Section 157(d) in The Tamil Nadu Building and other Construction Workers (Regulation of Employment and Conditions of Service) Rules, 2006
(d)a bulk-head anchorage and air lock is tested at its work place at an excavation or tunneling work immediately after their installation at such place.