Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 41, Cited by 0]

Delhi District Court

Hem Chand Gupta vs Bses Rajdhani Power Ltd on 5 November, 2016

         IN THE COURT OF SHRI HIMANSHU RAMAN SINGH,
             CIVIL JUDGE­01, CENTRAL DISTRICT, DELHI

Old Case No.175/14
New Suit No.598159/16

Unique Case ID No.02401C0066832000 

Hem Chand Gupta
S/o Sh. P. L. Gupta,
R/o RZ­A­32, Vijay Enclave,
New Delhi­110045.                                                                                                     ... Plaintiff

            Versus

BSES Rajdhani Power Ltd.
BSES Bhawan, Nehru Place,
New Delhi­110019.                                                                                                  ... Defendant


Date of institution of suit                                                          :            13.01.2000
Date of pronouncement of Judgment                                                    :            05.11.2016


    SUIT FOR PERPETUAL AND MANDATORY INJUNCTIONS

JUDGMENT

1.  The brief facts as gleaned from the plaint are that the plaintiff  is living at the above mentioned address and is running a business of "Tent House" in the name and style of "Shri Balaji Tent House" on the ground floor of RZ­A­32, Vijay Enclave, New Delhi­110045.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 1 of 33

2.  It   is   further   the   case   of   the   plaintiff   that   the   plaintiff   had   a domestic   electric   connection   bearing   K.   No.1222870   in   the   above mentioned address, which was installed in the year 1989 and the same was disconnected in the year 1997 because non­payment as the plaintiff was not residing at that period at the above mentioned address.

3.  It   is   further   the   case   of   the   plaintiff   that   the   plaintiff   installed welding   and   drilling   machines   on   the   ground   floor   of   the   above mentioned address some time in October 1999 and he also applied to the defendant to convert his disconnected domestic meter into a commercial meter with the request to increase the load of electricity supply as well. As per the direction of the defendant the plaintiff deposited a sum of Rs.5,320/­, vide receipt no.12421 dated 01.10.1999. After depositing this amount the defendant restored the electricity connection and accordingly converted   the   same   from   domestic   to   commercial   by   permitting   the increased load and sanction as required by the plaintiff i.e. 3.5 K.W. Plaintiff also have a generator in the above mentioned property to meet the   requirement   of   power.   After   the   re­connection   of   electricity connection   the   defendant   did   not   issue   any   electricity   bill   inspite   of repeated requests and personal visits of the plaintiff at the office of the defendant.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 2 of 33

4.  It is further the case of the plaintiff that on 10.01.2000 one raiding party organized  by the defendant came in the area of Vijay Enclave to check the theft  of the electricity by the residents of the area. The raiding party visited the premises of the plaintiff and they were interested in some gratus but on refusal  the raiding party took the photographs of the wire, which was lying on the terrace of the above mentioned property and was connected with the generator for the supply of the electricity to the different parts of the above mentioned property. The raiding party also took photographs of the several other houses from the terrace of the plaintiff's premises. The raiding party involved the plaintiff in the theft of   electricity   and   issued   a   bill   of   Rs.1,12,287.98/­   for   the   theft   of electricity   on   11.01.2000   which   was   received   by   the   plaintiff   on 12.01.2000.   The   raiding   party/defendant   also   removed   the   electricity meter issued to the plaintiff without any prior notice and without issuing any receipt. Plaintiff seeks the following reliefs:

(i)   Decree   of   perpetual   injunction   restraining   the   defendant,   their employees, representatives, etc. to create any false bill or any penalty or lodging FIR against the plaintiff in this matter.
(ii) Decree of mandatory injunction thereby giving the direction to the defendant to restore the electricity connection with immediate effect as a necessary amenity after installing the electricity meter and withdraw the false electricity theft bill dated 11.01.2000 for a sum of Rs.1,12,287.98/­ and refund the deposited amount of Rs.1,12,287.98/­ under protest on 15.01.2000.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 3 of 33

5.   The defendant in its WS has taken the preliminary objection that the suit of the plaintiff is without any cause of action and as such the same is liable to be dismissed under Order 7 Rule 11 CPC. The suit of the plaintiff is not maintainable in the view of the fact that the plaintiff has prayed for ancillary relief of permanent injunction without seeking declaration.  It   has  been  further  stated  that  the plaintiff   cannot  ask  to refund the money at this belated stage. The theft amount was deposited on   15.01.2000  and   now   in   2013  the   plaintiff   is  asking   to   refund   the money which is highly time barred.

6.  On   30.09.2004,   the   following   issues   were   framed   by   Ld. Predecessor of this court:

1. Whether the suit of the plaintiff is maintainable in the present form? OPD
2. Whether the plaintiff is entitled to the decree for permanent injunction as prayed for? OPP
3. Whether the plaintiff is entitled to the decree for mandatory injunction as prayed for? OPP
4. Relief.

7.  Additional  issues  were  framed  by the  Ld.  Predecessor   of  court vide order dated 17.02.2014:

2A. Whether plaintiff is entitled to the refund of deposited  amount of Rs.1,12,287/? OPP 2B. Whether suit of plaintiff is barred by limitation? OPD Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 4 of 33
Evidence

8. Thereafter, matter was fixed for plaintiff's evidence.   In order to prove   the   case   plaintiff   examined   himself   as   PW1   and   he   has   not exhibited any document in affidavit.

9.  Vide   order   dated   23.08.2005   PE   was   closed.   Vide   order   dated 21.04.2015,   PE   was   again   closed   and   matter   was   fixed   for   DE. Defendant in order to prove his case examined Ms. Kavita Sharma as DW1. The witness relied upon the following documents:

            Ex.PW1/D1                            :           Copy of theft bill 
            Mark A                               :           Inspection reports dated 10.01.2000


10.  DE   was   closed   on   05.04.2016   and   matter   was   fixed   for   final arguments. 

11.  I have heard the arguments at length and gone through the record carefully. Written submissions have been filed by both the plaintiff and the defendant. The issue wise findings are as under:

Issue no. 1 Whether the suit of the plaintiff is maintainable in the present form? OPD

12.  The onus to prove this issue was on the defendant.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 5 of 33

13. It is contend by the Ld. counsel for the defendant that this court has no subject matter jurisdiction in view of The Electricity Act, 2003. The relevant provision reads as under:

Section 135. Theft of electricity..........
...Section   153.  Constitution   of   Special   Courts.(1)   The   State Government may, for the purposes of providing speedy trial of offences referred to in sections 135 to 140 and Section 150, by notification in the official gazette, constitute as many Special Courts as may be necessary for such area or areas, as may be specified in the notification." 

14. Reliance   has   also   been   placed   upon   B.   L.   Kantroo   Vs.   BSES Rajdhani Power Ltd., 154 (2008) Delhi Law times 56. In that case the plaintiff/appellant had filed a civil suit, seeking declaration that the bill issued by the respondent/defendant was false and illegal and had also sought   consequential   relief   of   injunction   against   disconnection   of electricity supply. He had also sought a declaration that he was not guilty of theft of electricity and the inspection reports/speaking orders of the defendant were illegal and void. The said civil suit was dismissed by the Hon'ble High Court of Delhi for want of jurisdiction.

"...we are of the view that any dispute about civil liability in theft cases is impliedly excluded from the jurisdiction of civil court in view of the provisions of Section 153 and 154 of the Act wherein special court has got the jurisdiction to determine any dispute regarding the quantum of civil liability specifically in theft cases and the said court can act as civil court as well as criminal court while conducting the cases before it."

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 6 of 33

15. The Hon'ble High Court vide judgment dated 02.02.2011, Super Auto Centre vs. BSES Rajdhani Power Ltd., RFA  (OS) No.66/2011 also has taken a similar view and held as under:

"The jurisdiction of civil court is not barred but the power to try offences   punishable   under   section   135   to   139   is   conferred exclusively on the Special Court constituted under section 153 of the Act and the provisions of sub­section (5) of section 154 specifically   invest   Special   Court   with   the   jurisdiction   to determine any dispute regarding the quantum of civil liability in theft cases whether or not the allegation of theft is disputed, is still entitled to make such a challenge to the disputed bill before the Special Court, even in cases where no criminal complaint is filed against the consumer and the amount of civil liability so determined shall be recovered as if it were a decree of a civil court and it can act as civil court as  well as criminal court while conducting the cases  before it."

16. It has been argued that in the present matter a case of direct theft has   been   registered   against   the   plaintiff   on   the   basis   of   the checking/inspection   report   dated   10.01.2000,   raised   by   the   then government   officers   of   the   defendant.   This   is   also   affirmed   by   the plaintiff   in   his   cross   examination   dated   21.04.2015   as   follows:   "I remember that  on 10.01.2000 my property bearing no. R/o RZ­A/32, Vijay   Enclave,   New   Delhi   has   been   booked   under   the   theft   of electricity".

 

17. The second limb of argument of the Ld. counsel for the defendant is that the present suit is not maintainable before this Court in view of the fact that the suit praying for ancillary relief of permanent injunction Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 7 of 33

without seeking the main relief of declaration is bad in the eyes of law as held in a number of cases. In case titled as Sarjiwan Singh vs. Delhi Vidyut Board,  110 (2004) DLT 633, dated 16.03.2004, wherein in the said   petition   the   Hon'ble   High   Court   while   deciding   the   common question of fact and law that whether  the plaintiff is entitled to relief in which only an injunction simplicitor has been prayed for in the wake of receiving electricity bills for sundry amounts, had dismissed the petition by holding as follows:

"Reference Nos. 1/1998, 2/1998, 3/1998, 4/1998, 5/1998 and 6/1998 are disposed of by holding that where a bill has been raised by the Electricity Department, which is prima facie legal, a declaration must be prayed for to the effect that the bill is incorrect or illegal before the plaintiff can legally pray for an injunction against the recovery made on the basis of such bills."

18. It has been argued that the plaintiff deposited the bill amount on 15.01.2000. The plaintiff after much after thought belatedly stated that the   said   amount   was   deposited   under   protest   by   preferring   an amendment in the plaint in the year  2013.

It   has   been   argued   that   the   plaintiff   failed   to   seek   a   relief   of declaration to the effect that the bill was incorrect or illegal and instead sought a decree of recovery of sum so deposited by him which was also highly time barred. It has been argued that when the theft bill is not challenged per se there is no question of granting a relief of recovery of amount qua the said bill so deposited by the plaintiff. 

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 8 of 33

I may gainfully refer to the judgment passed by the Hon'ble High Court of Delhi in the case No. CRP No. 72/2006 in the matter of NDPL vs. Ganesh Aggarwal which laid down that where the bill is prima facie not legal then the suit for simplicitor injunction is also maintainable. It is settled principle of law that civil court has jurisdiction in cases where fundamental fairness of procedure is not followed.

19. In CRP No.72/2006 the Hon'ble High Court of Delhi vide order dated 02.11.2006 noted that an exception which is carved out in para 7 of the judgment in Sarjiwan Singh vs. Delhi Vidyut Board, 110 (2004) DLT 633 is that the court must be satisfied that the bill is prima facie legal. The relevant portion is as under:

"7. In these circumstances the Order dated 25.09.1997 in Suit No.791/1997   does   not   disclose   any   error   in   the   exercise   of jurisdiction;   CRNo.1186/1997   is   accordingly   dismissed. Reference   Nos.   1/1998,   2/1998,   3/1998,   4/1998,   5/1998   and 6/1998 are disposed of by holding that where a bill has been raised by the Electricity Department, which is prima facie legal, a declaration must be prayed for to the effect that the bill is incorrect or illegal before the Plaintiff can legally pray for an injunction   against   the   recoveries   made   on   the   basis   of   such bills."

20.  In B. L. Kantroo vs. BSES Rajdhani Power Ltd., 154 (2008) DLT 56   (DB)   also   exceptions   were   carved  out.   The   relevant  portion  is   as under:

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 9 of 33
27. No doubt Electricity Act is a complete code in itself, but in the following cases, civil suit can be entertained even though the jurisdiction of the civil Court may have been specifically ousted.  Where provisions of law are not complied with or the Forum or Tribunal does not act according to the fundamental principles of judicial procedure, the jurisdiction of civil Court is clearly implied. This was laid down under the following cases:
(a) if the court is of prima facie opinion that the order is nullity in the eye of law because of any 'jurisdictional error' in exercise of the power by the Commissioner or that the order is outside the Act - Shiv Kumar Chadha v. MCD, JT 1993 (3) SC 238.
(b) even if jurisdiction is so, excluded, the Civil Courts have   jurisdiction   to   examine   into   cases  where   the provisions of the Act have not been complied with, or the statutory Tribunal has not acted in conformity with the   fundamental   principle   of   judicial   procedure   -

Secretary of State vs. Mask and Co., AIR 1940 Privy Council 105.

21.  One of the exception is that jurisdiction of the civil court is not barred   where   provisions   of   the   Act   have   not   been   complied   with. Therefore,   in   view   of   para   7   of   of   Sarjiwan   Singh   vs.   Delhi   Vidyut Board and further clarification in CRP No. 72/2006, the onus is now cast upon the plaintiff to show that the bill is prima facie illegal.  Therefore this issue can be decided only after appreciating the evidence led by the plaintiff and after discussing issue no.2 and 3.

Issue no. 2 and 3

2.   Whether   the   plaintiff   is   entitled   to   the   decree   for permanent injunction as prayed for? OPP

3.   Whether   the   plaintiff   is   entitled   to   the   decree   for Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 10 of 33

mandatory injunction as prayed for? OPP

22.  The onus to prove these issues was on the plaintiff.

23.  It   has   been   contended   by  the   Ld.   counsel   for   the  plaintiff   that defendant has miserably failed to follow the core principle of natural justice. It has been contended that no show cause notice ever issued to the defendant. It has further contended that the defendant never handed over  any show  cause  notice prior  to filing of  suit or  given any civil opportunity of personal hearing before raising of such bill. It has been further contended that the plaintiff was never given opportunity to rebut the allegations raised by the defendant. It has been further contended that the bill  was received on 12.01.2000 with direction to deposit the same on or before 13.01.2000 thereby violating the due process of law with arbitrary act.

24. Ld counsel for the plaintiff has placed reliance on the judgment passed by the Hon'ble Delhi High Court in the case titled as M/s Rakesh Rubber Industries vs. MCD, 54 (1994) DLT 156 (DB).  The relevant portion is as under:

"2. The controversy is squarely covered by a Division Bench judgment dated April 10, 1991 in Civil Writ No.669 of 1990. We see   no   reason   why   the   respondent   should   not   apply   that judgment to all cases, like the present one, where the liability  of a SIP consumer to be re­classified and billed on higher tariff as LIP   user,   or   the   liability   of   a   consumer   to   pay   penalty   for alleged misuse of electricity is disputed.
Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 11 of 33
3. Following the aforesaid Division Bench judgment, we quash the   impugned  bills   and  direct   the  respondents  to  give  to   the petitioner   an   opportunity   to   be   heard   and   then   to   take   a decision   on   the   matter   in   accordance   with   law,   before proceeding   to   raise   any   bill   for   misuse   charges   or   for consumption of electricity at the higher rates on LIP basis."

25. Ld counsel for the plaintiff has placed reliance on the judgment passed   by   the   Hon'ble   Delhi   High   Court   in   the   case   titled   as  J.   K. Steelomelt (P) Ltd. vs. BSES Rajdhani Power Ltd., 140 (2007) DLT

563. The relevant portion is as under:

"21. This Court has in a series of decisions in Udham Singh v. BSES Rajdhani Power Ltd., 137 (2007) DLT 500, Col. R. K. Nayyar   v.   BSES,   140   (2007)   DLT   257   (Judgment   dated 18.4.2007   in   W.P.   (C)   No.   2904   of   2005)   and   Smt.   Jagdish Narayan   v.   NDPL,   140   (2007)   DLT   307   (Judgment   dated 18.4.2007 in W.P. (C) No. 10287 of 2005, etc.) interpreted the provisions   of   Section   135   of   the   Act   read   with   the   DERC Regulations.   The   relevant   passages   of   the   last   mentioned judgment in Jagdish Narayan reads as under:
23.   What   is   central   to   the   definition   of   theft   under Section   135   of   the   Act,   which   according   to   the respondent   covers   DAE   as   well   is   the   element   of 'dishonesty'. Therefore the mens rea or the intention of the consumer to dishonestly abstract electricity must be proved   "conclusively"   to   bring   home   the   charge   of DAE.   Therefore   the   requirement   of   "conclusive evidence" in terms of Regulations 25(iii) is consistent with the statutory mandate of Section 135(1). That can be established only by showing that the consumer was responsible   for   tampering   the   meter   by   some   visible means. To external manifestations of tempering, as has been found in the inspections conducted in the present case, can only raise a suspicion of DAE. That suspicion will have to be made good by some tangible evidence of physical means of tampering before the presumption can be drawn that it was the consumer who tempered the Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 12 of 33
meter.
25. Applying the above test, it has to be held that an automatic   presumption   of   DAE   on   the   basis   of   the external   symptoms   of   tampering   together   with   the analysis of the consumption pattern would not be a safe and   error   free   method.   Some   other   tangible   evidence must  be  shown  to  exist.  An  accu  check  meter  can  be deployed   to  find   out  if   the  meter   is   in  fact   recording lesser units. The analysis of the consumption pattern in terms of the Regulation 26(ii) is merely corroborative and   not   by   itself   substantive   evidence   of   DAE.   The decision of this Court in Udham Singh v. BSES Rajdhani Power Ltd., 136 (2007) DLT 500 is to the same effect. In fact,   the   formula   is   applied   in   terms   of   Regulations 25(iv) read with 26 (ii) only for determining the penalty payable by the consumer once a case of either direct theft or DAE has been made out. The penalty formula cannot itself supply the proof of DAE or theft.
24. In view of the above conclusion, the other submissions of the petitioner   about   it   not   being   furnished   with   the   copy   of   the inspection report dated 13.12.2004 along with the show cause notice issued prior to the passing of the speaking order need not be examined. However, it should be observed that the burden of showing the supply of relevant documents to the petitioner is definitely on the respondent. The endorsement on the inspection report dated 13.12.2004 shows that the consumer had refused to sign. However, this by itself does not settle the issue since this endorsement is by an official of the respondent. The respondent will then have to show that a copy of this report was dispatched to   the   petitioner   by   registered   post   or   any   other   verifiable means.  Without   the  supply   of  the   documents   upon  which  the respondent   is   relying   to   draw   an   inference   adverse   to   the petitioner, there would be justification in the consumer claiming that   there   has   been   a   violation   of   the   principles   of   natural justice.  In   such   cases,   it   will   not   be   a   valid   defence   for   the respondent to contend that the petitioner should have asked for a copy of the report. If the petitioner in fact did not know that such a report existed then it is hardly surprising that it did ask for   such   a   report.   The   decision   of   this   Court   in   Harvinder Motors v. BSES Rajdhani Power Ltd. 135 ( 2006) DLT 198 also underscores the importance of complying with the principles of Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 13 of 33
natural justice.
25. Nothing has been brought on record in the instant case to show that the respondent had in fact dispatched the inspection report dated 13.12.2004 to the petitioner by registered post or otherwise. That burden was on the respondent which it did not discharge. The mere fact that the speaking order contained a reference   to   an   enforcement   case   dated   13.12.2004   without anything more can hardly be construed to be a reference to the inspection   of   that   date.   The   photographs   too   do   not   show whether in fact the inspection report was prepared and given to the petitioner.
Connected load alone cannot form basis for DAE.
26. The petitioner is also right in contending that the reduction in the consumption pattern in the six months previous to the inspection   report   dated   13.12.2004   was   consistent   with   its application for reduction of sanctioned load from 78 HP to 20 HP.   The   explanation   offered   by   the   respondent   that   the petitioner   had   not   followed   up   this   application   can   hardly justify an inference of DAE on the basis of the reduced units. It is one thing to plead that the connected load is more than the sanctioned load but in another to say that in fact the connected load has been used throughout by the petitioner. This could be only verified by the actual consumption recorded in the meter.

If, as is indicated in the inspection report, the meter wiring is OK and the disc is moving in the right direction then the actual units recorded will reflect how much of the connected load is in fact being used. Therefore, merely because the connected load is more than the sanctioned load cannot lead to an automatic presumption that the entire connected load is being used by the consumer throughout the period.

Conclusion

27.   For   all   of   the   above   reasons,   this   Court   finds   that   the impugned   speaking   order   dated   24.12.2004   holding   that   the petitioner   is   guilty   of   DAE   is   unsustainable   in   law   and   is accordingly set aside. Consequently, the demand raised in the impugned bill dated 11.1.2005 also would stand quashed. The amount   paid   by   the   petitioner   pursuant   to   the   interim   order dated   8.2.2005  will   now  become  refundable  to  the  petitioner together with interest at 12 per cent per annum from the date of payment till the date of refund. The refund should be made to the petitioner within a period of 4 weeks from today and in any Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 14 of 33

event not later than 25.5.2007. In addition costs of Rs.5,000 will be paid by the respondent to the petitioner within a period of 4 weeks and in any event not later than 25.5.2007."

26. Ld counsel for the plaintiff has placed reliance on the judgment passed by the Hon'ble Delhi High Court in the case titled as  Kuldeep Singh Dhingra vs. Municipal Corporation of Delhi & Ors., AIR 1992 Delhi 228. The relevant portion is as under:

"11. ....The Undertaking ignored them before issuing the show­ cause notice on the ground that there was no such requirement. It ignored them again after notice presumably on the ground that they had not been made in response to the notice thereby reducing fairness into something worst than a rigid, ritualistic abstraction where the victim has been lock­jawed. It must not be forgotten that fair hearing, however minimal, is the requirement of administrative gentlemanliness. What has happened here is that natural justice which V. R. Krishna Iyer, J. described as "a brooding omnipresence" has been baried fathoms deep. It was observed   by   Lord   Parker   that   good   administration   and   an honest or bona fide decision require not only impartiality or merely bringing one's mind to bear on the problem, but acting fairly In re. H. K. (An Infant) 1965 AC 201. Unfortunately, by ignoring the representations made by the plaintiff, the study of which could have helped the defendants in taking a fair and balanced view, they have acted unfairly or unjustly. What could have promoted was thus frozen.
What should then be done?
Byles   J.   tells   us   in   Cooper   v.   Wandeworth   Board   of   Works:
(1863) 14 CB (NS) 180:
"I remember to have heard it observed by a very learned man that even. God himself did not pass sentence upon Adam before he   was   called   upon   to   make   his   defence.   "Adam   (say   God) "where   art   thou?   Hast   thou   not   eaten   of   the   tree   whereof   I commanded thee that thou shouldest not eat:" And the same question was put to Eve also."

Let the defendants follow the laws of God, for they are the laws of man also. Opportunity shall be given to the plaintiff to make Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 15 of 33

his defence, if he has any, and in so making it, he shall also be, in view of the peculiar facts of the case, afforded one hearing. In   the   meanwhile   the   defendants   may   remove   the   metering equipment etc. which may be required for investigation but shall see   to   it   that   supply   of   electricity   is   restored   to  the   plaintiff within   two   days   from   today.   Of   course,   nothing   stops   the defendants,   not   this   order   at   least,   from   taking   appropriate action after hearing the plaintiff in his defence."

27. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Delhi High Court in the case titled as Col. R. K. Nayar (Retd.) vs. BSES Rajdhani Power Ltd., 140 (2007) DLT 257. The relevant portion is as under:

"20. Applying these tests in the instant case it is seen that the petitioner himself was hardly shown to be responsible for the tampering of the meter. Since it was he who complained having found   the   meter   tempered,   it   was   unreasonable   for   the respondent company to turn around and accuse the petitioner himself of tampering the meter. The documents dated 7.10.1998 hardly reads like an inspection report. There are no signatures of the team of officers who visited the premises. There is no signature   of   the   petitioner   or   even   an   endorsement   that   he refused to sign. In fact, it is not even in the standard format. In the circumstances, the petitioner is justified in doubting if such inspection took place at all. Moreover, the presumption that is sought to be drawn in the present case is completely belied by the   fact   that,   after   the   two   inspections   on   1.8.1998   and 7.10.1998 ( a fact that remains disputed) the I.G. (Enforcement) of the DVB had on 24.12.1998 asked for a re­examination of the case, a fact that is not denied by the respondent. Nowhere in the pleadings   or   even   in   the   written   submissions   filed   by   the respondent   is   it   actually   explained   whether   in   fact   that   re­ examination took place. By merely reiterating what was found at the time of inspection in the Speaking Order, the respondent does not add to the understanding whether the petitioner can be held to be guilty of FAE.
21. A strange argument is advanced that an amnesty scheme was commenced in 1999 for a specific period and that "simply Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 16 of 33
informing   breakage   of   seal   of   CT   and   meter   box     when   the amnesty   scheme   was   not   operative   does   not   absolve   the petitioner from the case of fraudulent abstraction of energy."

This   argument   does   not   stand   to   logic.   It   certainly   does   not answer   the   point   made   by   the   petitioner   that   the   respondent failed to take action on his complaint made on 18.6.1997. The only other ground on which the inference of FAE is sought to be made   is   the   pattern   of   consumption   and   comparing   the computed   consumption   with   the   recorded   consumption.   As already   held,   the   consumption   pattern  by   itself   again   cannot lead to an inference of FAE it would have to corroborate what is   detected   on   a   physical   examination.   An   accu   check   meter could have been used to detect if the meter was recording lesser energy   than   it   should.   That,   however,   was   not   done   in   the instant case. Since it is not shown that there was some device or even   any  technique   used   to  slow   down  the   meter   to   make   it record lesser energy, the consumption pattern cannot be itself constitute the substantial evidence of FAE. On the contrary in the instant case since admittedly the petitioner has informed the respondent   since   May   1992   that   the   use   of   a   portion   of   the premises was no longer domestic but commercial, that factor was   required   to   be   accounted   for   determining   if   there   was anything unusual in the consumption pattern. The fact that the meter   was   replaced   in   June   2002   and   the   petitioner   was refunded a sum of Rs.1.92 lakh for the period from 2.7.1999 to 26.6.2002 also is relevant in this regard. However, the Speaking Order is silent on these aspects.

23.   The   petitioner   has   in   his   written   submissions   given   a calculation of the amounts due to him and claims that a sum of Rs.10,48,364/­   against   K.   No.   0803434   and   a   sum   of Rs.2,76,841/­ against K. No. 1333658 is owing to him by the respondent. This amount includes the interest he claims to have paid on the loans borrowed to make the payment. He has also enclosed   a   working   sheet   to   his   application   which   gives   the details.   It   appears   reasonable   that   the   petitioner   should   be refunded   the   amounts   paid   by   him   in   respect   of   the   two impugned   theft   bills   after   adjusting   the   normal   changes   for actual   recorded  consumption,   together   with   interest     at   12% p.a. from the date of payment by the petitioner to the date of refund by the respondent. A direction is accordingly issued to the   respondent   to   refund   the   aforementioned   sum   to   the Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 17 of 33

petitioner within a period of 8 weeks from today and in any event not later than 20.6.2007. Any delay beyond this period will attract a higher interest at 18% p.a. The respondent will also pay to the petitioner costs in the sum of Rs.10,000 within a period of four weeks from today and in any event not later than 20.5.2007."

28. Ld counsel for the plaintiff has placed reliance on the judgment passed by the Hon'ble Delhi High Court in the case titled as  Ramesh Chander & Ors. vs. State of Delhi & Anr. 68 (1997) DLT 257.  The relevant portion is as under:

"6. In Jagarnath Singh v. Krishna Murthy and Another, AIR 1967   SC   947,   the   Supreme   Court   held   that   existence   of   a tampered meter, does not amount to 'such an artificial means for the abstraction of electricity' as would make it an offence under Section 39 of the Act.
7. Reverting to the case in hand, the charge does not even say that the abstraction was dishonest. In order to frame a charge under Section 39 of the Act, there must be material on record to, prima facie, show dishonest abstraction, consumption or use of energy. Learned Counsel for the respondents has not been able to point out any circumstance coupled with the tampered seals indicating dishonest intention of the petitioners as contemplated by Section 39 of the Act.
8.  Having  regard  to the  aforesaid  discussion  and keeping  in view of the above referred decisions of the Supreme Court, I am of   the   opinion   that   no   prima   facie   case   has   been   made   out against the petitioners under Section 39 of the Indian Electricity Act and Section 44, which is a penalty provision. Accordingly, the charge framed against the petitioners is hereby quashed. The matter is disposed of."

29. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Delhi High Court in the case titled as Jagdish Narayan vs. North Delhi Power Limited & Anr., 140 (2007) Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 18 of 33

DLT 307. The relevant portion is as under:

"16. Relying on the judgment of the Hon'ble Supreme Court in P.   R.   Metrani   v.   Commissioner   of   Income   Tax,   Bangalore, (2007)   1   SCC   789,   Mr.   Kumar   submitted   that   the   words "conclusive evidence" occurring in Regulation 25 (iii) had to be   interpreted   as   requiring   proof   to   be   determined   by conclusive   means   and   not   by   a   deeming   provision   by   way legislative fiction.  Referring to Regulation 25(vii), Mr. Kumar submitted that the requirement of handing over a copy of the inspection report to the consumer failing which having it pasted on the premises had not been adhered to in the instance case.

Finally, adverting to the consumption patter under Regulation 26 (ii), Mr. Kumar submitted that the formula for determining penalty in the event of theft cannot be applied unless there is in fact a discovery of theft. In other words, the penalty formula cannot be first applied to conclude that there was a case of theft or DAE.

24. The decision of the Hon'ble Supreme Court in Jagannath Singh   v.   B.S.   Ramaswamy,   [1966]   1   SCR   885   is   illustrative although   there   the   Court   was   concerned   with   a   criminal conviction for the offence of theft of electricity under Sections 39 and 44 of the Indian Electricity Act, 1910. The approach to the requirement of proof of dishonest abstraction of energy is nevertheless relevant for the present case. The Hon'ble Supreme Court held that the existence of artificial means for abstracting energy can only give rise to a presumption that there had been a dishonest abstraction. The supplier would still have to show that the   consumer   is   responsible   for   such   tampering.   In   the   said case, it was contended that the existence of an open stud­hole on the meter was sufficient proof that dishonest abstraction of energy   had   taken   place.   In   answer   to   that   contention,   the Hon'ble Supreme Court observed as under:

"A   meter   with   an   exposed   stud­hole,   without   more,   is   not   a perfected   instrument   for   unauthorized   taking   of   energy,   and cannot be regarded as an artificial means of its abstraction. To make it such an artificial means, the tampering must go further, and   the   meter   must   be   converted   into   an   instrument   for recording   less   than   the   units   actually   passing   through   it.   A check   meter   affords   an   easy   method   of   proving   that   the consumer's meter is recording less than the units consumed and Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 19 of 33
is   being   used   as   an   artificial   means   for   abstraction   of   the unrecorded energy. To bring home the charge under Section 39, the   prosecution   must   also   prove   that   the   consumer   is responsible   for   the   tampering.  The   evidence   adduced   by   the prosecution must establish beyond doubt that the consumer is guilty of dishonest abstraction of energy."

25. Applying the above test, it has to be held that an automatic presumption of DAE on the basis of the external symptoms of tampering together with the analysis of the consumption pattern would not be a safe and error free method. Some other tangible evidence must been shown to exist. An accu check meter can be deployed to find out if the meter is in fact recording lesser units. The   analysis   of   the   consumption   pattern   in   terms   of   the Regulation   26(ii)   is   merely   corroborative   and   not   by   itself substantive   evidence   of   DAE.   The   decision   of   this   Court   in Udham Singh v. BSES Rajdhani Power Ltd., 136 (2007) DLT 500 is to the same effect. In fact, the formula is applied in terms of   Regulation   25   (iv)   read   with   Regulation   26(ii)   only   for determining the penalty payable by the consumer once a case of either   direct   theft   of   DAE   has   been   made   out.   The   penalty formula cannot itself supply the proof of DAE or theft.

30. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Delhi High Court in the case titled as Udham Singh vs. BSES Rajdhani Power Ltd., vs. 136 (2007) DLT 500. The relevant portion is as under:

"18. I would not dwell at length upon the difference which were introduced   by   Section   126,   which   in   many   respects,   is significant from the provisions of Regulations 25 and 26. The latter enumerate a common procedure to deal with dishonest abstraction of electricity, ("DAE") and theft; the relevant load factors   too   are   common.   However,   the   Central   Act   creates separate   mechanisms   for   "unauthorized   use   of   electricity"   ­ which conceptually, and definitionally overlaps with "dishonest abstraction of electricity" ­ and theft. For the latter, a separate mechanism   has   been   enacted   in   the   form   of   an   independent adjudicating body, i.e.  the Special Court. The Court has to try the case, and in the event of finding of guilt, can also determine Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 20 of 33
civil liability.
19. A harmonious reading of all the provisions indicates that an inspection should preceded assessment that the consumer has indulged in DAE. The licensee is obliged to follow principles of natural justice, and grant reasonable hearing [Section 126(3) and Regulation 25(viii)]. Mere irregularity in meter seals, or breakage of glass, etc. do not authorize the licensee to issue show­cause   notice;   the   assessing   officer   has   to   observe   the consumption pattern, before the personal hearing is granted to the consumer [Regulation 25(iv) read with Regulation 26(ii)]. The definition also envisons some collateral evidence of such objectionable behaviour; it enacts that DAE means­ "......abstraction of electrical energy where accessibility to the internal   mechanism   of   the   metering   equipment   and   some collateral evidence is found to support the conclusion that the meter   has   been   caused   to   record   less   energy   than   actually passing through it." (Emphasis supplied) The   necessity   of   recording   existence   of   such   materials (collateral evidence) is reinforced by Regulation 25(iii) which obliges the inspecting team to record if "conclusive evidence"

substantiating   the   fact   that   energy   was   being   dishonestly abstracted was found or not."

21. I am of the opinion that in the absence of any collateral materials, or conclusive proof, about DAE, the mere existence of an irregular seal could not have justified such findings. The inference led to "study" of the consumption pattern, which was application of a calculation formula, and its comparison with the billing resorted to. The facts of this case did not disclose any evidence in support of the conclusion reached by the assessing officer.

22. For the foregoing reasons, the writ petition is entitled to succeed.   The   impugned   bill,   and   speaking   order   are   hereby quashed. The sum of Rs. One lakh deposited pursuant to interim order of the Court shall be refunded by the respondent to the petitioner within six weeks. The writ petition is allowed in above terms."

31. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Delhi High Court in the case titled as Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 21 of 33

Kiran Mehta vs. B.S.E.S. Rajdhani Power Ltd., 2011 (121 )DRJ 611. The relevant portion is as under:

"8....It is argued that though in the inspection report, it is noted that   photographs   have   been   taken   but   the   said   photographs have not been produced inspite of directions from time to time of the Court in these proceedings and imposition of costs on the respondent for not production of the records. The counsel has argued   that   unless   the   respondent   prima   facie   satisfies   this Court of the basis of a case of direct theft, the petitioner cannot be permitted to face the prosecution or to pay the bill for direct theft. It is also contended that if the writ petition is dismissed, the   interim   order   made   in   this   writ   petition   and   pursuant whereto electricity supply was restored to the petitioner would also disappear and the petitioner would again be left without electricity, even though the respondent inspite of directions has not been able to place any material before this Court of any merit in its case of direct theft against the petitioner.
9. The question whether the inspection report of the respondent is correct or not, is a question of fact. If this Court was to in this writ petition hold that no case for direct theft is made out and the bill for direct theft was to be quashed for the said reason, the same would foreclose the right of the respondent of proving before the Special Court by cogent evidence the case if any of direct   theft   against   the   petitioner   or   of   genuineness   of   the inspection report. This Court in writ jurisdiction cannot allow any   such   finality   when   disputed   questions   of   fact   requiring adjudication   by   examination   and   cross­examination   of witnesses arises.
12.   The   counsel   for   the   respondent   also   states   that   the respondent has already placed before this Court documents to establish a case of direct theft.
13. In the circumstances, the writ petition is disposed of with the directions:­
(i)  that as against the demand of the respondent against the petitioner of Rs.3,51,396/­ for direct theft charges, the petitioner till the disposal of the complaint case, shall be liable   to   pay   only   the   sum   of   Rs.1,10,000/­   already deposited   with   the   respondent.   If   the   petitioner   is ultimately   held   liable   for   any   further   amount,   the petitioner   shall   remain   liable   to   pay   the   same   together Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16             Page 22 of 33
with the applicable interest.
(ii)   conversely,   if   the   complaint   of   the   respondent   is dismissed, consequently the direct theft bill shall also fail and   the   petitioner   shall   then   be   entitled   to refund/adjustment of Rs.1,10,000/­ paid by her against the said bill together with interest at rate of interest in terms of Section 154(6) of the Act from the date when the said amount   was   deposited   by   the   petitioner   with   the respondent under orders of this Court and till the date of refund/adjustment.
(iii) it shall be open to the petitioner, if summoned in the direct  theft  complaint  to   oppose     the  said  claim   on  all grounds available under the law.
(iv) the petitioner if so desirous, shall also have liberty to approach the Special Court impugning the action of the respondent. No order as to costs."

32. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Supreme Court in the case titled as P. R. Metrani vs. Commissioner of Income Tax, Bangalore, JT 2006 (10) SC 537. The relevant portion is as under:

"15. A presumption is an inference of fact drawn from other known or proved facts. It is a rule of law under which courts are authorized to draw a particular inference from a particular fact. It is of three types, (i) "may presume", (ii) "shall presume" and
(iii)"conclusive   proof".   "May   presume"   leaves   it   to   the discretion of the court to make the presumption according to the circumstances  of the case. "Shall presume" leaves no option with the court not to make the presumption. The court is bound to take the fact as proved until evidence is given to disprove it.

In this sense such presumption is also rebuttable. "Conclusive proof" gives an artificial probative effect by the law to certain facts. No evidence is  allowed to be produced with a view to combating   that   effect.   In   this   sense,   this   is   irrebuttable presumption."

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 23 of 33

33. Ld   counsel   for   the   plaintiff   has   also   placed   reliance   on   the judgment passed by the Hon'ble Supreme Court in the case titled as M/s Time Properties & Promoters vs. Delhi Development Authority, C.R. 245/1984. The relevant portion is as under:

"6. The ratio of these decisions is that if there is legal necessity for a declaration before grant of relief of injunction it would not be   a   suit   for   injunction   and   if   grant   of   declaration   is   not necessary the suit would be purely a suit for injunction.
9.   Learned   counsel   for   the   respondent   refers   to   M/s   Ratlam Straw Board Mills Pvt. Ltd. vs. Union of India and another, AIR 1975 Delhi  270 (4) wherein the  plaintiff  had filed a suit  for declaration that contract came to end by acts of defendants and injunction be issued restraining the defendants from recovering the specified amount. It was held that ad valorem court fee was payable.  In Punjab  Exchange  vs. Rajdhani  Grains   Ltd. 1975 Raj. Law Reporter 485 (5) it has been observed that if, in a suit for mandatory injunction relief claimed by the plaintiff amounts to   his   asking   for   possession   from   a   defendant   in   exclusive possession the court fee payable is as required by Section 7 (v) of the Court Fee Act. In Asit Baran Chaudhary and another vs. Profulla Chandra Bose, AIR 1984  Calcutta 366 (6) the plaintiff was seeking to avoid forfeiture of a sum of Rs.91,900 which on terms of the contract the defendant No.1 had forfeited. Under those circumstances it was held that the plaintiff was liable to pay ad valorem court fee. In the instant case it is not the case of the defendant that sum of Rs.6,50,000 has already been forfeited by it. These precedents referred to by the learned counsel for the defendant are not relevant for the determination of court fee payable in the present case.
10.   The   trial   court   acted   illegally   in   the   exercise   of   its jurisdiction by demanding ad valorem court fee. The impugned order is liable to be set aside. The revision petition is accepted setting aside the impugned order dated 21st February, 1984. It is held that the suit has been properly valued for purposes of court fee  and  jurisdiction  and  proper   court  fee  has   been  paid.   No order as to costs. Parties are directed to appear before the trial court on 22nd July, 1985."

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 24 of 33

34. It has been contended by the Ld. counsel for the defendant that on 10.01.2000,   inspection   of   connection   bearing   no.   K.   No.1222870 installed at property bearing no. RZ­A­32, Vijay Enclave, New Delhi (said   'Property')   was   conducted   by   the   Enforcement   Team   alongwith M.T.D   (Meter   Testing   Department)   staff,   Zonal   Staff   and   CISF Officials. At the time of inspection plaintiff was present during the entire process of the inspection and found indulged in direct theft of electricity by   bypassing   meter   No.  E­99728684   R­000942  MF   with   the   help   of PVC wire.

35. For ready reference, the relevant extract of the inspection report has been reproduced herein: (already marked as Exhibit DW1/1) "User Sh. Hem Chand Gupta, address RZ­32A, Vijay Enclave, New Delhi. C/load Drill m/c 1x1/2 HP, Welding Set 1x5 HP, Jet Pump 1x1  HP, Fan 3x60w, lamp 3x60w. The total connected load found 5.479 KW IP.  This defaulter was using electricity by bypassing meter  no. E­99728684 R­000942 MF. The meter &   PVC   wire   removed   from   site.   The   necessary   photographs were taken at site. The reel of photographs H/O (handover) to Sh.  N. Chowdhary  inspector   zone  for   developing  & printing. The   meter,   service   line/PVC   wires   through   which   the   above defaulters were stealing electricity removed from site by zonal staff.  AE zone is requested to raise bills on account of direct theft   as   per   connected   load   &   category   also   as   per   tariff provisions   as   per   rules.    AE   Zone   is   requested   to   deposit removed   material   from   site   deposit   in   police   station   while lodging FIR. AE Zone is further requested to lodge FIR U/S 39 of I.L.A read with 379 of I.P.C as per rules. The copy of raised bill sent to XEN Enf. West. The original copy of this inspection report H/O to Sh. N. Chowdhary Inspector Zone No. 1503 for AE Zone for taking further necessary action as per rules at his ends." 

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 25 of 33

36. As per applicable rules the premises of the plaintiff was booked under DT (Direct Theft) and the impugned bill of Rs.1,12,287.98/­ was duly raised on 11.01.2000.

37.  It is further argued by the Ld. counsel for the defendant that the plaintiff had never lodged a complaint before Police Station or higher authority   of   the   defendant   department   in   respect   of   his   allegation   of bribery   against   government   officers   (CISF   officers,   DVB   Officials, including enforcement team, MTD staff and Zonal staff).

38. It has been argued that defendant had discharged all functions in accordance with all applicable provisions and rules and in a fair  and transparent manner.

39. Sh. Hem Chand Gupta was examined as PW1. Ld. counsel for the defendant has attracted the attention of the court towards the following statements. In   para   no.6,   of   the   affidavit   by   way   of   evidence,   the plaintiff/deponent   affirms   that   he   has   a   generator   in   the   property   in question to meet the requirement of power and to meet the requirement in an emergency. Further, in para no.8 of the affidavit in evidence of the plaintiff, it has been deposed that on refusal of gratification to the raiding party, they took the photographs of the wire, which was lying on the terrace of the said property and was connected with the Generator for the Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 26 of 33

supply of electricity in different parts of the said property.

40. It is pertinent to note that the plaintiff has not filed, any proof of installation   of   generator   set   in   the   premises   in   question.   The   said averments in relation to demanding of gratification and on refusal of the same a theft case was initiated is an after thought story of the plaintiff. Not a single iota of evidence supporting plaintiff's story has been placed before this Court. Even CISF was present at the time of inspection which is not denied by the plaintiff.

41. Ms.   Kavita   Sharma   was   examined   as   DW1,   on   behalf   of   the defendant,   Ms.   Kavita   Sharma,   presently   working   as   a   DGM   (T) Contract,   in   the   Delhi   Transo   Ltd,   and   the   then   government   officer working  with  the  DVB  as  AE(Enf.)W,  filed  the  evidence  by  way   of affidavit as 'DW1'. The DW1 was part of the inspection team that visited the  premises  of   the  plaintiff   on  10.01.2000,  and  therefore  conversant with the facts and circumstances of the case.

42. The DW1 deposed that the theft amount was deposited, without any   protest   on   15.01.2000.   Further,   the   DW1   reiterated   the   contents pertaining  to  inspection  that  was  conducted   in  the   said  premises   and found   the   plaintiff   indulged   in   direct   theft,   as   stated   in   the   written statement filed on behalf of the defendant, as true and correct.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 27 of 33

43. The Ld. counsel for the defendant was referred to the following contradictions in the testimony of the plaintiff (a) In cross examination of the plaintiff dated 28.01.2015, it has been submitted by the plaintiff that the receipt of generator and the photograph of the same were filed before   the   Court.   Whereas,   in   deferred   cross   examination   dated 21.04.2015, the plaintiff has admitted that there is no proof  of generator in the court file.

b) In para no.8 of the affidavit by way of evidence of the plaintiff it has been alleged by the plaintiff that on refusal of gratification to the raiding party they, took the photographs of the wire, which was lying on the terrace of the said property whereas it has been submitted by the plaintiff in his cross examination that it is wrong to suggest that raiding team has taken photographs of PVC wires in his presence.

c) In cross examination of the plaintiff dated 23.08.2005, it has been admitted by the plaintiff that entire inspection was carried out in his presence, whereas in cross examination dated 21.04.2015, it has been submitted by the plaintiff that during the raid he had left the raiding team alone for once or twice further he has submitted that he had left the raiding team alone for about 10 minutes or so.

44. It   has   been   contended   that   the   inspection   was   conducted   when power   distribution   was   under   the   government   and   that   government officials inspected and then raised the impugned bill and the Court must consider the well recognised principle that prima facie public servants Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 28 of 33

must be presumed to act honestly and conscientiously and their evidence has to be assessed on its intrinsic worth and cannot be discarded merely on   the   ground   that   being   public   servants   they   are   interested   in   the success of their case.

45. Reliance has been placed upon State of Kerala vs. Mathew (M.M) and Anr., 1978 AIR 1571, 1979 SCR (1) 264, the Hon'ble Lordship of the Supreme Court have observed as follows:

"It is true that courts of law have to judge the evidence before them   by   applying   the   well   recognised   test   of   basic   human probabilities   and   that   some   of   the   observations   made   by   the sessions  Judges especially one to the effect that the evidence of officers   constituting   the   inspecting   party   is   highly   interested because   they   want  that   the   accused   are   convicted   cannot   be accepted as it runs counter to the well recognised principle that prima facie public servants must be presumed to act honestly and conscientiously and their evidence has to be assessed on its intrinsic worth and cannot be discarded merely on the ground that being public servants they are interested in the success of their case"

46.  DW1 Ms. Kavita Sharma was cross examined at length by the plaintiff. The witness admitted that she does not remember the exact reading of the meter at the time of removal. The witness also stated that the   signatures   of   the   defaulter   is   to   be   taken   on   the   load   inspection report. The witness also stated in case party refused to sign then such endorsement is to be made on the report. A copy of the report also given to the party. There are no signatures on the load inspection report of the plaintiff. There is no mention of the fact that the plaintiff has refused to Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 29 of 33

sign.

47.  The   defendant   has   failed   to   produce   on   record   any   document which can show that the plaintiff was present at the site of inspection. On the contrary, the inspection note does not bear the signatures of the plaintiff.   The   defendant   has   also   failed   to   prove   that   even   the   basic procedure  was   followed   and   the   plaintiff   was   given  a   fair   chance   of hearing. In light of the foregoing discussion, it is held that the plaintiff has been able to prove that the bill is prima facie illegal.

Issue no.1 stands decided accordingly against the defendant. Issue no.2 was whether the plaintiff is entitled to a decree for permanent injunction thereby restraining the defendants from creating any false bill or penalty. Such kind of protection is available to each and every one and there is no requirement of granting an injunction in each and every case. 

Issue no.2 therefore stands decided against the plaintiff.

Issue no.3 was whether the plaintiff is entitled for a decree of mandatory injunction   thereby   directing   the   defendant   to   restore   the   electricity connection and withdraw the false electricity bill dated 11.01.2000.

The plaintiff has been able to discharge the burden of proof cast upon him. In view of the foregoing discussion,  this issue stands decided in favour of the plaintiff.

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 30 of 33

Issue no. 2B 2B. Whether suit of plaintiff is barred by limitation? OPD

48. The onus to prove this issue was on the defendant. The plaintiff has filed the present suit for perpetual and mandatory injunction. In the month of January 2010, plaintiff moved an application for amendment of the plaint. In para no. 8 of plaint, the amendment has been done that the plaintiff has deposited the theft bill 'under protest' (though, no evidence has been filed to show how was it made 'under  protest'). The prayer clause 1 was also amended and for the first time the plaintiff claimed the refund of the amount already deposited, that is,  Rs.1,12,287.98/­ After the above stated amendments subsequently, following issue were framed by this Court:

"2A. Whether plaintiff is entitled to the refund of deposited amount of Rs.1,12,287/­? OPP 2B Whether suit of plaintiff is barred by limitation? OPD"

49.  It has been argued by the Ld. counsel for the defendant that the plaintiff has voluntarily, without any force or pressure deposited the theft amount on 15.01.2000. The plaintiff in the year 2013, for the first time, asked for the refund of the said amount by preferring an amendment in the   plaint   in   the   above   stated   suit   for   perpetual   and   mandatory injunction. It is argued that the plaintiff cannot ask for refund of money Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 31 of 33

at this belated stage. As per the provision of Limitation Act, the refund can be sought within three years from the date of cause of action and in this   matter,   as   per   the   plaintiff   the   alleged   cause   of   action   arose   on 10.01.2000. It has been argued by the Ld. Counsel for the plaintiff that the plaintiff has voluntarily and without any pressure or force deposited the theft amount on 15.01.2000, such that no criminal/civil liability shall be incurred on the plaintiff. 

50. Section 3 of the Limitation Act provides  inter­alia  that if the suit is instituted after the prescribed period of limitation, the suit   shall be dismissed.   Section   2(j)   of   the   Limitation   Act defines   prescribed period  as  the  period  computed  in accordance  with  the  provisions  of the   Limitation   Act. To put it differently, successive violation of the right will not give rise to fresh cause and the suit will be liable to be dismissed if it is beyond the period of limitation counted from the day when the right to sue first accrued. 

It is the contention of the plaintiff that the amount was deposited under protest on 15.01.2000. The present case was filed on 13.01.2000. Therefore,   it   is   held   that   the   suit   was   filed   within   the   prescribed limitation period. The necessary corollary of even the earlier suit would be that the plaintiff shall be entitled to refund of amount if the bill was found to be illegal. This issue is therefore decided against the defendant. The fact that the plaintiff had deposited the theft amount cannot be taken against him. 

Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   

Suit No.598159/16             Page 32 of 33

Issue No. 2A Whether plaintiff is entitled to the refund of deposited amount of Rs.1,12,287/? OPP The onus to prove this issue was on the plaintiff. In view of my findings on issue no. 1, 2 and 3 it is held that the plaintiff has discharged the burden of proof cast upon him successfully. It appears reasonable that the amount deposited by the plaintiff shall be refunded. The plaintiff is held entitled to refund of amount of Rs.1,12,287/­ alongwith interest @ 6% per annum from 15.01.2000 till the date of decree.  Relief

51. In view of the foregoing discussion the suit filed the plaintiff is decreed. The defendant is permanently restrained from realising the dues of the impugned bill. The defendant is directed to refund the amount of Rs.1,12,287/­   alongwith   interest   @   8%   per   annum   from   15.01.2000 within 8 weeks from today. Any delay beyond this period will attract a higher rate of interest @ 18% per annum. The defendant is directed to give plaintiff an opportunity to be heard and then take a decision on the matter in accordance with law before proceeding further to raise any bill.

No order as to cost Decree sheet be prepared accordingly.

File be consigned to record room after due completion.

Announced in the open                                                             (Himanshu Raman Singh)
court today on 05.11.2016                                                 Civil Judge­1, Central District,
                                                                                      Tis Hazari Courts, Delhi
Hem Chand Gupta vs BSES Rajdhani Power Ltd.                                                                                                   
Suit No.598159/16                                                                                                      Page 33 of 33