15             NIL             (73,89,32,572)     29.12.2016

2.     Land Component of TDR cannot be considered de hors the
total project:

2.1    The Ld. AO erred in considering sale of Land TDR as an
independent stream of income detached from the above project. Though
there are two components of the TDR, namely, the Land TDR and
Construction TDR, they both form an integral and inseparable part of the
project revenue, which cannot be separated and considered in isolation.
Clause (16) of the Agreement (p.87 of PB) provides that the release of
TDR in the form of DRC in phases is to facilitate the developer to raise
finance and construct tenements within the agreed time limit. The basic
and fundamental obligation of the developer is to construct the required
number of tenements and other infrastructure amenities as per the
Agreement as a part of Rehabilitation Scheme of the SRA. Therefore,
revenue from sale of Land TDR can be assessed only upon completion
of the project, and not when the project is not yet taken off due to the
pending litigation.

2.2 The Agreement dated 30.04.2021 (pp. 78-115 of PB) read as a
whole, would show that it was a composite agreement for transfer of
the land and construction of tenements/infrastructure facilities on the
land. Recital 'B', "C', 'D' and Clause (3), (7), (8) of the Agreement shows
this fact. Clause (9)(ii) of the Agreement reads as under-

"TDR in respect of the said Land Component which is declared to be part
of the approved SRA project in this Agreement;"

Clause (12) of the Agreement reads as under-
                                    28
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

"The SRA confirms that this scheme is for erecting of housing stock of
rehabilitation tenements for rehabilitation project affected persons
affected by vital public purpose project undertaken by Government
and/or its agencies. Upon the Developer obtaining the occupation
certificate from the SRA after completing all necessary on site
infrastructures such as water supply line, electricity supply and drainage
line, etc., the Developer shall be entitled to the balance Land TDR......."

Clause (17) of the Agreement provides the time when TDR for the Land
Component will be recommended by the SRA in favour of the
Respondent, and it is clearly linked to progress in the construction of
tenements, and the final 15% TDR will be released only upon completion
of construction of tenements and the occupation certificate for the same
is issued by the SRA.

Recital T' and 'J' of the Conveyance Deed dated 30.4.2011 (pp.71 & 72
of PB) also stipulates that Respondent has agreed to undertake project
of construction of tenements comprising certain built-up area sanctioned
by SRA in phase in lieu of TDR in respect of the said land and conveyance
is made in advance as required by SRA. Thus, conveying this land in
favour of SRA was only because such advance conveyance was required
by SRA; but it is a part and parcel of the rehabilitation project of
construction of tenements for settlement of PAP. Further, the main body
of the Conveyance Deed at p.5 onwards (pp.72 -74 of PB) stipulates that
the said land has been conveyed in favour of SRA in the consideration
of the SRA agreeing and undertaking with Respondent to provide or
cause to be provided TDR in the form of DRC in respect of the said land
as set out in the Agreement, and that the terms and conditions thereof
are binding and form part of this Conveyance. In other words, the
transfer of the said land was a part of the overall rehabilitation project
undertaken by Respondent and could not be considered in isolation on
standalone basis. It is further provided that the said Conveyance is
conditional upon and subject to the obligation on the part of the SRA as
stipulated in the Agreement and that Respondent is in possession of the
said land for and on behalf of the SRA with a right to carry out
construction of the tenements and develop the same in accordance with
the terms of the Agreement and that the assessee has a special lien on
the said land which will not be disturbed, affected and prejudiced by the
SRA unless the term of the Agreement are complied with, observed and
performed and the SRA shall not convey this land to anybody unless and
                                    29
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

until SRA release all the benefit of TDR under the Agreement (p.74 of
PB).

2.3 All the above provisions, stipulations and conditions clearly establish
the inextricable, inseparable and organic nexus between the transfer of
the said land and construction of tenements. It would be erroneous to
consider transfer of the said land as a separate, independent and
standalone transaction between Respondent and SRA, de hors the
overall composite project undertaken by Respondent. Transfer of the
said land to the SRA is only a preliminary step in that direction; and not
the end in it. Clause (2) of the Agreement for Sale dated 5.2.2010 [p.139
of PB] entered into by Respondent with Bombay Industrial Corporation
shows its clear intention to develop the said land under a scheme of SRA
etc. It was never the intention of any of the parties to the Agreement to
consider the land transfer as an independent transaction; it is always
considered and intended as an integral part of the overall rehabilitation
project.

2.4 Further, the Ld. AO also erred in not appreciating that until the end
of the year under appeal, Respondent did not receive total TDR of Land
Component. The Ld. AO himself has admitted in para (5.3) of the
assessment order that till date the Respondent got 75% of the total Land
Component TDR.

2.5 Respondent relies upon decision in I.T.O. vs. Chembur Trading
Corporation (ITA No. 2593/Mum/2006) [pl refer pp. 9-10 of
Compilation of Case Laws), wherein the agreement was a composite
agreement for handing over land for Expressway and also for
construction of tenements and shops by the assessee on land belonging
to it. The entire land was acquired in phases and also consideration in
the form of TDR was received in phases. Consideration was received in
kind. The funds received on sale of TDR were utilised for construction of
tenements and shops. Hon'ble Tribunal held that it was clearly one
project and not two projects as they have been treated by the AO. It
was held that the AO cannot adopt two methods of accounting in one
project to determine the income of the assessee. It observed that in case
of construction activity there are two recognised methods of accounting
viz. (1) Project Completion Method and (2) Percentage Completion
Method. It is stated that the assessee has a right or a privilege to adopt
any one of the methods of accounting for determining its profit. In this
case, the assessee had been following the project completion method to
                                     30
                                                     ITA.NO.1931 & 5181/MUM/2019
                                                        M/s Aristo Shelters Pvt. Ltd

determine the profits of a project for last so many years, but during the
year under consideration the AO had dissected the project in two
segments and for one segment he applied project completion method
and for the remaining segment, he determined the profit on sale of TDR.
The method of accounting adopted by the AO was held to be neither
prevalent nor recognised by the ICA! or under any law. Hon'ble Tribunal
held that the assessee had rightly computed its profit on the basis of the
project completion method. Accordingly, it upheld the order of CIT(A)
and dismissed the appeal filed by the Revenue.

Hon'ble Bombay High Court confirmed the above decision by dismissing
the Revenue's appeal CIT vs. M/s. Chembur Trading Corporation
(Bombay High Court - IT Appeal No.3179 of 2009) [pl refer p. 1
of Compilation of Case Laws]

Reliance is also placed on the following judicial rulings:

 a)    ACIT vs. M/s. Atithi Builders & Constructors P. Ltd. (ITA No. 4047
       & 4048/Mum/2009) [pl. refer pp. 14-22 of Compilation of Case
       Laws]

 b)    CIT vs. Shri. Sudhir V. Shetty (Bombay High Court - IT Appeal
       No.6159, 6160 & 6161 of 2010) [pl refer pp.2-3 of Compilation of
       Case Laws]

 c)    ACIT vs. M/s. Videocon Atithi Shelters Pvt. Ltd. (ITA No. 3496-
       3499/Mum/2009)[pl refer pp.11-13 of Compilation of Case Laws]

 d)     ACIT vs. Skylark Build [2011] 48 SOT 306 (Mumbai)[pl refer
       pp.4-8 of Compilation of Case Laws

 e)    M/s. Pushpa Construction Co. vs. ITO (ITA No.193/Mum/2010)
       [pl refer pp.23-25 of Compilation of Case Laws]

3. Impact of Accounting Standard-9 (AS-9) on Revenue
Recognition:

AS-9 pronounced by the Institute of Chartered Accountants of India lays
down the accounting standard for recognising revenue by an enterprise.
As per AS-9, revenue is to be recognised when significant risks and
rewards stand transferred between the parties. Further, the revenue can
be recognised only when there is no significant uncertainty about its
ultimate collectability. Having regard to the nature of the project under
execution, it cannot be said that Respondent has transferred any
                                               31
                                                                ITA.NO.1931 & 5181/MUM/2019
                                                                   M/s Aristo Shelters Pvt. Ltd

         significant risks of the project to SRA when land is transferred to it, while
         construction of tenements, which is the basic obligation, is not even
         started. On handing over of constructed tenements with occupation
         certificate one can say Respondent has transferred the associated risk
         and reward to SRA.

         Further, accrual of TDR is also doubtful until construction is completed
         as stipulated. The stage-wise allotment of TDR is for purpose of enabling
         the developer to raise finance required for the implementation of the
         project. This is provided in Clause (16) of the Agreement.

         In view of pending litigation before Hon'ble Bombay High Court,
         execution of this project is standstill, and therefore, it is now couched
         with very significant risks as to its ultimate completion and realization of
         revenue, though Respondent incurred costs (including interest on
         borrowings) year after year.

         Therefore, it is submitted that in view of AS-9 also, there is no case for
         recognition of any revenue from this project at this stage.

         AY 2013-14: Ground No.2:

         Submissions:

         The details of interest-bearing funds and interest-free funds available to
         Respondent and also its utilization for business purposes and non-
         business purposes are summarised as under:

Available Funds                   Amount (Rs.)       Utilization of           Amount (Rs.)
                                                     Funds
I) Interest Free Funds                               I) Non- Business
                                                     Purpose
i) From Directors                          10,68,852 i) To Directors                  4,57,950
ii) From related parties                41,02,36,335 ii) To related parties      167,36,35,000
iii) TDR Advances                     1,56,44,69,461 iii) TDR Advances            20,64,92,400
Total (I)                           1,97,57,74,648 Total (I)                   1,88,05,85,350

II) Interest Bearing Funds                           (II) Business
                                                     Purpose
i) From non- related parties          1,03,78,20,098 i) Work in Progress           32,95,87,462
(Secured)
ii) From non- related parties           31,38,04,913 ii) Sundry Debtors            31,54,70,092
(unsecured)
                                                   iii) Fixed Assets              86,25,65,386
                                                   iv) Deposits                    2,37,80,484
Total (II)                          1,35,16,25,011 Total (II)                  1,53,14,03,424


Total Funds (I) + (II)              3,32,73,99,659 Total Funds (I) +(II)       3,41,19,88,774
                                    32
                                                    ITA.NO.1931 & 5181/MUM/2019
                                                       M/s Aristo Shelters Pvt. Ltd

It is submitted that where assessee has both, interest-free as well as
interest- bearing funds, which are mixed, then, there is a legal
presumption that the assessee has utilised interest-free funds for the
purpose of financing non-business purposes. Reliance is placed on
decision of Hon'ble Supreme Court in CIT vs. Reliance Industries
Ltd. [2019] 410 ITR 466 and Hon'ble Jurisdictional High Court in
CIT vs. Reliance Utilities & Power Ltd. [2009] 313 ITR 340.

It is further submitted that merely because the TDR Advances were
received in the course of carrying on business cannot convert them
into interest-bearing, when factually, they are not so. The claim of
compensation that would be payable on non-delivery of TDR as
business expenditure is to be considered on its own merits and the
claim of such expenses can alter the fact that the TDR advances are
interest free. Thus, TDR advances received are fundamentally
interest-free funds available to the Respondent about which there
can be no dispute. Reliance is placed on the order of Ld. CIT(A) on
this issue.

In view of above, the Ld. CIT(A) had correctly, based on the facts
and also in law, deleted the disallowance of interest paid of
Rs.6,22,22,922/-.

Without prejudice to the above, the Respondent further submits that
the Ld. AO erred in adding the sum of Rs.6,22,22,922/- being the
amount of disallowance of interest paid. The Ld. AO ought to have
noted that the Respondent did not claim any deduction for the
interest paid during the year under appeal, and the same was added
to the WIP of the project. If at all, the disallowance was to be made,
then, the same could be deducted from the WIP that is carried
forward to the subsequent year. Reliance for this proposition is
placed on the decision in Savala Associates vs. ITO [2010] 35
SOT 148 (Mum-Trib).

Prayer:

The Respondent prays Your Honours to kindly confirm the orders of
Ld. CIT(A) and dismiss both the Grounds of Appeal raised by the
Appellant-revenue for AY 2013- 14 and sole Ground of Appeal raised
by the Appellant-revenue for AY 2014-15."
                                    33
                                                 ITA.NO.1931 & 5181/MUM/2019
                                                    M/s Aristo Shelters Pvt. Ltd

19. Considered the rival submissions and material placed on record, we

observe that assessee has entered into an agreement to develop the slum

rehabilitation scheme as per which assessee has acquired the land from

M/s. Bombay Industrial Corporation and entered into multipartite

agreement with SRA and different tenements. No doubt assessee has

transferred the land to SRA and surrendered all the rights over the

property.    However, assessee had a basic obligation to construct the

building and receive TDR on the portion of land on which the construction

is completed in the ratio of 1:1 on TDR and construction TDR in the ratio

of 1:1.33.



20. It is fact on record that the construction agreement received by the

assessee is to construct the building as per the agreed terms only when

assessee completes the constructions assessee gets the rights of TDR,

that means assessee gets the TDR rights only when it completes the

construction.



21. Further, we observed that assessee is following the project

completion method which is recognized method of accounting.                We

observe that Ld.CIT(A) has extracted the clause (17) of the agreement

dated 30.04.2011 as under: -
                                        34
                                                        ITA.NO.1931 & 5181/MUM/2019
                                                           M/s Aristo Shelters Pvt. Ltd

     i)     20% on the execution thereof and lodging the conveyance
            with the registrar in respect of land agreed to be conveyed in
            favour of PIA i.e. Project implementing authority.

     ii)    65% upon developer constructing 50% of the plinth of the
            tenements

     iii)   Balance 15% upon developer completing the construction of
            tenements.


22. By reference to the above Ld.CIT(A) came to the conclusion that

the sale proceeds of land TDR is part of the project undertaken and cannot

be treated independently of the total project for the computation of the

income by relying on the decision of the CIT v. Chembur Trading

Corporation (I.T. Appeal No. 3179 of 2009).             Accordingly, he gave a

direction to the Assessing Officer to accept the method of accounting

followed by the assessee.



23. We observe that Hon'ble Jurisdictional High Court in the case of

CIT v. Chembur Trading Corporation (supra) has held that in this case

method of accounting followed by the assessee is completion of project

and has offered the income received on sale of TDR in the subsequent

assessment year and the same has been duly assessed.                         In these

circumstances sustaining the addition in the assessment year in question

does not arise.
                                         35
                                                         ITA.NO.1931 & 5181/MUM/2019
                                                            M/s Aristo Shelters Pvt. Ltd

24. Further, we observe that the Coordinate Bench decided the issue in

ITO v. Chembur Trading Corporation in ITA.No. 2593/Mum/2006 dated

21.01.2009 for the A.Y. 2000-01 and held as under: -

     "The Tribunal noted that the agreement was a composite agreement
     for handing over land for Expressway and also for construction of
     tenements and shops by the assessee on land belonging to it. The
     Tribunal also noted that the entire land was acquired in phases and
     also consideration in the form of TDR was received in phases.
     Consideration was received in kind. The funds received on sale of
     TDR were utilised for construction of tenements and shops. The
     Tribunal held that it was clearly one project and not two projects as
     they have been treated by the AO. The Tribunal held that the AO
     cannot adopt two methods of accounting in one project to determine
     the income of the assessee. It observed that in case of construction
     activity there are two recognised methods of accounting viz. (1)
     Project Completion Method and (2) Percentage Completion Method.
     The Tribunal stated that the assessee has a right or a privilege to
     adopt any one of the methods of accounting for determining its
     profit. In the present case, the assessee had been following the
     project completion method to determine the profits of a project for
     last so many years, but, during the year under consideration the AO
     had dissected the project in two segments and for one segment he
     applied project completion method and for the remaining segment,
     he determined the profit on sale of TDR. The method of accounting
     adopted by the AO was held to be neither prevalent nor recognised
     by the ICAI or under any law. The Tribunal held that the assessee
     had rightly computed its profit on the basis of the project completion
     method. Accordingly, it upheld the order of CIT(A) and dismissed the
     appeal filed by the Revenue."


25. Respectfully following the above said decisions, we are inclined to

accept the findings of the Ld.CIT(A) and accordingly, grounds raised by

the revenue is dismissed.
                                    36
                                                  ITA.NO.1931 & 5181/MUM/2019
                                                     M/s Aristo Shelters Pvt. Ltd

26. With regard to Ground No. 2, we observe that assessee has utilized

the funds to its director and to its related concerns and we observe from

the balance sheet submitted by the assessee that assessee has both

interest free funds of ₹.1,97,57,74,648/- and interest bearing funds of

₹.1,35,16,25,011/-. From the submissions we observe that assessee had

interest bearing funds of ₹.1,35,16,25,011/- and assessee has applied for

business purpose in the work-in-progress, sundry debtors, fixed assets

and other deposits totaling to ₹.1,53,14,03,424/-. Therefore, assessee

has utilized the total interest bearing funds only for the purpose of

business purposes to the extent of ₹.1,53,14,03,424/- which is more than

interest bearing funds borrowed by the assessee. When there is a mixed

funds available to the assessee, there is legal presumption that the

assessee has utilized the interest free funds for the purpose of financing

non business activities as held in the case of CIT v. Reliance Industries

Ltd., [2019] 410 ITR 466.     Therefore, we are inclined to accept the

findings of the Ld.CIT(A) in deleting the proposed addition of notional

interest. Accordingly, the ground raised by the revenue is dismissed.



27. In the result, appeal filed by the Revenue is dismissed.
                                     37
                                                 ITA.NO.1931 & 5181/MUM/2019
                                                    M/s Aristo Shelters Pvt. Ltd

ITA.No. 5181/MUM/2019 (A.Y. 2014-15)



28. Coming to the appeal relating to A.Y. 2014-15, since facts in this

case are mutatis mutandis, therefore the decision taken in A.Y.2013-14 is

applicable to this Assessment Year also.     Accordingly, this appeal is

dismissed.



29. In the result, both the appeals filed by the Revenue are dismissed.



         Order pronounced in the open court on 06th February, 2023



     Sd/-                                               Sd/-
(SANDEEP SINGH KARHAIL)                        (S. RIFAUR RAHMAN)
JUDICIAL MEMBER                                ACCOUNTANT MEMBER
Mumbai / Dated 06/02/2023
Giridhar, Sr.PS


Copy of the Order forwarded to:
 1.   The Assessee
 2.   The Respondent.
 3.   The CIT(A), Mumbai.
 4.   CIT
 5.   DR, ITAT, Mumbai
 6.   Guard file.

      //True Copy//
                                                        BY ORDER

(Asstt. Registrar) ITAT, Mum