[Cites 0, Cited by 0]
[Entire Act]
Union of India - Section
Section 28 in The Central Electricity Regulatory Commission (Terms And Conditions For Tariff Determination From Renewable Energy Sources) Regulations, 2009
28. Capital Cost
.-(1) The normative capital cost for small hydro projects during first year of Control Period (FY 2009-10) shall be as follows:-| Region | Project Size | Capital Cost(Rs Lakh/MW) |
| Himanchal Pradesh, Uttarkhand and North Eastern States | Below 5 MW5 MW to 25 MW | 700630 |
| Other States | Below 5 MW5 MW to 25 MW | 550500 |