Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 2]

Delhi High Court

Sh.Bali Ram vs Municipal Corporation Of Delhi on 13 April, 2009

Author: G.S. Sistani

Bench: G.S.Sistani

*              IN THE HIGH COURT OF DELHI AT NEW DELHI
[1]                        WP(C)No.9669/2007

                              Judgments delivered on April 13th, 2009


# SH. BALI RAM                               ....       Petitioner
                           Through     : Ms. Anusuya Salwan, Adv.


                     Versus


$ MUNICIPAL CORPORATION OF DELHI    ....         Respondent
^                   Through   : Mr. Amit K. Paul, Adv.


[2]                        WP(C)No.9287/2007


# SH. BALI RAM                               ....       Petitioner
                           Through     : Ms. Anusuya Salwan, Adv.


                     Versus


$ MUNICIPAL CORPORATION OF DELHI    ....         Respondent
^                   Through   : Mr. Amit K. Paul, Adv.


CORAM:

         HON'BLE MR. JUSTICE G.S.SISTANI

         1. Whether reporters of local papers may be allowed to see
            the judgment?                               Yes
         2. To be referred to the Reporter or not?      Yes
         3. Whether the judgment should be reported in the
            Digest?                                     Yes


G.S. SISTANI, J:

    1.

    2. Learned counsel for the parties submit that both the writ

         petitions are identical in nature, the parties in both the

         petitions are same and the pleadings and annexures are also

         identical, except the work order is different. Hence both the
         WP(C)No.9669/2007 & WP(C)No.9287/2007              Page 1 of 18
    abovesaid petitions are being disposed of by a common

   judgment.

3. In the writ petition [WP(C)No.9669/2007] the petitioner was

   awarded work of Development of U/R Colony SH: Construction

   of drain and providing RMC from Arya Samaj Mandir to out fall

   drain and from Rza 34/233 to RZJ-43 in West Sagarpur in W

   No.52/NGZ.        The estimated cost of work was Rs.49.75 lakhs

   and the time for completion of work was eight months.

4. In   the   writ    petition   [WP(C)No.9287/2007   petitioner    was

   awarded     a     work   of   Development   of   U/R   Colony     SH:

   Construction of drain and providing RMC from WZ 404 Gali

   No.4A, near Ram Chowk to Pradhan Chowk and from Tanwar

   House Gali No.16 to Sanchan Medical Store in Sadh Nagar in

   Work Order No.387/NGZ.           The estimated cost of work was

   Rs.49,42,700/- and the time for completion of work was eight

   months.

5. It is contended by counsel for the petitioner that immediately

   after awarding of work, the petitioner mobilized his resources

   to execute the work but it was found that though the work was

   awarded with respect to construction of a drain but actually

   the work which was sought to be executed pertained to work

   of sewerage system.           Hence, the work was not within the

   scope of work awarded and the petitioner immediately brought

   it to the notice of the respondent vide letter dated 30.05.2007.

   The petitioner kept on representing to the respondent and

   after persistent efforts the Superintending Engineer, Nazafgarh

   Zone, agreed to have a meeting in the office wherein the

  WP(C)No.9669/2007 & WP(C)No.9287/2007                    Page 2 of 18
 representative of the petitioner was present and it was agreed

by the respondent that since the scope of the work was totally

different, extra items would be sanctioned and the same would

be got approved by the executive engineer and also his

running bills would be passed. Learned counsel contends that

despite having given an assurance that extra items would be

sanctioned, nothing was done and this fact was brought to the

notice of the respondent vide letter dated 29.10.2007.        It is

also contended that no work could be carried out at the site on

account of various reasons which were brought to the notice of

the respondents.     Vide letter dated 30.05.2007 petitioner

brought it to the notice of the respondent that the site was

also not available as the width of the road was from 12 feet to

18 feet and even lesser in places and in the said site two

sewer lines and two water lines were in running position

because of which there was no scope for excavation and

hence RCC pipes could not be laid unless the running sewer or

water pipes were removed. It was also brought to the notice

of the respondent that this was not within the scope of the

work and further that the width of the road was so narrow that

the material could not be stacked. These facts were brought

to the notice of the respondents vide letter dated 29.10.2007

and 13.11.2007. While no action was taken pursuant to the

letters of the petitioner, the petitioner received a letter dated

06.11.2007 informing the petitioner that the above mentioned

contract work have been closed and his earnest money have

been forfeited and action would be taken against him for not

WP(C)No.9669/2007 & WP(C)No.9287/2007                Page 3 of 18
   following instructions for enlistment of contracts in the MCD.

  Petitioner claims to have replied to the aforesaid letter vide

  letter dated 14.11.2007 bringing it to the notice of the

  respondent that there has been no delay on his part and it is

  the respondent who had committed breach of contract.

  Various other reasons were also brought to the notice of the

  respondent including non-availability of approval of designs

  and   drawings.       The   petitioner   thereafter   received    the

  impugned circular dated 26.11.2007 blacklisting the petitioner,

  which led to the filing of the present petitions.

6. Learned counsel for the petitioner submits that the circular

  dated 26.11.2007 is bad in law and is liable to be set aside as

  the petitioner was not given any show cause notice before

  passing the impugned circular blacklisting the petitioner. It is

  contended that the petitioner was informed by the Executive

  Engineer that action would be taken against him under the

  Enlistment Rules, but no show cause notice has been given.

  Moreover, the Additional Commissioner (Engineering) passed

  the impugned order without giving any opportunity to the

  petitioner to show cause and give a personal hearing.            The

  respondents, as per the petitioner, have failed to comply with

  the principles of natural justice and the petitioner has been

  debarred and thus his right of livelihood has been taken away

  by a cryptic and an unreasoned order. Learned counsel for the

  petitioner also contends that the only action that could have

  been taken was under Rule 22 of the Enlistment Rules.            Rule

  22 reads as under:-

  WP(C)No.9669/2007 & WP(C)No.9287/2007                   Page 4 of 18
               "22   Disciplinary Actions

                    The contractor shall have to abide by all the
                    rules of enlistment and also by the terms
                    and conditions of the contract and the Notice
                    inviting tenders. He shall have to execute
                    the works satisfactorily, on time and with
                    good quality. The enlisting authority shall
                    have the right to a lower class, suspend
                    business with him for any period, debar him
                    or remove his name from the approved list
                    of contractors after issue of show cause
                    notice. Decision of the department shall be
                    final and binding on the contractor. The
                    following actions of the contractor shall, in
                    general, make him liable to disciplinary
                    actions."

                                            [Emphasis supplied]



7. Mr.Amit K. Paul, learned counsel for the respondent - MCD has

  opposed these petitions on two grounds: firstly the petitioner

  has not approached this court with clean hands and has

  suppressed and withheld material facts and communications

  and thus the petitioner is not entitled to invoke the extra

  ordinary jurisdiction of this Court and secondly respondents

  have complied with the principles of natural justice and have

  issued show cause notice to the petitioner, granted personal

  hearing and thereafter passed the impugned order. Learned

  counsel further submits that even on merits the petitioner did

  not comply with the terms of the work order and thus the

  impugned orders were passed. Counsel for the MCD relies on

  paras 3 to 6 of the counter affidavit, which are reproduced

  below:


              "3. It is respectfully submitted that the instant
              petition is not maintainable as it is devoid of any
              justiciable cause of action or legally enforceable
              rights in favour of the petitioner. Neither is the
  WP(C)No.9669/2007 & WP(C)No.9287/2007              Page 5 of 18
             instant case one where the respondent has failed
            to discharge a statutory obligation or acted
            contrary to the statute or procedure prescribed
            therein. The petitioner has in fact misrepresented
            and concealed vital facts from this Hon‟ble Court
            and is attempting to abuse the process of this
            Court to secure his vested interests.

            4.     The main grievance of the petitioner is that
            he has been debarred from further tendering with
            the MCD for a period of 5 years vide circular dated
            26.11.07 without following the principles of natural
            justice in as much as neither was any show cause
            opportunity given to him and nor was any personal
            hearing granted to him before passing the said
            order. On the contrary it is submitted that a show
            cause notice as well as personal hearing was given
            to the petitioner and only thereafter the impugned
            order was passed in accordance with the rules of
            enlistment of the contractors.

            5.     The petitioner was awarded the work of
            Development of unauthorized regularized colony,
            Sub-Head construction of drain and providing
            Ready Mix Concrete from WZ 404 Gali No.4A, Near
            Ram Chowk to Pradhan Chowk and from Tanwar
            House, Gali No.16 to Sanchan Medical Store in
            Sadh Nagar, in ward no.52 in Najafgarh Zone vide
            work order no.EE/VI/Plan /TC/06-07/387 dated
            15.03.2007. It is respectfully submitted that the
            petitioner has failed to perform any work
            whatsoever awarded to him under the subject
            contract. It is submitted that work order on the
            petitioner had been placed on 15.3.2007 and the
            contract agreement was entered into on
            20.3.2007.     Needless to say, at the time of
            tendering and even at the time of accepting the
            work order and signing the work contract, the
            applicant was deemed to have inspected the work
            site and/or satisfied himself as to the nature of the
            work to be performed and therefore all grievances
            /disputes raised by the petitioner in this regard
            subsequently are devoid of merit.

            6.     That even though the work order had been
            placed on the petitioner on 15.03.2007 the
            petitioner did not commence any work pursuant to
            the same citing one reason or the other. Since the
            awarded work was to be completed within a period
            of eight months i.e. by 23.11.2007, the
            respondents     vide  letter   dated   03.10.2007
            requested the petitioner to commence the work
            immediately.     Subsequently, vide letter dated
            09.10.2007 the petitioner was given notice to
WP(C)No.9669/2007 & WP(C)No.9287/2007                Page 6 of 18
               show cause as to why action under clause of the
              agreement be not taken against him as he was
              liable to pay compensation on account of not
              starting the work.       The petitioner was further
              directed to show cause within a week‟s time as to
              why action for suspension of business from
              debarring from tendering in the M.C.D./Black
              listing of the firm for not executing the work as per
              the rules of enlistment be not taken. It was again
              brought to the notice of the petitioner vide letter
              dated 10.10.2007 that the work awarded was of
              urgent nature for providing drainage system and
              improvement of roads and since it had not yet
              been started, the residents in the area were facing
              great difficulty. However, before taking any action
              in the interest of natural justice, the petitioner was
              granted an opportunity to explain his position with
              regard to the non-commencement/non-completion
              of the awarded work.

              7.     That before taking any further disciplinary
              action against the petitioner a personal hearing
              was given to him by the Superintending Engineer,
              Najafgarh Zone on 15.10.2007 during the course
              of which the petitioner acknowledged that he was
              yet to start the contracted work and further
              promised to commence and complete the same at
              the earliest. However, despite this commitment,
              the petitioner failed to commence the contracted
              work because of which the respondent were
              constrained to send him another letter dated
              06.11.2007 informing him that his work order "had
              been closed" and earnest money of Rs.72,500/-
              deposited at the time of tendering had been
              forfeited and that his case was being processed for
              further disciplinary action. Only thereafter as per
              the enlistment rules circular dated 26.11.2007 was
              issued by the Administrative Officer, Engineering
              Department (HQ)."



8. I have heard learned counsel for the parties, who have taken

  me through the petitions as well as annexures filed along with

  the writ petition and reply thereto.     No rejoinder has been

  filed. Petition [WP(C)No.9287/2007] was filed earlier in time.

  On the first date of hearing, when the matter came up for

  hearing, the following order was passed on 17.12.2007:


  WP(C)No.9669/2007 & WP(C)No.9287/2007                 Page 7 of 18
               "WP(C)9287/2007
                    Issue notice to show cause to the respondent
              as to why rule nisi be not issued.

                    Mr.Amit S.Paul, Adv. accepts notice and
              prays for time to file counter affidavit. Let the
              same be filed within four weeks.         Rejoinder
              thereto, if any, may be filed before the next date
              of hearing.

                     List on 14th May, 2008.
              CM.17518/2007
                     Notice.
                     Mr.Amit S.Paul, Adv. accepts notice and
              prays for time to file reply. Let the same be filed
              within four weeks. Rejoinder thereto, if any, may
              be filed before the next date of hearing.
                     List on 14th May, 2008.
                     Having regard to the grievance of the
              petitioner that he has been debarred from
              contracting with the MCD without issuing of notice
              to show cause, there shall be a stay of the order
              dated 26th November, 2007, till the next date of
              hearing."

9. Subsequently   petition   [WP(C)No.9669/2007]      was     filed.

  Relying upon the earlier order, show cause notice was issued

  and the following order was passed on 2.1.2008:


              "WP(C)9669/2007 & CM.18235/2007
                    Learned counsel for the parties state that in
              an another writ petition WP(C)No.9287/2007,
              notice has been issued and operation of the
              circular dated 26th November, 2007 relating to the
              work order No.EE-VI/Plan/TC/06-07/387 has been
              stayed.
                    In these circumstances, issue notice to the
              respondent /MCD to show cause as to why rule nisi
              be not issued.
                    Mr.Amit K. Paul, Adv. accepts notice on
              behalf of the Municipal Corporation of Delhi.
              Counter affidavit shall be filed within three weeks.
              Rejoinder, if any, will be filed within two weeks
              thereafter.
                    In the meantime, operation of the impugned
              Circular dated 26th November, 2007 is stayed.
              However, it is clarified that it will be open to the
              respondent/ MCD to issue show cause notice and
              pass appropriate orders in terms of instructions for
              enlistment of Contractors in MCD including Clause
              22."
  WP(C)No.9669/2007 & WP(C)No.9287/2007               Page 8 of 18
 10.     This court while issuing notice to show cause had

  considered the submissions of counsel for the petitioner that

  MCD without issuing show cause notice had debarred the

  petitioner.    On this submission, stay of the order dated

  26.11.2007 was passed. Even in the body of the writ petition

  it has been stated that after the award of the work, the

  petitioner mobilized his resources, but found that the work

  awarded was with respect to the construction of drain

  however, the work which was sought to be executed pertained

  to sewerage system which was brought to the notice of the

  respondent vide letter dated 30.5.2007 (identical in both the

  matters).     Thereafter, petitioner is stated to have met the

  Superintendent Engineer, Najafgarh Zone on 15.10.2007.

  Perusal of the counter affidavit of respondent would show that

  this meeting of 15.10.2007 was held in fact pursuant to a

  communication dated 10.10.2007.           As per the respondent,

  after the work having been awarded to the petitioner, the

  latter did not commence the work, forcing the respondent to

  issue a communication dated 3.10.2007 which is reproduced

  below:

                "No. D/ 499/EEVI/2007           Dated 3.10.2007
                M/s.Dagar & Co.
                Mpl. Contractor,

                Sub:   Dev. of U/R. Cly. S/H: C/o. drain & [pdg. RMC
                       from Arya Samaj Mandir to outfall drain and from
                       RZA 34/233 to RZ-343 in West Sagarpur NGZ


                      The above cited work has been awarded to you
                vide Work Order No.EEVI/Plan /TC/06-07/388 dated
                15.3.07 with a completion period of 8 months. The
                work has not been started by you so far even after
                verbal pursuations. The non-taking up of the work may
  WP(C)No.9669/2007 & WP(C)No.9287/2007                    Page 9 of 18
                 result in inordinate delay in completion of the project
                and inconvenience to the residents. You are, therefore,
                directed to start the work without further loss of time
                failing which action under the relevant clauses of the
                agreement will be started against you & explain the
                reasons for non starting the work so far within three
                days of the receipt of this letter.

                                                       Yours faithfully,

                                                                   Sd/-
                                                      Asstt. Engineer-II

                Copy to: 1. SE (NGZ) for information pls.
                         2. EE VI for information pls."


11. After issuing of this letter dated 3.10.2007, another letter

    dated 9.10.2007 was issued wherein it was pointed out that

    the stipulated date of completion was 23.11.2007. Despite six

    months having already been elapsed, the work has not

    commenced till date.     Petitioner was also directed to show

    cause within one week as to why action for suspension of

    business with his firm and further tendering the firm in the

    black list, be not taken by the MCD.          Petitioner was also

    cautioned that if no reply is received within the specified

    period, it would be presumed that you have nothing to say.

    Communication dated 9.10.2007 is reproduced below:


                "No. D/ 525/EEVI/2007            Dated 9.10.2007

                M/s.Dagar & Co.
                Mpl. Constractor,
                Village & Post Office Issapur,
                New Delhi -110 073

                Sub: Development of unauthorized colony S.H.:
                C/o. drain & pdg. RMC from WZ 404 Gali No.4A,
                near Ram Chowk to Pradhan Chowk and from
                Tanwar House Gali No.16 to Sanchan Medical Store
                in Sadh Nagar

                Dear Sirs,


    WP(C)No.9669/2007 & WP(C)No.9287/2007                   Page 10 of 18
                    The above said work was awarded to you
            vide W.O. NO.EEVI/Plan/ TC/06-07/387 dated
            15.3.2007 with a completion period of 8 months.
            The stipulated date of completion of this as per
            agreement is 23.11.2007. Time of more than 6
            months have already been elapsed, but you have
            not started the work even after personal
            pursuations as well as in writing vide letter
            No.D/498/EEVI dated 3.10.2007. This work is of
            urgent nature for providing drainage system and
            improvement of road by providing ready mix
            concrete, but you have not started the work due to
            which area residents are facing great difficulties.
            It is, therefore, directed to start the work
            immediately and complete with full swing. Your
            non-taking up of work so far rendered yourself
            liable to pay compensation under clause 2 of the
            aforesaid agreement.

                   In exercise of powers conferred on me under
            clause 2 of the agreement I, Ravinder Singh,
            Executive Engineer (VI) hereby give you notice to
            show cause within a week‟s time to my satisfaction
            as to why action under clause 2 of the agreement
            be not taken against you as are liable to pay
            compensation on account of not starting the work.
            You are also directed to show cause within a
            week‟s time as to why action for suspension of
            business with your firm/ debarring your firm from
            further tendering in the MCD/ black list of your
            firm, for not taking up the work as per the rules of
            enlistment be not taken. If no reply is received
            from you to the satisfaction of the undersigned
            within above specified period, it will be presumed
            that you have nothing to say in this regard and the
            matter will be referred to the higher authority for
            initiating disciplinary action against you under the
            relevant clauses of the agreement.

                                                Yours faithfully,

                                                            Sd/-
                                               (Ravinder Singh)
                                         Executive Engineer (VI)
            Copy to:
            1. C.E.-I for information pl.
            2. DC (NGZ) for information pl.
            3. SE(NGZ) for information pl.
            4. AE-II to pursue & report.

                                        Executive Engineer (VI)"




WP(C)No.9669/2007 & WP(C)No.9287/2007               Page 11 of 18
 12. It is further observed that vide letter dated 10.10.2007

   another opportunity was granted to the petitioner to explain in

   person on 15.10.2007 at 11:00 a.m. Thus, the letters dated

   3.10.2007, 9.10.2007 and 10.10.2007 would show that hearing

   which    took    place   on   15.10.2007      was    pursuant     to

   communication dated 10.10.2007 and not due to persistent

   requests by the petitioner, as stated in para 5 of the writ

   petition. As per the writ petition, meeting of 15.10.2007 was

   held on account of persistent efforts of the petitioner. Para 5

   of the writ petition reads as under:


               "5.   The petitioner kept representing to the
               respondent bringing out the aforementioned facts
               to the Respondents that the work awarded is in
               fact contrary to the work to be executed and
               therefore extra items should be prepared.
               Accordingly     after   persistent   efforts    the
               Superintending Engineer, Nagafgarh Zone agreed
               to have a meeting in his office wherein the
               representative of the petitioner was present and
               that it was agreed by the Respondent that since
               the scope of work was totally different extra time
               would be sanctioned and the same would be got
               approved by the Executive Engineer and also his
               running bills would be passed. That despite having
               given assurance that extra items would be
               sanctioned nothing was done, as a result of which
               the petitioner was constrained to bring this to the
               notice of the respondent by letter dated
               29.10.2007"


 13.During the course of hearing no reasonable explanation has been

   rendered as to why the petitioner has suppressed the aforestated

   communication.    In the case of Arunima Baruah Vs. Union of

   India, (2007) 6 SCC 120, the Apex Court has held that a petitioner

   would be disentitled to seek discretionary relief in case of

   suppression of material facts. Para 12 of the same reads as under:


   WP(C)No.9669/2007 & WP(C)No.9287/2007                  Page 12 of 18
             "12. It is trite law that so as to enable the court to
            refuse to exercise its discretionary jurisdiction
            suppression must be of material fact. What would be a
            material fact, suppression whereof would disentitle the
            appellant to obtain a discretionary relief, would depend
            upon the facts and circumstances of each case.
            Material fact would mean material for the purpose of
            determination of the lis, the logical corollary whereof
            would be that whether the same was material for grant
            or denial of the relief. If the fact suppressed is not
            material for determination of the lis between the
            parties, the court may not refuse to exercise its
            discretionary jurisdiction. It is also trite that a person
            invoking the discretionary jurisdiction of the court
            cannot be allowed to approach it with a pair of dirty
            hands. But even if the said dirt is removed and the
            hands become clean, whether the relief would still be
            denied is the question.


            13. xxxxxxxx

            14. In Halsbury's Laws of England, 4th Edn., Vol. 16,
            pp.   874-76, the law is stated in the following terms:

                  "1303. He who seeks equity must do equity.--In
                  granting relief peculiar to its own jurisdiction a
                  court of equity acts upon the rule that he who
                  seeks equity must do equity. By this it is not
                  meant that the court can impose arbitrary
                  conditions upon a plaintiff simply because he
                  stands in that position on the record. The rule
                  means that a man who comes to seek the aid of
                  a court of equity to enforce a claim must be
                  prepared to submit in such proceedings to any
                  directions which the known principles of a court
                  of equity may make it proper to give; he must do
                  justice as to the matters in respect of which the
                  assistance of equity is asked. In a court of law it
                  is otherwise: when the plaintiff is found to be
                  entitled to judgment, the law must take its
                  course; no terms can be imposed.
                         *      *     *
                  1305. He who comes into equity must come with
                  clean hands.--A court of equity refuses relief to a
                  plaintiff whose conduct in regard to the subject-
                  matter of the litigation has been improper. This
                  was formerly expressed by the maxim „he who
                  has committed iniquity shall not have equity‟,
                  and relief was refused where a transaction was
                  based      on     the    plaintiff‟s  fraud     or
                  misrepresentation, or where the plaintiff sought
                  to enforce a security improperly obtained, or
                  where he claimed a remedy for a breach of trust

WP(C)No.9669/2007 & WP(C)No.9287/2007                    Page 13 of 18
                      which he had himself procured and whereby he
                     had obtained money. Later it was said that the
                     plaintiff in equity must come with perfect
                     propriety of conduct, or with clean hands. In
                     application of the principle a person will not be
                     allowed to assert his title to property which he
                     has dealt with so as to defeat his creditors or
                     evade tax, for he may not maintain an action by
                     setting up his own fraudulent design."


14.     As far as the merits of the matter is concerned, a bare

  reading of the writ petition would show that not only has the

  petitioner concealed three important letters from this Court i.e.

  letters dated 3.10.2007, 9.10.2007 and 10.10.2007, but has

  intentionally tried to hoodwink this court, in para 5 of the

  petition, it has been averred that a meeting of 15.10.2007 was

  fixed on account of persistent efforts on the part of the

  petitioner for the meeting. It may be noticed that work was

  awarded to the petitioner vide work order dated 15.3.2007 for

  completion    of   the   same   within   eight   months    i.e.   by

  23.11.2007.    On 3.10.2007, the petitioner was warned that

  despite verbal requests the petitioner has not started the work

  and due to delay in completion of the project there would be

  inconvenience to the residents.       Petitioner was directed to

  start the work without loss of time failing which action under

  the relevant clause of the agreement will be initiated and

  petitioner was asked to explain the reasons for not starting the

  work within three months.           Vide communication dated

  9.10.2007, while the contents of earlier letter were reiterated

  and petitioner was informed that his not taking up the work till

  date had rendered himself liable to pay compensation under


  WP(C)No.9669/2007 & WP(C)No.9287/2007                  Page 14 of 18
   clause 2 of the aforesaid agreement and petitioner was asked

  to show cause as to why action under clause 2 of the

  agreement be not taken and also show cause why his firm

  should    not   be   blacklisted.      Vide    communication      dated

  10.10.2007, the petitioner was informed that in the interest of

  justice he had been granted an opportunity to explain his

  position in person on 15.10.2007 at 11:00 a.m. Petitioner did

  not file any reply to letters dated 3.10.2007, 9.10.2007 and

  10.10.2007.     In addition to the aforesaid letters, a personal

  hearing was granted wherein the petitioner had assured that

  the work would commence.            However, the petitioner did not

  commence the work and he was informed by letter dated

  6.11.2007 that as per circular dated 2.6.2003, the cases where

  the work order /contract has been awarded for more than six

  months and work has not yet started, the same is deemed as

  closed and accordingly the contract /work order was closed

  and earnest money of Rs.75,000/- was forfeited.            Petitioner is

  stated to have sent reply to this communication which was

  found unsatisfactory.

15.     Perusal of these communications would show that

  despite a work order having been issued to the petitioner to

  comply with the work within eight months, for over a period of

  six months, the petitioner did not even start the work and in

  addition of being asked verbally, the petitioner was issued

  several    communications           dated     3.10.2007,    9.10.2007,

  10.10.2007 and 6.7.2007; and a personal hearing was also

  granted to the petitioner and it was only thereafter that the

  WP(C)No.9669/2007 & WP(C)No.9287/2007                      Page 15 of 18
 petitioner was black listed. Not only the petitioner was issued

show cause notice, but he was also granted a personal

hearing.   Learned counsel for the petitioner has relied upon in

the case of Gullapalli Nageswara Rao Vs. APSRTC,

reported at AIR 1959 SC 308, Saraswati Dynamics (P) Ltd.

Vs. U.O.I., reported at 2003 (IV) AD (Delhi) 225, and

Mekaster Trading Corporation Vs. U.O.I., reported at 106

(2003) DLT 573 in support of his submission that observance

of principles of natural justice was mandatory before passing

an order „blacklisting the petitioner‟.   There is no quarrel to

this proposition of law argued by the counsel for the petitioner.

However, the judgments relied upon by the petitioner cannot

come to his rescue, in view of the facts of this case wherein a

proper show cause notice as well as a personal hearing was

given and even otherwise, the fact that despite work having

been awarded, the petitioner did not even commence the

work, I find there to be no infirmity in the impugned order.

Learned counsel for the petitioner has also referred to clause

22 of the Enlistment Rules, in support of her plea that the

show cause notice was mandatory. I find that the said rule has

been complied with in this case as a show cause notice was

given. In the case of Nova Steel (India) Ltd. Vs. MCD &

Ors., reported at (1995) 3 SCC 334, notice was issued to the

petitioner as to why should he not be black listed or debarred

for having not replied despite receipt of notice by the

petitioner, the Apex Court did not interfere with the order of




WP(C)No.9669/2007 & WP(C)No.9287/2007                Page 16 of 18
     respondent, who had debarred the petitioner.             Relevant

    portion of the judgment reads as under:


                "2.    It is thus clear that the petitioner having
                negotiated with the respondent to supply the iron
                and received the acceptance in that behalf, he was
                required to enter into the contract and to start
                supply immediately, had not done the same.
                Despite receipt of the notice of show cause, no
                reply thereto was given.            The respondent
                necessarily has to take further action to get the
                supply of required steel. Therefore, they exercised
                the power and issued notice to the petitioner
                which would be consistent with the principles of
                natural justice and passed the offending order
                blacklisting the petitioner for a period of two years.
                The conduct of the petitioner constrained the
                respondents to pass the order of blacklisting. The
                exercise of the power, therefore, cannot be said to
                be unwarranted nor arbitrary nor irrelevant. The
                High Court, therefore, is right in declining to
                interfere with the offending order in exercise of its
                discretionary power under Article 226 of the
                Constitution.     We, therefore, find no ground
                warranting interference under Article 136. The
                SLP is accordingly dismissed."


16. For the reasons that sufficient opportunity had been granted

    to the petitioner to explain his case and the petitioner has not

    even started the work, I find no reason to interfere in the

    impugned circular dated 26.11.2007.

17. In addition the conduct of the petitioner is such that he is not

    entitled to any discretionary relief on the grounds that he had

    mala fide intention and with a view to gain unfair advantage,

    the petitioner on the first date of hearing misled this Court,

    stating that no show cause notice was issued prior to the order

    of blacklisting, and obtained a stay order. The petitioner has

    suppressed documents which are material, integral, essential

    and necessary for deciding the lis between the parties.           A

    WP(C)No.9669/2007 & WP(C)No.9287/2007                 Page 17 of 18
     person who seeks equity must do equity. The petitioner has

    not   approached   this   Court    with   clean    hands     and     has

    suppressed    material    communications          dated    3.10.2007,

    9.10.2007 and 10.10.2007.         The sharp practices adopted by

    the litigants are fast gaining pace and should be discouraged.

18. Petitions are accordingly dismissed with costs of Rs.25,000/-

    each to be paid to the Delhi High Court Legal Aid Society.




                                                       G.S. SISTANI, J.

th April 13 , 2009 'ssn‟ WP(C)No.9669/2007 & WP(C)No.9287/2007 Page 18 of 18