Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

Delhi District Court

M/S Curo India Pvt Ltd vs M/S Shri Ji Project P. Ltd on 4 February, 2017

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd



 IN THE COURT OF SH. AJAY PANDEY, ADDL. DISTRICT JUDGE­05,
  ROOM NO. 605, SOUTH DISTRICT, SAKET COURTS, NEW DELHI

In the matter of
ARB No. 20781/2016
Case ID No. DLST01­004825­2016

M/s. Curo India Pvt Ltd.
Through its Authorized Representative
Mr. R.K.Arora
K­28, Green Park Extension
New Delhi­110019
                                                                       .............Petitioner
                                      Versus

M/s Shri Ji Projects
30/2, Street No. 10,
Vishwas Nagar, Shahdra
Delhi­110032                                                           ..............Respondent

         Date of Institution                                    :      15.09.2015
         Date of reserving the Judgment                         :      25.01.2017
         Date of pronouncement                                  :      04.02.2017
         Decision                                               :      Award Set aside

       PETITION UNDER SECTION 34 OF THE ARBITRATION AND
      CONCILIATION ACT, 1996 FOR SETTING ASIDE THE AWARD
                        DATED:26.06.2015

JUDGMENT

1.   This   is   a   petition   u/s   34   of   the   Arbitration   and Conciliation Act, 1996 filed against the Award dated 26.06.2015 passed by Learned Sole Arbitrator. 

 

2.   Matter was fixed for pronouncement of judgment on ARB No.173/15 Page 1 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd 07.02.2017.   In   view   of   the   receipt   of   the   transfer   order   no. 02/DHC/Gaz/G­1/VI.E2(a)/2017 dated 01.02.2017 from Hon'ble High   Court   of   Delhi   and   in   compliance   of   para   2   of   the   Notes mentioned   therein,   the   date   of   pronouncement   of   judgment   is preponed to 04.02.2017.

3.   For   the   sake   of   convenience,   parties   are   referred according to their ranks in the arbitration proceedings before the learned arbitrator. 

 

4.   Brief facts necessary for disposal of the  petition are that the claimant who is the respondent herein, filed statement of claim before the learned sole arbitrator stating interalia that the claimant is the registered contractor. He entered into a contract with   the   respondent   for   the   construction   of   multiplex   blocks through the Letter of Intent (LOI) issued on 17.02.2012. Contract was illegally foreclosed by the respondent on 31.01.2013. On the foreclosure of the contract huge amount of scaffolding materials, belonging to claimant were left at site. Respondent did not return that   material.   Claimant   was   pursuing   with   the   respondent   for settlement   of   accounts   and   sent   a   letter   dated   30.04.2013. Claimant   also   submitted   final   bill   for   an   amount   of   Rs 8238205.95/­. An amount of Rs 3747105/­ was claimed for non scheduled   items   also,   which   included   the   idle   cost   of   labour materials, hire charges of shuttering and scaffolding material, RCC work,   extra   height   for   shuttering   etc.   Respondent   verified   an ARB No.173/15 Page 2 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd amount of Rs 207682/­ only for the first three items. The cost of shuttering   material   retained   and   used   by   the   respondent   is   Rs 650000/­. The respondent did not even clear the running account bills submitted by the claimant on 07.01.2013. 

  

5.   These   actions   of   the   respondent   are   stated   to   be illegal and uncontractual. The claimant is stated to be entitled for loss of profit of 15 % of the contractual value due to illegal closure of the contract. It is stated that respondent released an amount of Rs 5752118/­ only to the claimant whereas the balance payment of Rs 15042910/­ plus interest @ 15% per annum was still due from the respondent.

 

6.   It   was   further   stated   that   certain   disputes   arose between the parties. Claimant invoked the provisions of clause 39 of LOI for appointment of Arbitrator. Ultimately, Hon'ble Justice (Retd.) V.S.Agarwal was appointed as the Sole Arbitrator.

 

7.   Claimant had the following claims before the learned Sole Arbitrator:­

1.  Claim no. 1:­ Claimant's claim towards payment of Final Bill­ Rs   6990791/­   :­   It   was   alleged   that   work   was   illegally foreclosed w.e.f. 30.01.2013 with directions to raise full and final   bill.   Claimant   in   his   letter   dated   30.04.2013   submitted final bill. Final bill was duly verified for total value of work ARB No.173/15 Page 3 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd done for Rs 8095805.35/­ as against the bill for Rs 8238205/­. As against non schedule items of Rs 3747103.95 an amount of RS   207682/­   only   was   verified   by   respondent.   Respondent released   total   amount   of   Rs   5752119/­   thus   the   balance amount   of   Rs   6090791/­   was   stated   to   be   payable   by   the respondent. It appears that by mistake in the title of claim no. 1, this amount was mentioned as Rs 6990791/­ instead of Rs 6090791/­.

2. Claim no. 2:­ Claim towards loss of profit due to alleged illegal foreclosure of contract @ 15% of the contact value amounting to Rs 25,50,000/­  

3.  Claim no. 3:­ Interest @ 18% p.a. for the delayed payment of running bills and final bill.

 

4.  Claim no. 4:­  Contractors claim towards cost of proceedings Rs 200000/­   

8.   Respondent filed their written statement cum counter claim   thereby   denying   their   liability   and   claiming   following amount from the claimant:­  S. Particulars Amount No. A. Loss of rent @ Rs 1280000/­ per month Rs ARB No.173/15 Page 4 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd for a period of 14 months 13 days w.e.f 18456774/­ 01.07.2017 till 13.10.2014  B. Penalty   for   delay   @   5%   of   the   contract Rs 1129609/­ value  C. Sub Total Rs 19586383/­ D. Amount payable to claimant as per para Rs 960883/­ 22 and 23 above E. Sub Total Rs 18625500/­ F. Litigation   expenses   for   the   current Rs 200000/­ litigation G. Grand Total E+F Rs 18825500/­

9.   Claimant   filed   rejoinder/reply   to   the   written statement/counter claim of the respondent.

 

10.  Learned   Arbitrator   framed   following   issues   on 07.10.2014:­ ISSUES:­ 

1. Whether the claimant is entitled to Rs 6990791/­ towards the payment of the final bill? 

2. Whether   the   claimant   is   entitled   to   loss   of   profits   due   to   the alleged closure of the contract, if so, how much?

3. Whether the claimant is entitled to interest @ 18% p.a. for the delayed payments of the running bills and the final bill?

ARB No.173/15 Page 5 of 15

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd

4. Whether the respondent is entitled to any amount for loss of rent, penalty for alleged delay and other amounts stated in para 29 of the counter claim. If so, how much?

5. Whether   the   respondent   is   entitled   to   claim   the   damages mentioned in para 30 of the counter claim. If so, how much?

6. Whether the respondent is entitled to any interest. If so, at what rate?

7. Relief.

11.  Issue no. 4, 5 and 6 relate to the counter claim of the respondent. They were taken together for decision by learned sole arbitrator.

 

12.  All these issues were decided against the respondent.

 

13.  Issue no.1 was partly decided in favour of claimant and claimant was held entitled to Rs 3747103.95/­ for providing non scheduled items to the respondent. In addition thereto, the claimant was further held entitled to Rs 1515603/­ for recovery of the cost of scheduled work as well as refund of security amount of Rs 408482/­.

 

14.  During the course of arguments learned Sh. Somesh Arora, advocate for petitioner who is respondent in the  arbitral proceedings, submitted that the award is being challenged by him on three counts. 

ARB No.173/15 Page 6 of 15

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd

15.  Firstly, because the learned arbitrator did not decide issue  no. 4 though he held that the  delay in  completion  of the contract   was   attributed   to   the   claimant.   Secondly,   learned   sole arbitrator, against the contract of the parties, ignored the admitted document i.e. R­23 which was exhibited as RW1/34. Thirdly, the learned arbitrator considered the claim for non scheduled items on   the   basis   of   statement   of   facts   submitted   by   the   claimant without the same being proved on record and ignoring the final settlement/bill   arrived   at   between   the   parties   as   well   as contractual   obligations   under   the   Letter   of   Intent   dated 17.02.2012.

 

16.  Learned   Sh.   Rajappan   has   submitted   that   the objection   petition   is   liable   to   be   dismissed   as   no   ground   for interference   in   the   award   is   made   out   from   the   facts   and circumstances of the case.

 

17.  Learned   Sh.   Rajappan   while   placing   reliance   on "Shree Krishna Woolen Mills (P) Ltd vs Union of India 7 Anr" 2008 (3) Arb. LR 477 (Delhi) submitted that the scope of interference by court in the award passed by the learned arbitrator is very limited. He submits that the court cannot sit in appeal against the award passed by the learned arbitrator and the petitioner must satisfy that   either   of   the   grounds   mentioned   under   section   34   (2)   of Arbitration   and   Conciliation   Act,   1996   is   made   out   from   his ARB No.173/15 Page 7 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd petition. Learned Sh. Rajappan submits that no ground for setting aside of the award is made out from the petition.

 

18.  In   reply   to   the   submissions   of   the   learned   Sh.

Rajappan, learned Sh. Somesh has submitted that the award is in contravention with the fundamental policy of the Indian Law as the contract between the parties was ignored while passing the award. He also submits that non deciding the issue framed in the matter  was also against the basic notions of justice. 

 

19.  Court has considered the arguments advance by the learned counsels for parties.

 

20.  While holding the claimant entitled for recovery of Rs 3747103.95/­, learned arbitrator appears to have relied upon the summary   sheet   -   final   bill   which   was   enclosed   with   the   letter dated 30.04.2013 sent by the claimant. Total amount of summary sheet/final bill is Rs 11985309.88/­. Two heads are included in the said amount are as follows:­    A Value of Work Done This   Bill Cumulative Amount in Rs Bill   Amount in Rs (A1)   Work   Done 8238205.95 8238205.95 Scheduled Items (A2)   Work   Done   Non 3747103.93 3747103.93 Scheduled Items ARB No.173/15 Page 8 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd Total 11985309.88 11985309.8 (A= A1 8 +A2_  

21.  Learned Sh. Somesh has drawn the attention of the court to clause 40 of the Letter of Intent executed between the parties which provides as follows:­    "40. Payment Terms: - R/A bill shall   be   submitted   every   month   after   joint measurements   taken   alongwith   Company's Authorized   representative   at   site.   Payment shall   be   made   after   joint   measurement, verification and checking of bills."  

 

22.  In   page   six   of   the   award,   learned   arbitrator   has produced the following statement of account between the parties as per the respondent:­ S. No. Particulars Amounts (Rs) A. Total amount payable to claimant 8169836/­ B. Amount already paid by respondent to 5752198/­ the claimant by cheques and RTGS C. Amounts paid by TDS 163398 respondent   on WCT 408491 behalf   of Service Tax 202611 claimant Cess 81640 Labour Payment 134080 Electricity Bill 45895 D. Security   deposit   deducted   by   claimant 408492 in terms of LOI ARB No.173/15 Page 9 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd E. Total amount paid (B+C+D) 7196805 F. Amount payable to claimant (A­E) 973031  

23.  While deciding issue no. 1 learned arbitrator held that the final bill, annexure R­23 which is also exhibited RW 1/34 was jointly   verified.   The   said   document   was   the   final   bill   dated 13.04.2012   raised   by   the   claimant,   which   was   issued   by   the claimant and the dues therein were duly verified by the parties. The   said   document   bears   the   signature   of   the   partner   of   the claimant on 06.09.2013 encircling the amount of Rs 8169835.87/­ jointly verified by the parties. In the said bill also two heads are included which are as follows:­ A Value   of   Work This   Bill Cumulative Done Amount in Rs bill   amount in Rs (A1)   Work   Done 8087955.35 8087955.35 Scheduled Items (A2)   Work   Done 81880.52 81880.52 Non   Scheduled Items Total 8213325.55 8213325.55 (A= A1 + A2) Gross 8169835.07 8169835.07 Total  

24.  Learned counsels for both the parties admit that on 06.09.2013, this amount of Rs 8169835.07 was jointly verified as against this bill. 

ARB No.173/15 Page 10 of 15

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd  

25.  Counsel for the claimant however submitted that this amount do not include the total cost of non scheduled items. He submits that the award of Rs 3747103.95/­ allowed by the learned arbitrator on this account was justified.

 

26.  It is rightly submitted by learned Sh. Somesh that the learned arbitrator ignored the admitted document Ex. RW 1/34 which contain the value of work done for scheduled items as well as   work   done   for   non   scheduled   items.   It   is   further   rightly submitted   by   him   that   the   reliance   on   the   documents   dated 30.01.2013 which was jointly verified by the parties was against clause 40 of the LOI. At page 15 of the award, learned arbitrator observed:

  "The   other   dispute   is   with regard   to   the   non   schedule   items.   Ex.   RW 1/34 is a summary but the claimant alleged that does not refer to all non schedule items. The   plea   of   the   claimant   deserves   to   be accepted.   It   is   obvious   that   non   schedule items  were many  and Ex  RW  1/34  cannot deal with them all.
  One   would   have   gone   by   the said   document   but   this   is   a   verification which is insignificant as stated above. In the affidavit Ex AW 1/A pertaining to the non schedule   item   the   claimant   has   lead   the following evidence"
 

27.     It is rightly submitted by learned Sh. Somesh that the ARB No.173/15 Page 11 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd observation of the learned arbitrator that non schedule items were many and Ex RW1/34 cannot deal with them all is not brought out from the record. There is nothing in the arbitral record which could suggest that RW1/34 could not deal with the non scheduled items. After the aforesaid observation the learned arbitrator has narrated the description  of non scheduled items from " i to ix"

alongwith   the   respective   cost.   It   is   seen   that   Ex   RW   1/34   also contains   the   description   of   all   these   non   schedule   items.   An amount   of   Rs   51129.52/­   was   verified   between   the   parties   as against non scheduled items no. (i), an amount of Rs 3571/­ was also verified on account of item no. (iii). Both these amounts were included in the verified liability of Rs 8169835.87/­ under exhibit RW 1/34. Thus, RW1/34 infact dealt with all non scheduled items narrated   by   the   learned   arbitrator   in   his   award.   Hence,   the observation   that   Ex.   RW1/34   cannot   deal   with   non   scheduled items was contrary to the record. 
 

28.  Learned Sh. Somesh has further rightly submitted that when under the contract i.e. LOI   dated 17.02.2012 between the parties,   the   payment   was   required   to   be   made   after   joint measurement,   verification   and   checking   of   bills,   the   learned arbitrator cannot have observed that :­   "One   would   have   gone   by the   said   document   but   this   is   a verification   which   is   insignificant   as stated above."

   ARB No.173/15 Page 12 of 15

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd

29.  It   is   important   to   mention   here   that   the   joint verification of the final bill Ex RW 1/34 was done by the parties on 06.09.2014, whereas the learned arbitrator has relied upon the non verified bill dated 30.04.2013 for grant of the claim for non scheduled items. 

 

30.  It   is   therefore   rightly   submitted   by   learned   Sh.

Somesh   that   the   award   is   against   the   contractual   obligation between   the   parties   and   therefore   is   in   contravention   with   the fundamental policy of Indian law.

 

31.  Submissions   of   learned   Sh.   Somesh   that   complete findings qua issue no. 4 were not given by the learned arbitrator are also found correct. 

 

32.  Item B of the table A is related to the penalty for the alleged delay in the performance of contract. While deciding issue no. 2 learned arbitrator held that it was the claimant who was delaying the work and therefore he disallowed the claim for loss of profits allegedly suffered by claimant due to foreclosure of the contract. Despite the observation that claimant delayed the work, he   did   not   give   any   findings   qua   the   entitlement   or   non entitlement of the amount claimed for delay in execution of work in the counter claim.

 

33.  Hence, the award appears to be in conflict with the ARB No.173/15 Page 13 of 15 M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd basic   notions   of   justice.   If   an   issue   was   framed   the   same   was required   to   be   decided   or   some   observation   for   non   decision thereof was required to be given.

 

34.  It is rightly submitted by learned Sh. Rajappan that court cannot sit in appeal over the award and cannot impose its own findings or the observation over the observation/findings of the   learned   Arbitrator.   But   the   award   herein   reflects   glaring contravention   with   the   fundamental   policy   of   Indian   law   and appears to be in conflict with the basic notions of justice.

 

35.  Learned   Arbitrator   has   ignored   the   admitted document   existing   on   record   as   per   the   contract   between   the parties   and   has   considered   extraneous   material   which   was   not verified as per the contract between them. 

 

36.  Award is therefore liable to be set aside.

 

37.  Held accordingly.

 

38.  Petition   under   section   34   of   Arbitration   and Conciliation Act 1996 for  setting aside the impugned award dated 26.06.2015 passed by the learned sole arbitrator is allowed.

 

39.  Award dated 26.06.2015 is hereby set aside.

  ARB No.173/15 Page 14 of 15

M/s Curo India Pvt Ltd vs M/s Shri Ji Project P. Ltd

40.  Arbitral Record be sent back.

 

41.  File be consigned to record room.

Announced in the open                                    (AJAY PANDEY)
Court on 04.02.2017                             ADJ­05 (SOUTH DISTRICT)
(Judgment contains 13 pages)                   SAKET COURTS, NEW DELHI




ARB No.173/15                                                    Page 15 of 15