Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 5, Cited by 1]

Appellate Tribunal For Electricity

Oil And Natural Gas Corporation Ltd. ... vs Gujrat Electricity Regulatory ... on 8 March, 2011

                                                                                Appeal No. 52 0f 2010 




                   Before the Appellate Tribunal for Electricity 
                               (Appellate Jurisdiction) 
                                          Appeal No. 52 of 2010  
      Dated :  8th  March, 2011 

     Present:       Hon'ble Mr. Justice M. Karpaga Vinayagam,    Chairperson. 
                    Hon'ble Mr. V.J. Talwar, Technical Member 
     In the matter of: 

     Oil and Natural Gas Corporation Ltd., (ONGC), 
     Head Engineering Services, 3rd Floor, Avani Bhawan, 
     Chandkheda, Ahmedabad‐5.                     ....Appellant 

                    Versus 
     1.    Gujrat Electricity Regulatory Commission. 
           1st Floor, Neptune Tower, Opp. Nehru Bridge, 
           4 Ashram Road, Ahmedabad‐ 380 009 
      
     2.    Gujrat Energy Transmission Co. Ltd. (GETCO) 
           Race Course, Vidyut Bhawan, Vadodara 390 007. 
      
     3.    Uttar Gujrat Vij Company Limited (UGVCL), 
           Visnagar, Mehsana 384 001. 
      
     4.    Dakshin Gujrat Vij Company Ltd., (DGVCL), 
           Nana Varachha Road, Surat 390 007. 
      
     5.    Madhya Gujrat Vij Company Ltd., (MGVCL), 
           Race Course, Vidyut Bhawan, Vadodara 395006.                                 
                                          .............Respondents 
Counsel for Appellant:                    Mr.P.B. Suresh  
                                               Mr. Vipin Nair.  
Counsel for Respondents:                       Mr. M.G. Ramachandran for R‐2 
                                               Ms. Sneha Venkatramni for R‐2 

                                                                                        Page 1 of 37 
                                                                               Appeal No. 52 0f 2010 




                    J u d g m e n t 

Per Hon'ble Shri V.J. Talwar, Technical Member: 

 Oil and Natural Gas Corporation (ONGC) is the Appellant.  

1. Gujarat  Electricity  Regulatory  Commission  (State  Commission)  is  the  first  Respondent.  Gujarat  Electricity  Transmission  Corporation  (GECTO)  is  the  second  Respondent.  3rd,  4th  &  5th  Respondents  are  distribution  licensees  in  the State of Gujarat.  

3.  Aggrieved  by  the  impugned  Order  of  State  Commission  dated  23.9.2009  in  respect of  wheeling charges for wheeling power from Captive Wind Energy  Generators  setup  by  the  Appellant  in  the  State  of  Gujarat  through  Transmission  system  of  GECTO  (R‐2)  to  various  locations  for  its  own  use,  ONGC, the Appellant has filed this Appeal.  

4.  Material facts of this  case are given below. 

5.  State Commission (R‐1) notified Regulations for Procurement of Power from  Renewable  Sources  on  29.9.2005.  Government  of  Gujarat  (State  Government)  issued  Wind  Power  Policy  2007  on  13.6.2007  to  encourage  generation  of  electricity  from  Renewable  Sources  of  Energy  in  the  State.  State Commission issued Tariff Order for wind energy on 11.8.2006. 

6.   Appellant (ONGC) decided to setup 34 Wind Energy Generators each of 1500  kW in Kutch district of Gujarat for captive use at various locations in Gujarat  in  terms  of  State  Commission's  Regulations  and  State  Government's  Policy  2007.  Three Wind Energy Generators were commissioned on 31.3.2008.  The      Page 2 of 37  Appeal No. 52 0f 2010  wheeling agreement was signed between ONGC (Appellant) and GECTO (R‐2)  on  27.5.2008.  Another  set  of  seven  Wind  Energy  Generators  were  commissioned on 31.5.2008. However, GECTO (R‐2) did not  allow wheeling  of  energy  to  Appellant's  various  facilities  (at  more  than  two  captive  locations). 

7.   Hence,  the  Appellant  approached  State  Commission  (R‐1)  vide  petition  No.  954 of 2008 filed on 10.9.2008 with the following prayers: 

i. Seeking  permission  for  wheeling  of  energy  provided  by  31  nos.  of  Wind  Energy Generators installed in Kutch District. 
ii. Seeking  permission  to  sign  wheeling  agreements  with  GECTO                  (R‐
2)/Discoms  concerned  for  wheeling  of  power  from  these  Wind  Energy  Generators to the places of consumption  iii. For payment of surplus energy at the rate of Rs 3.37 per unit determined in  the tariff Order dated 11.8.2006. 

8.  While the said petition was pending,  remaining 24 Wind Energy Generators  were  also  commissioned  on  29.9.2008.  On  20.12.2008  GECTO  (R‐2)  entered  in  to  wheeling  agreement  for  wheeling  of  power  from  7  Wind  Energy  Generators  commissioned  earlier  on  31.5.2008.  GECTO  (R‐2),  however,  refused  to  enter  in  to  wheeling  agreement  for  balance  24  Wind  Energy  Generators  commissioned  on  29.9.2008  on  the  ground  that  as  per  State  Government Wind Power Policy 2007, wheeling of power is restricted to two  captive  locations  per  Wind  Energy  Generator  and  that  ONGC  would  wheel      Page 3 of 37  Appeal No. 52 0f 2010  power  from  these  24  Wind  Energy  Generators  to  more  than  two  locations,  which is not permitted under State Government Policy 2007. 

9.  The State Government amended its 2007 Policy which provided for Wheeling  of  power  from  a  Wind  Energy  Generator  to  more  than  two  locations  of  consumption  subject  to  certain  conditions.  This  amendment  to  2007  Policy  came in to effect from date of notification i.e. 7.1.2009.      

10.  GECTO  (R‐2)  informed  ONGC,  the  Appellant    on  5.3.2009  that  wheeling  agreement  between  GECTO  (R‐2)  and  ONGC  could  be  signed  in  accordance  with  the  amendment  to  State  Government  policy  2007  vide  notification  dated 7.1.2009.   ONGC replied to the above letter on 12.3.2009 stating that  since  State  Government    issued  an  amendment  in  the  wind  power  policy  2007 on 7th January 2009, they had no objection in revising the agreement as  advised  by  the  GECTO  (R‐2)  vide  its  letter  dated  5.3.2009.  ONGC,  the  Appellant,  however,  added  in  their  letter  that  it  might  be  ensured  that  this  comes in to effect from the date of notification i.e.  07.01.2009. The date of  commissioning  of  their  Wind  Energy  Generators  being  much  earlier,  ONGC  requested that applicability of the wheeling charges & levy of 5 paise per unit  may  be  incorporated  in  the  agreements  from  the  date  of  notification  of  Amendment  to  2007  policy.    ONGC  further  added  that  matter  was  already  pending before State Commission and its decision shall be final. 

11.  State  Commission  issued  Tariff  Order  on  17.1.2009  on  GECTO's  (R‐2)  ARR  petition  for  FY  2009‐10  fixing  transmission  charges  at  Rs  2410/MW/day.   Accordingly,  GECTO  (R‐2)  started  recovery  of  transmission  charges  from  all  Wind Energy Generators wheeling power through GECTO (R‐2) network.  

    Page 4 of 37 

Appeal No. 52 0f 2010 

12.  Thereupon  State  Commission  passed  Order  in  ONGC's  petition  No.  954  of  2008 on 6.5.2009.  In the said Order, State Commission observed that it is in  the  process  of  reviewing  its  existing  regulations  and  Order  on  renewable  energy and as a part of this process, the State Commission would take a view  separately,    on  the  amendments  to  the  wind  power  policy  announced  by  State  Government  in  January  2009.    The  State  Commission  in  this  Order,  directed  GECTO  (R‐2)  to  immediately  allow  ONGC,  the  Appellant  to  wheel  power to all the locations as proposed by ONGC with a condition that ONGC  will pay transmission and wheeling charges and excess power purchase as per  amendment to Wind Power Policy 2007 dated 7th January 2009.  

 

13.  The said Order also directed both parties (ONGC and GECTO ) to enter into a  wheeling  agreement  with  a  provision  that  the  Transmission  charges  for  wheeling of power and payment for surplus energy in respect of Wind Energy  Generators  connected  to  grid  prior  to  7th  January  2009  should  be  in  accordance with the prevailing regulations/Orders of the Commission and for  others,  the transmission charges for wheeling power and payment of surplus  energy will be as per the arrangement agreed to by both parties i.e. GECTO  (R‐2) and ONGC, the Appellant.  

14.  GECTO  (R‐2)  raised  the  bill  for  transmission  charges  for  all  the  34  Wind  Energy  Generators  in  accordance  with  amendment  to  State  Government  Wind  Power  Policy  dated  7.1.2009.    ONGC,  the  Appellant    was  of  the  view  that  since  all  his  Wind  Energy  Generators  have  been  commissioned  and  connected  to  grid  prior  to  7.1.2009,  it  should  have  been  charged  in      Page 5 of 37  Appeal No. 52 0f 2010  accordance  with  the  then  prevailing  regulations/Orders  i.e.  as  per  State  Government  Policy  2007  and  State  Commission's  wind  energy  tariff  Order  dated 11.8.2006  and not under  the  amendment to State  Government  Wind  Power Policy 2007 notified on 7.1.2009. .  

 

15.  Having  aggrieved  over  GECTO's  (R‐2)  action  of  raising  the  bill  under  the  amended  policy,  ,  ONGC  filed  a  petition  No  971  of  2009  before  State  Commission, praying  for the compliance of State Commission's Order dated  6.5.2009  to  the  effect  that  amendment  to  State  Government  Wind  Power  Policy notified on 7.1.2009 should not be made applicable to 24 no. of Wind  Energy Generators commissioned earlier.  

16.  After  hearing  the  parties,    State  Commission  passed  impugned  Order  dated  23.9.2009 in the  petition No.  971/2009.   The State Commission in para [5]  of impugned Order has observed that:  

"The  petitioner has in  para  3  of  the  earlier  petition no. 954/2008  Stated  that 3 No. Wind Energy Generators out of 34 nos. were commissioned on  31.3.2008 and wheeling agreement had been signed.  Seven more no. of  Wind  Energy  Generators  were  commissioned  in  May  2008  and  wheeling  agreement  was  under  execution.  Remaining  24  no.  of  Wind  Energy  Generators  were  ready  for  commissioning  in  June  2008  had  not  been   connected to the grid in spite of petitioner's requests. Thus, the petitioner  has accepted that on 9.9.2008 when petition was filed, only 10 nos. of the  WEGs  were  commissioned  and  remaining  24  nos.  of  WEGs  were  not      Page 6 of 37  Appeal No. 52 0f 2010  connected  with  the  grid.  The  aforesaid  matter  was  disposed  off  by  the  Commission on 6.5.2008. Till that day, no other fact contrary to the above  was  brought  to  the  notice  of  the  Commission  by  the  petitioner.  Even  during  the  proceedings  of  Petition  no.  954/2008  the  petitioner  did  not  submit that 24 nos. of WEGs were commissioned and connected with the  grid."  

17.  State  Commission  in  para  5.4  of  the  impugned  Order  dated  23.9.2009  has  recorded that:  

"5.4 Hence, GECTO (R‐2) ought to have sent invoice /bill for transmission  charges  as  per  Wind  Power  Policy,  2007  and  Order  No.2  of  2006  dt.11.8.2006 for 10 Nos of Wind Energy Generators and not as per Policy  dated 7.1.2009. In case of remaining 24 nos. of Wind Energy Generators,  GECTO (R‐2) is entitled to raise invoice/ bills as per amendment made in  the Wind Power Policy,2007, which was agreed to by the petitioner during  the proceedings in Petition No.954/2008. Both ONGC and GECTO (R‐2) are  directed  to  implement  the  Commission's  Order  dt.6.5.2009  in  Petition  No.954/2008  accordingly.  GECTO  (R‐2)  is  directed  to  withdraw  invoices/  bills  issued  on  25.5.2009  and  18.6.2009  and  revise  the  same  as  per  the  direction given in earlier para of this Order. It is clarified that amendments  to  State  Government  Policy,  2007  notified  on  7.1.2009  will  not  be  applicable  to  the  10  nos.  of  Wind  Energy  Generators  which  were  commissioned  and  connected  to  the  grid  prior  to  6.5.2009.  Through  the  Amendment to State Government Policy,2007 notified on 7.1.2009 is to be  applied  by  GECTO  (R‐2)  to  the  remaining  24  nos.  of  Wind  Energy      Page 7 of 37  Appeal No. 52 0f 2010  Generators as a special case. Both petitioner and respondents are directed  to implement this Order immediately." 

18.  Aggrieved  by  this  Order  dated  23.9.2009,    the    Appellant,  ONGC  has      filed  this present appeal.   

19.   Learned Counsel for the Appellant would raise the contentions as follows:  

i. There was no restriction on number of locations for Wind Energy Generator  as  per  the    State  Government  Wind  Power  Policy  2007.  GECTO  (R‐2)  had  delayed wheeling agreement without any reason. 
ii. Appellant's  Wind  Energy  Generators  were  commissioned  and  connected  to  grid much before amendment to State Government Wind Power Policy 2007,  which  came in to force  on 7.1.2009  iii. State Commission in its Order dated 6.5.2009 had observed that it was in the  process of reviewing its existing regulations and Order on renewable energy  and as a part of this process,  the State Commission would separately take a  view  on  the  amendments  to  the  wind  power  policy  announced  by  State  Government  in  January  2009.  Thus  the  earlier  Order  dated  6.5.2009  was  a  protem  Order  until  the  State  Commission  finalized  consideration  of  State  Government's  amendment  dated  7.1.2009.    Since  then,  State  Commission  has  come  out  with  a  number  of  Orders  by  which  it  is  made  clear  that  for  Wind  Energy  Generators  commissioned  prior  to  11.8.2009,  the  unamended  policy  would  alone    apply  and  as  such  there  is  no  basis  for  increased  tariff  under the amended policy.  
    Page 8 of 37 
Appeal No. 52 0f 2010  iv. It  is  not  open  to  State  Commission  to  materially  amend  its  earlier  Order  dated 6.5.2009.  In case, the State Commission is  of the view that they had  been misled,  they should have examined the matter dispassionately on the  merits  after  recalling  the  earlier  Order  as  being  based  on  a  mis‐ representation. 
v. The categorical assertion in the operative part of the earlier Order is that in  respect  of  Wind  Energy  Generators  connected  to  the  Grid  prior  to  January,  2009,    the  unamended  policy  would  prevail.    Admittedly,  in  this  case,  34  Wind Energy Generators were connected to the Grid prior to 7.1.2009  vi. The  impugned  Order  itself  recognizes  that  for  10  WTGs  connected  prior  to  7.1.2009, the earlier policy is applicable.  Therefore, on a parity of reasoning,  the balance 24 WTGs also should be governed by the earlier policy only. 

20.    The learned counsel for respondent submitted in reply as follows:  

i. Appellant  had  been  misinterpreting  the  Order  dated  6.5.2009,  which  refers  to  Wind  Turbine  Generators  connected  to  the  Grid  prior  to  7.1.2009  in  the  sense  of  supply  of  the  electricity  to  the  Grid.  The  Appellant  is  confusing  it  with the testing of the units and making it ready for commercial operation. 
ii. The correct factual position is that unlike the first 10 wind turbine units, the  24 wind turbine units were connected to the grid after 7.1.2009 for wheeling  and therefore would be governed by the Wheeling charges as specified in the  Amended Policy effective from 7.1.2009.  
    Page 9 of 37 
Appeal No. 52 0f 2010  iii. The  reading  of  the  Order  dated  6.5.2009    clearly  establishes  that  the  Appellant  claimed commissioning of 24 units was prior to 7.1.2009 and the  Respondent No. 2 objecting to the claim for wheeling of electricity to more  than two locations.  The differing stand taken by both parties had invited the  decision of the State Commission (by settling the matter) that the connection  to  the  grid  for  wheeling  be  considered  with  effect  from    4.3.2009  and  that  the Appellant would pay wheeling charges for the 24 Wind Turbine units as  per Amended Policy dated 7.1.2009. 
iv. Appellant  had  settled  the  matter  with  the  Respondent  No.  2  vide  his  the  letter dated 12.3.2009, wherein the Appellant dealing specifically with the 24  Wind  Turbine  units  in  issue  Stated  clearly  that  the  Appellant  agrees  to  the  payment of wheeling charges as per Amendment dated 7.1.2009. The same  was  reiterated  in  the  Rejoinder  filed  before  the  State  Commission  on  25.3.2009.  The  Order  dated  6.5.2009  was  made  pursuant  thereto.  It  is  not  open to the Appellant to take a contrary stand subsequently and claim that  the  wheeling  from  24  units  shall  be  governed  by  the  un‐amended  2007  policy. 

v. The  Appellant  signed  wheeling  agreements  with  the  Respondent  No.  2  for  wheeling of electricity from the 24 units set up after the Amended Policy of  the Government of Gujarat dated 7.1.2009. Pursuant to and in terms of the  wheeling  Agreements  executed,  the  Appellant  was  permitted  to  wheel  electricity from the place of generation to its different locations. 

21.    In view of rival  contentions  referred  to  above  urged  by the  learned  counsel  for parties, following questions would arise for consideration: 

    Page 10 of 37 
Appeal No. 52 0f 2010  i. Whether there was any provision for restriction up to two locations per Wind  Energy Generator in State Government Wind Policy 2007 and on this ground   GECTO (R‐2) delayed entering into wheeling agreement with ONGC?  
ii. Whether  all  34  Wind  Energy  Generators  of  ONGC  were  commissioned  and  connected to grid prior to 7.1.2009? 
iii. Whether ONGC can raise the issue of wheeling charges when it has agreed to  pay the same as per provisions of amended policy?  
iv. Whether  State  Commission  was  right  in  holding  that  issue  cannot  be  raised  on the ground that commissioning of 24 Wind Energy Generators were not  brought  to  its  notice  during  proceedings  and  appellant  had  agreed  to  be  covered by amended policy? 
v. Whether Government of Gujarat's amendment to 2007 Policy date 7.1.2009  fixing wheeling charges for captive Wind Energy Generators is legally tenable  in terms of  Electricity Act 2003. 

22.  We shall now deal with each question one by one. 

23.  First question to be decided as to whether there was any restriction in regard  to  number  of  locations  per  Wind  Energy  Generator  in  State  Government  Wind Power Policy 2007. For the purpose of finding out the answer for this,   we will have to examine the contents of State Government's Wind Power  Policy 2002 and Wind Power Policy 2007. 

24. The Wind Power Policy of the Government of Gujarat, notified in 2002. inter      Page 11 of 37  Appeal No. 52 0f 2010  alia, provided for wheeling of electricity by Industrial Undertakings for their  use as under : 

"3. Eligibility: 
 ............... such industrial units may be allowed to wheel power to their  own manufacturing units (maximum up to two units) within the State  at wheeling price to be paid by them" (emphasis supplied)  ................... 
"8. Wheeling of Electricity The  industrial  undertakings  setting  up  wind  energy  generators  while  opting  for  wheeling  the  electricity  to  their  manufacturing  units  may  be allowed to do so at a wheeling charge of 4%." 

The Wind Power Policy of 2002 was superseded by notification of the Wind  Power Policy, 2007 providing for various terms and conditions applicable to  the generators setting up wind energy projects in the State of Gujarat. 

The Policy of 2007, inter‐alia, provided as under : 

"2. Operative period: 
This policy will come into force with effect from 20th June, 2007 and shall  remain  in  operation  upto  30th  June,  2012,  which  will  be  the  operative  period  of  the  scheme.  Wind  Turbine  Generators  (WTGs)  installed  and  commissioned during the operative period shall become eligible for the      Page 12 of 37  Appeal No. 52 0f 2010  incentives declared under this policy, for a period of twenty years from  the date of commissioning or for the life span of the WTGs, whichever is  earlier. 
3. Eligible Unit Any  company  or  body  corporate  or  association  or  body  of  individuals,  whether incorporated or not, or artificial judicial person, will be eligible  for setting up of WTGs, either for captive use and/or selling the energy,  in  accordance  with  the  Electricity  Act  2003,  as  amended  from  time  to  time. 

Explanation :‐ The use of electricity for own consumption at his end use  location/s by the owner of WTGs shall be considered as captive use. 

5. Wheeling of Electricity:

The  wheeling  of  electricity  generated  from  the  WTGs,  to  the  desired  location/s within the State, shall be allowed at a wheeling charge of 4%  of  the  energy  fed  to  the  grid,  as  per  Gujarat  Electricity  Regulatory  Commission (State Commission) Order, as amended from time to time."  (emphasis supplied) 
25.    From perusal of the two policies i.e. 2002 Policy and 2007 Policy, it can be  noticied that the 2002  policy explicitly provided restriction of two location  per Wind Energy Generator, where as  the 2007 policy did not specifically  provide for the number of locations to which wheeling shall be allowed. In  fact  the  use  of  word  location/s  in  explanation  to  clause  3  and  clause  5  of      Page 13 of 37  Appeal No. 52 0f 2010  the Wind Power Policy 2007 clearly indicate that end use could be at more  than  one  location.  GETCO  (R‐2)  assumed  that  in  the  absence  of  specific  provision, earlier provision would continue and thus did not allow ONGC to  wheel power to more than two locations per Wind Energy Generator.  
26.      It  is  well  established  principle  of  law  that,  when  an  alteration  is  made  to  existing  provision,  the  alteration  must  be  considered  to  have  been  made  deliberately.  Hon'ble  Supreme  Court  in  K  C  Deo  Bhanj  v  Raghunath  Misra  (AIR 1959 SC 586) observed that  "In the marginal note, however, the word "reduce"was not substituted  by  the  word  "modify",  apparently  through  inadvertence.  If  the  word  "modify"is  to  be  read  as  "reduce",  then  there  could  be  no  point  in  provincial  legislature  substituting  the  word  "reduce"  by  the  word  "modify". This change must have been made with some purpose and the  purpose  could  only  have  been  to  use  the  expression  of  wider  connotation  so  to  include  not  only  reduction  but  also  other  kinds  of  alteration...  In  our  opinion  the  dropping  of  the  word  "reduce"  and  introduction  of  the  word  "modify"  in  the  body  of  section  60  of  the  Act  under consideration clearly indicate an intention on part of legislature to  widen the scope of this section... 
27.    In  the  present  case,  specific  restriction  of  up  to  two  captive  locations  per  Wind  Energy  Generator  as  provided  in  2002  Policy  was  dropped  in  2007  Policy of State Government. In fact the words "up to two locations" in 2002  Policy  were  replaced  by  word  "location/s"  in  2007  Policy.  The  change      Page 14 of 37  Appeal No. 52 0f 2010  cannot be assumed to have occured inadvertently.  
28.   Further, through its letter dated 6th November 2008 from Deputy Secretary,  Energy  and  Petrochemical  Department;  State  Government  addressed  to  Managing  Director,  GECTO  (R‐2)  clarified  the  issue  beyond  doubt.  The  relevant portion of said letter is reproduced below: 
"With reference to the letter dated 21st May 2008 from the Vice Chairman,  M/S India Wind Energy Association, Ahmadabad regarding interpretation  of certain provisions of Wind Power Policy along with earlier Wind Power  Policy  ‐2002  for  wheeling  of  wind  power  to  more  than  two  Captive  locations. 
In this regard, I am directed to clarify that the wheeling of Wind Power to  more  than  two  captive  locations  is  allowed  under  existing  Wind  Power  Policy 2007, I am therefore, to request you to kindly take note of this for  favour  of  further  necessary  action  at  your  end  accordingly."  (emphasis  added) 
29.  The  above  letter  dated  6th  November  2008  from  Deputy  Secretary,  State  Government  had  cleared  any  doubt  in  respect  of  number  of  captive  locations  and  GECTO  (R‐2)  should  have  entered  into  wheeling  agreement  with ONGC without further delay. However, GECTO (R‐2) further waited till  the State Government amended its Wind Power Policy 2007 on 7th January  2009  wherein  wheeling  charges  had  increased  substantially.  Only  then  GETCO (R‐2) invited Appellant ONGC to enter in to wheeling agreement on      Page 15 of 37  Appeal No. 52 0f 2010  revised terms and conditions as per amended policy. 
30.      From  the  above  discussions,  it  is  to  be  concluded  that  there  was  no  restriction on number of captive locations in Wind Power Policy 2007 and  GECTO  (R‐2)  had,  therefore,  delayed  the  wheeling  agreement  to  the  disadvantage of the Appellant. 
31. Next question for consideration is as to whether Wind Energy Generators of  ONGC were commissioned and connected to grid prior to 7.1.2009?  
32.  ONGC, the Appellant  in its petition number 954 of 2008 dated 10.9.2008 filed   before  the  State  Commission,  had  Stated  that  3  number  Wind  Energy  Generators  had  already  been  commissioned  and  connected  to  grid  for  wheeling  of  power  and  Wheeling  agreement  had  been  entered  into  by  GETCO  (R‐2).      Seven  number  Wind  Energy  Generators  were  also  commissioned and connected to grid but GETCO (R‐2) was not entering in  to wheeling agreement with Appellant. 
33.    Another  set  of  24  numbers  of  Wind  Energy  Generators  were  ready  for  commissioning.  Hence  Appellant  requested  State  Commission  to  direct  GECTO (R‐2) to enter into wheeling agreement. ONGC has claimed that 24  Wind Energy Generators were also commissioned on 29.9.2008 and has put  on record a certificate from Gujarat Energy Development Agency (GEDA) in  support of this claim. Certificate from GEDA dated 23.10.2008 clearly shows  that  24  Wind  Energy  Generators  were  commissioned  on  29.9.2008.  These  Wind  Energy  Generators  had  produced  power  and  injected  it  into  GETCO      Page 16 of 37  Appeal No. 52 0f 2010  (R‐2) grid. The certificate mentions that: 
"This  wind  farm  is  connected  by  33  kV  grid  line  to  33/220  kV,  300  MVA capacity Moti Sindholi site substation at Moti Sindholi. The Moti  Sindholi  site  substation  is  connected  to  GECTO  (R‐2)  Nani  Khakhar  Substation." 

34.    GECTO  (R‐2)  on  the  other  hand  contested  the  above  and  submitted  that  the  certificate by GEDA was only for testing purposes and making them ready for  commercial  operation.  We  have  closely  examined  the  copy  of  certificate  issued  by  GEDA.  Relevant  portion  of  certificate  issued  by  GEDA  dated  23/10/2008 is reproduced below: 

"CERTIFICATE OF COMMISSIONING    This is to certify that M/S Oil and Natural Gas Corporation Ltd ... have  commissioned  36  MW  capacity  wind  farm  consisting  of  24  (twenty  four) numbers of new  wind  turbine  generators as  per  the  WTG  ID  no. 

and date of Commissioning given below.... 

This wind farm is connected by 33 kV grid line to 33/220 kV, 300 MVA  capacity  Moti  Sindholi  site  substation  at  Moti  Sindholi.  The  Moti  Sindholi  site  substation  is  connected  to  GETCO  Nani  Khakher  Substation..." 

      Page 17 of 37 

Appeal No. 52 0f 2010 

35.  The above certificate issued by GEDA cannot be taken as a mere certificate for  testing  and  making  them  ready  for  commercial  operation.  In  fact  the  title  of  certificate  itself  is  "Certificate  of  Commissioning".    This  certificate  has  also  given  details  of  generation  report  for  the  purpose  of  commissioning  of  wind  farm showing some amount of generation by wind farm and fed into the grid.  

36.  GETCO (R‐2) has in its written submission in para 8  also accepted that Wind  Energy  Generators  were  commissioned  and  connected  to  grid  as  indicated  below: 

"Thus, the wheeling of electricity from the 24 units of the Appellant was  only  commenced  after  the  date  of  coming  into  force  of  the  Amended  Policy  of  the  Government  of  Gujarat  dated  7.1.2009.  Prior  to  the  Agreement, there was  no wheeling  and  the  Appellant  did  not  get  any  adjustment  for  the  Energy  Units,  if  any,  injected  into  the  grid  by  the  Appellant by reason  of  connectivity  to  the  system.  All  such  units were  taken  as  unscheduled  injection  of  Energy  into  the  Grid.  Thus,  notwithstanding  any  connectivity  to  the  Grid,  there  was  no  wheeling  and  there  was  no  agreement  or  arrangement  where  under  the  Appellant could be said to have commenced wheeling of electricity." 

37.  Respondent (2) has, thus by admitting that prior to the agreement, there was  no wheeling and Appellant did not get any adjustment for the Energy units, if  any,  injected  into  the  grid  by  Appellant  by  reason  of  connectivity  to  the  system,  has  virtually  accepted  that  the  Wind  Energy  Generators  were  commissioned and connected to grid before signing of wheeling agreement.  There is no denial of the fact that wheeling would commence only from the      Page 18 of 37  Appeal No. 52 0f 2010  date  of  the  wheeling  agreement.    The  real  Question  is  as  to  whether  Wind  Energy Generators of ONGC were commissioned and connected to grid prior  to 7.1.2009 i.e. the date from which Amendment to Government of Gujarat's  Wind Power Policy 2007  came in to effect.  

38.  From commissioning certificates issued by GEDA and assertion of GETCO (R‐

2), it is clear that the Wind Energy Generators were in fact commissioned and  connected  to  grid  prior  to  7.1.2009.  The  State  Commission  ought  to  have  ascertained  these  facts  regarding  commissioning  and  grid  connectivity  from  full  dump  of  memory  contents  of  energy  meters  installed  at  Wind  Energy  Generator site.  However this was admittedly not done. 

39.  Under  these  circumstances,  we  are  of  the  opinion  that  all  Wind  Energy  Generators were commissioned and connected to grid prior to 7.1.2009 and  then same should have been dealt with  accordingly. 

40.  Next question under consideration is as to whether ONGC, the Appellant  can  be permitted to withdraw from a stand taken vide its letter dated 12.3.2009  that  there  was  no  objection  in  revising  the  agreement  in  terms  of  amendment to 2007 Policy and  now claim that his  Wind Energy Generators  were commissioned and connected to grid prior to 7.1.2009 and therefore it  is  not  liable  to  be  subjected  to  provisions  of  amendment  to  Wind  Power  Policy 2007? 

41.  For  getting  answer  to  this  question  it  would  be  proper  to  refer  to  the  contents of ONGC's letter dated 12.3.2009. Letter is reproduced below: 

    Page 19 of 37 
Appeal No. 52 0f 2010  "Please  refer  your  letter  no.  GETCO/EE‐C/2108  dated  05.03.2009  regarding subject cited above, since Government of Gujarat has issued an  amendment in the wind Power Policy 2007 on 7th January 2009 we have  no objection to revise the agreement clause no. 3.2 & 3.6 as advised vide  your above referred letter. 
However this may please be ensured that this comes into effect from the  date  of  G.R.  (this  is  w.e.f  07.01.09).  The  date  of  commissioning  of  our  WTGs  being  much  earlier,  it  is  requested  that  applicability  of  the  wheeling  charges  &  levy  of  5  paise  per  unit  under  clause  3.2  &  3.6  respectively  may  be  incorporated  in  the  agreements  from  the  date  of  notification of amendment to policy. 
It  is  not  out  of  Order  to  mention  that  the  hearing  of  our  petition  before  Hon'ble  GERC  is  scheduled  to  be  held  on  17.03.09  &  the  decision  of  Hon'ble commission shall be final" (emphasis added) 

42.  In the first paragraph of the said letter, the  Appellant has Stated that since  the  Policy  of  2007  had  been  amended  by  Government  of  Gujarat  on  7th  January  2009,  they  have  no  objection  in  revising  the  relevant  agreement  clauses  accordingly.  In  second  paragraph,  the    Appellant  has  clearly  mentioned  that  date  of  commissioning  of  their  Wind  Energy  Generators  being  much  earlier  to  7.1.2009,  applicability  of  amended  wheeling  charges  and other conditions to be incorporated in the agreement would be from the  date of notification of amendment to the policy.  

    Page 20 of 37 

Appeal No. 52 0f 2010 

43.  The relevant portion of Government of Gujarat Government Resolution dated  7th January 2009 amending Government of Gujarat's Wind Power Policy 2007  is reproduced below: 

"1.Title This Policy Shall be known as "Wind Power Policy (First Amendment) 2007  "2. Amendment of Clause No. 5 - Wheeling of Electricity The clause shall be substituted by the following:‐ 
(a) Wheeling  of  power  to  consumption  site  at  66  kV  voltage  level  and  above:‐  The  wheeling  of  electricity  generated  from  the  Wind  Turbine  Generators  (WTGs) to the desired location(s) within the State, shall be allowed on the  payment  of  transmission  charges  and  transmission  losses  otherwise  applicable to normal Open Access Customers. 

.............................. 

Wind farm owner desiring to wheel electricity to more than two locations  shall  pay  5  paise  per  unit  on  energy  fed  in  the  grid  to  concerned  Distribution  Company  in  whose  area,  power  is  consumed  in  addition  to  above mentioned transmission charges and losses, as applicable.  

... 

    Page 21 of 37 

Appeal No. 52 0f 2010  This  will  come  in  to  effect  from  the  date  of  Government  Resolution" 

(emphasis supplied) 

44.  According  to  the  Appellant,    the  date  of  above  mentioned  Government  Resolution  was  7.1.2009  and  therefore  all  Wind  Energy  Generators  commissioned prior to that date would be covered under earlier 2007 policy  and  Wind  Energy  Generators  commissioned  on  or  after  7.1.2009  would  be  covered under amendment to 2007 Policy.  

45.  Let  us  now  examine  the  chronological    events  in  this  context.  First  set  of  3  Wind  Energy  Generators  were  commissioned  and  connected  to  grid  on  31.3.2008 and Wheeling agreement was signed on 27.05.2008. Another set of  7  Wind  Energy  Generators  were  commissioned  and  connected  to  grid  31.05.2008  and  wheeling  agreement  was  signed  on  21.12.2008.  Balance  24  Wind Energy Generators were ready for commissioning during June 2008 but  wheeling agreement could not be signed due to GETCO's (R‐2) refusal to allow  wheeling to more than two captive locations.  

46.  On  10.09.2008  ONGC,  the  Appellant  filed  petition  before  State  Commission,  seeking  for  the  direction  to  GETCO  (R‐2)  to  enter  in  to  wheeling  agreement.  The matter was pending before State Commission for long.  In the meantime  all the 24 Wind Energy Generators were commissioned and connected to grid  on  29.9.2008.  State  Government  also  issued  clarification  on  6.11.2008  that  there  was  no  restriction  on  number  of  locations  to  wheel  wind  power.  On  7.1.2009 the State Government issued amendment to Wind Power Policy 2007  enhancing wheeling charges substantially. GETCO (R‐2) informed ONGC about  change in 2007 Policy on 5.3.2009.  

    Page 22 of 37 

Appeal No. 52 0f 2010 

47.  During  this  period,  Appellant's  Wind  Energy  Generators  were  commissioned  injecting  wind  power  in  to  the  grid  but  could  not  get  desired  benefit.  Under  the said circumstances, Appellant had no option but to accept the offer made  by GETCO (R‐2) for wheeling. While accepting the offer, Appellant was careful  enough  to  add  that  its  Wind  Energy  Generators  were  commissioned  much  before the date of said Government Resolution and provisions of amendment  to  2007  Policy  would  be  applicable  from  date  of  Government  Resolution.  In  other words, the Appellant had Stated that since its  units were commissioned  much  before  the  date  of  Government  Resolution  and  since  the  provisions  of  said Government Resolution are to be applied prospectively, it would not have  any  impact  on  it.    The  Appellant  further  added  that  the  matter  was  pending  before  State  Commission  and  its  decision  shall  be  final.  Thus  Appellant's  acceptance  vide  said  letter  dated  12.3.2009  cannot  be  termed  as  absolute  acceptance but at the best it can be considered a conditional acceptance.  

48. In view of above, in our opinion Appellant is not estopped from raising the issue  before the Commission and  in this Tribunal. 

49.  Next issue for our consideration is as to Whether State Commission was right  in holding that issue cannot be raised on the ground that commissioning of 24  Wind  Energy  Generators  were  not  brought  to  its  notice  during  proceedings  and appellant had agreed to be covered by amended policy? 

50.  State Commission's findings in this regard in the impugned Order are as given  below: 

    Page 23 of 37 
Appeal No. 52 0f 2010 
(i)  During the proceedings, the petitioner did not submit that 24 number  of  Wind  Energy  Generators  were  commissioned    and  connected  to  the  Grid.    The  petitioner  has,  for  the  first  time,  come  with  the  evidence in the form of certificate issued by GEDA that 24 numbers of  Wind Energy Generators were commissioned on 29.9.2008. This is a  new evidence and plea which was never brought to the notice of the  Commission.  There  was  nothing  on  record  that  remaining  24  numbers of Wind Energy Generators had also been commissioned on  29.9.2008. 

(ii)  The  letter  dated  6.11.2008  of  Deputy  Secretary,  Energy  &  Petrochemical Department in which it is Stated that wheeling of wind  power to more than two locations is allowed under the existing Wind  Power  Policy,  2007,  is  also  new  evidence  and  plea  advanced  by  the  petitioners. 

(iii)  Moreover,  petitioner  had  admitted  before  the  Commission  categorically and specifically that they are ready to pay transmission  and  wheeling  charges  as  per  Amendment  made  in  Wind  Power  Policy, 2007. 

51.  Before proceeding further, we would consider the merits of the observation  made above.  

51.1.  As regards the observation  made at (i) above, it is to be noted that Appellant  had  approached  State  Commission  vide  petition  no.  954  of  2008  dated  10.9.2008  with  a  prayer  to  direct  GETCO  to  enter  into  wheeling  agreement      Page 24 of 37  Appeal No. 52 0f 2010  with the Appellant for wheeling power from its Wind Energy Generators and  the  State    Commission  in  para  2.4  of  its  Order  dated  6.5.2009,  has  Stated  those  facts as per petition filed by the appellant, which are given below:  

"2.4  Three  Wind  Energy  Generators  out  of  the  34  Nos.  installed  were  commissioned  on  31.3.2008  and  wheeling  agreement  has  been  signed.  7 more Wind Energy Generators were commissioned in May,  2008,  wheeling  agreement  for  which  is  under  execution.    The  remaining  24  Nos.  of  Wind  Energy  Generators  which  were  also  commissioned  but  not  connected  to  the  grid  inspite  of  petitioner's  requests." 

In  para  7.7  of  the  said  Order  dated  10.9.2008    the  State  Commission  took  cognizance  of  Appellant's  letter  to  GETCO  dated  12.03.2008  wherein  Appellant  had  Stated  that  its  Wind  Energy  Generators  were  commissioned  much earlier than the date of Government Resolution i.e. 7.1.2009. In view of  the above it cannot be held that Appellant had not informed the Commission  about commissioning of 24 Wind Energy Generators during the proceedings  in petition No.  954 of 2008  and the same had been informed only  during  proceedings related to the  impugned Order. 

51.2.  As regards the second observation made by the State Commission, it is to be  Stated that the letter dated 6.11.2008 from Deputy Secretary, Government of  Gujarat  was  a  new  material  and  the  said  letter  was  also  addressed  to  MD,  GETCO  (R‐2).  In  this  letter,  Government  of  Gujarat  had  clarified  that  there  was no restriction on number of captive locations per Wind Energy Generator  in  Wind  Power  Policy  2007.  Immediately  upon  receipt  of  this  letter,  GETCO      Page 25 of 37  Appeal No. 52 0f 2010  (R‐2)  should  have  entered  into  Wheeling  Agreement  with  Appellant  and  allowed him to wheel power to desired locations without any further delay.  However, GETCO delayed the signing of wheeling agreement and waited for  Amendment  to  2007  policy  enhancing  wheeling  charges  substantially.  State  Commission  should  not  have  allowed  GETCO  to  get  benefit  of  higher  wheeling charges for its intentional delay. It is well settled principle that no  person  can  take  advantage  of  its  own  wrong.  The  well  known  maxim  is: 

"Nulls  commode  capere  potest  de  injuria  sua  propria"  (No  one  take  advantage  of  his  own  wrong).  Broom's  Legal  Maxims,  10th  Edition  explains  the maxim, inter alia as under:  
"It is a maxim of law, recognized and established, that no man shall take  advantage  of  his  own  wrong;  and  this  maxim,  which  is  based  on  elementary  principles,  is  fully  recognized  in  Courts  of  law  and  of  equity,  and, indeed, admits of illustration from every branch of legalprocedure." 

This maxim has been followed by the Hon'ble Supreme Court. In the decision  of Union of India vs Major General Madan Lal Yadav reported in 1996(4) SCC 

127.  In  the  present  case  before  us,  GETCO  (R‐2)  had  not  allowed  ONGC,  the  Appellant wrongly to wheel power from its Wind Energy generators to more  than  two  captive  location  despite  the  clarification  issued  by  Government  of  Gujarat  in  this  regard.  Hence,  GETCO  (R‐2)  cannot  be  allowed  to  take  advantage of its own wrong.   

    Page 26 of 37 

Appeal No. 52 0f 2010 

52.  In  the  light  of  above  discussions,  we  are  of  the  view  that  the  State  Commission should have decided the case on its own merits and not on the  basis  of  observations  made  above.      As  indicated  above,  the  State  Commission ought to have ascertained the fact about commissioning of Wind  Energy  Generators  from  full  dump  of  meters  provided  at  Wind  Energy  Generators and passed the Order accordingly. 

53.    Now,  next    important  question  before  us  to  consider  is  as  to  whether  the  amendment  to  2007  Policy  on  7.1.2009  enhancing  wheeling  charges  as  determined by the State Commission for captive Wind Energy Generators is  legally tenable.  

54.  A  new  concept  of  Open  Access  has  been  introduced  with  enactment  of  Electricity Act 2003. Statutes in force prior to the enactment of 2003 Act did  not have the  provisions regarding wheeling of power and wheeling charges  for  third  party  use  of  distribution  system  of  distribution  licensee  or  SEB.  Government of Gujarat with a view to harness vast potential of wind power  in the State issued Wind power Generation Policy 2002. Relevant portion of  this policy is given below: 

"RESOLUTION    Gujarat  has  largest  coast  line  in  the  country  and  the  potential  for  wind  energy in the State is around 5000 MW on the coast line of Saurastra and  Kutch. The Gujarat Energy Development Agency in collaboration with the  Indian Institute of Meteorology, Bangalore has identified several excellent  sites for wind power generation in the State. The Government of India has      Page 27 of 37  Appeal No. 52 0f 2010  also  announced  guild  lines  for  Wind  Energy.  The  formulation  of  a  sustainable wind power generation policy was therefore under the active  consideration  of  State  Government.  After  due  consideration,  the  State  Government has decided to declare Wind Power Policy 2002...  
3.  Eligibility    Under  this  policy  no  cash  incentives  of  Sales  Tax  incentives  are  available  primarily  due  to  constraints  of  resources.    It  is  therefore,  proposed to  widen the  eligibility  criteria  for setting  up  such wind  energy  generators.  The beneficiaries are classed in two parts as under: 
(i)  Any  registered  industrial  undertaking  engaged  in  manufacture  or  production of goods within the State  Such  Industrial  units  may  be  allowed  to  wheel  power  to  their  own  manufacturing  units  (maximum  upto  two  units)  within  the  State  at  a  wheeling  pace  to  be  paid  by  them.    This  would  encourage  the  industrial  undertakings to set up such wind generators since they would be availing  the benefits of relatively cheaper electricity.  Such wind energy generating  units  may  also  be  allowed  at  their  option  to  sell  electricity  to  the  Gujrat  Electricity  Board  at  a  fixed  price  to  be  paid  per  unit.    It  should  be  made  obligatory  for  them  to  give  the  option  and  the  option  once      exercised  should not be changed. 

8. Wheeling of Electricity: 

    Page 28 of 37 
Appeal No. 52 0f 2010  The  industrial  undertakings  setting  up  wind  energy  generators  while opting for wheeling the electricity to their manufacturing units may  be allowed to do so at a wheeling charge of 4%." 
55.  Since  the  statutes  in  force  prior  to  year  2003  had  no  provision  for  determination  of  wheeling  charges,  provision  contained  in  Government  of  Gujarat's 2002 Policy had force of law.  
56.  After enactment of  Electricity  Act  2003,  power  to  determine  tariff  including  wheeling charges did not remain with State governments. State Commissions  had  been  entrusted  with  determination  of  tariff  including  wheeling  charges  under  Electricity  Act  2003.  Section  86  of  this  Act  providing  the  functions  of  State Commission is reproduced below: 
86.  Functions  of  State  Commission  (1)  The  State  Commission  shall  discharge the following functions namely:‐ 
(a) determine the tariff for generation, supply, transmission and wheeling  of  electricity,  wholesale,  bulk  or  retail,  as  the  case  may  be,  within  the  State: 
Provided  that  where  open  access  has  been  permitted  to  a  category  of  consumers  under  section  42,  the  State  Commission  shall  determine  only  the wheeling charges and surcharge thereon, if any, for the said category  of consumers; 
    Page 29 of 37 
Appeal No. 52 0f 2010 
57.  In terms of Section 86 of 2003 Act, State Commission vide its Order no. 2 of  2006 dated 11th August 2006 determined Transmission and Wheeling Charges  as under: 
" 20 Transmission and Wheeling Charges  The  Commission  clarifies  that  the  procurement  of  power  by  distribution  licensee/GUVNL from wind energy sourse shall be undertaken on 'Ex‐Bus'  basis... 
However, in case the owner of a Wind Energy Generator opts for wheeling  power  for  own  use,  the  GETCO/  Distribution  Licensee  shall  transmit  the  power to the point of use. The transmitting this power to the point of use,  only GETCO will be entitled to charge 4% of energy injected (in kind) as all  inclusive Transmission/ wheeling charges" 

58.  Thus  State  Commission  adopted  wheeling  charges  as  specified  under  Wind  Power Policy 2002. These charges specified under State Commission's Order  no.  2  of  2006  would  remain  unchanged  until  State  Commission  by  another  Order  or  Regulations  modifies  them.  State  Government  has  no  power  to  disturb  tariff  or  transmission  charges  or  wheeling  charges  defined  by  State  Commission.  

59.  Government  of  Gujarat  replaced  Wind  Power  Policy  2002  by  Wind  Power  Policy 2007 on 13.6.2007. New Policy of 2007  also has provision of wheeling  charges as under 

5. Wheeling of Electricity:
    Page 30 of 37 
Appeal No. 52 0f 2010  The  wheeling  of  electricity  generated  from  the  WTGs,  to  the  desired  location/s within the State, shall be allowed at a wheeling charge of 4% of  the  energy  fed  to  the  grid,  as  per  Gujarat  Electricity  Regulatory  Commission (GERC) Order, as amended from time to time." 

60.  Thus, Government of Gujarat, in its Policy of 2007, recognized the power of  State  Commission  to  specify  the  wheeling  charges  by  stating  "shall  be  allowed  at  a  wheeling  charge  of  4%  of  the  energy  fed  to  the  grid,  as  per  Gujarat  Electricity  Regulatory  Commission  Order."  Government  of  Gujarat,  however, while amending the 2007 Policy in January 2009, made changes in  wheeling  charges  enhancing  them  substantially.  The  modified  clause  of  amendment to 2007 Policy read as under:   

"2. Amendment of Clause No. 5 - Wheeling of Electricity  The clause shall be substituted by the following:‐ 
(b) Wheeling  of  power  to  consumption  site  at  66  kV  voltage  level  and above:‐  The  wheeling  of  electricity  generated  from  the  Wind  Turbine  Generators  (WTGs) to the desired location(s) within the State, shall be allowed on the  payment  of  transmission  charges  and  transmission  losses  otherwise  applicable to normal Open Access Customers. 

.............................. 

Wind farm owner desiring to wheel electricity to more than two locations  shall  pay  5  paise  per  unit  on  energy  fed  in  the  grid  to  concerned      Page 31 of 37  Appeal No. 52 0f 2010  Distribution  Company  in  whose  area,  power  is  consumed  in  addition  to  above mentioned transmission charges and losses, as applicable."  

61.  Since  the  above  modification  in  wheeling  charges  were  made  without  the  approval  of  the  State  Commission  which  is  the  sole  authority  to  specify  wheeling charges in terms of 2003 Act.  The State Commission had taken up  the  issue  with  the  Gujrat  Urja  Vikas  Nigam    through  their  letter  No.  GERC/SE/2009  dated  23rd  January  2009,  in  which,  the    State  Commission  emphasized  that  as  per  Electricity  Act  2003,  only  State  Commission  has  got   powers  to  determine  tariff  including  Transmission  and  wheeling  charges.  Relevant portions of the said letter dated 23.1.2009 have been  reproduced  below: 

"The  Commission  is  considering  /  reviewing  the  policy  declared  by  the  Govt. on 7/1/2009. Under the Electricity Act 2003, determination of tariff  including transmission tariff/charges and wheeling charges etc. are to be  decided by the Commission. In the last para of your letter States that you  are issuing instructions to GETCO and DISCOMs to start wheeling charges  from  wind  turbine  generators  for  wheeling  of  electricity  (a)  to  consumption at 66 kV and above (b) to consumption site below 66 kV level  according  to  the  Government  Policy.  This  is  not  in  accordance  with  the  Order of the Commission as of date. 
All  Orders  and  regulations  issued  by  the  Commission  are  required  to  be  followed by the utilities/licensees till they are revised by the Commission"  
    Page 32 of 37 

Appeal No. 52 0f 2010 

62.  Further,  the  State  Commission  in  para  7.9  of  its  Order  dated  6.5.2009  have  observed that; 

"...it  may  be  noted  that  Commission  is  in  the  process  of  reviewing  its  existing  regulations  and  Order  on  renewable  energy.  As  part  of  this  process,  the  Commission  will  take  a  view  on  the  amendments  to  the  Wind Power Policy announced by the Government in January 2009." 

63.  From  the  above,    it  is  clear  that  so  far  levy  of  wheeling  charges  are  concerned,  the    amendment  to  Wind  Power  Policy  2007  issued  by  Government of Gujarat in January 2009 was without authority and were ultra  vires. In fact Government of Gujarat had also recognized the powers of State  Commission in Government Resolution dated 7.1.2009 as given below: 

"Notwithstanding anything contained in this resolution, the provisions  of  the  Electricity  Act  2003  and  the  GERC  regulations,  as  issued  from  time  to  time,  shall  prevail,  for  the  purpose  of  the  implementation  of  this policy." 

Thus  the  arrangement  of  wheeling  power  from  Appellant's  Wind  Energy  Generators as per amendment to 2007 Policy and Commission's Order dated  6.5.2009 were protem till Commission takes final decision in the Matter.  

64.   Thereupon,  the  State  Commission  had  notified  its  new  Regulation  on  Renewable Energy vide its Order no. 1 of 2010 dated 30.1.2010. In para 6.1 of  this  Order  Commission  has  dealt  with  Transmission  and  Wheeling  charges.  Relevant  portion  of  the  Commission's  Order  dated  31.1.2010  is  reproduced  below:   

    Page 33 of 37 
Appeal No. 52 0f 2010  " 6.1 Transmission and Wheeling charges  ... 
Commission's Ruling: 
The  Commission  had,  in  the  draft  Order,  proposed  lower  transmission/wheeling  charges  in  case  of  the  wind  energy  generators  opting  for  wheeling  of  power  for  own  use,  considering  the  lower  power  plant  load  factor  of  the  wind  energy  projects.    But,  as  suggested  by  GETCO, cost of transmission/distribution asserts created  for such projects  is required to be recovered through tariff.  The proposed charges do not  recover  fully  the  cost  of  transmission  and  distribution  assets.    After  considering the suggestions of the objectors and Govt. of Gujrat Amended  Wind Power Policy dated 13th January, 2009, the Commission decides the  transmission and wheeling charges applicable to the captive consumers as  under: 
(a) Wheeling  of  power  to  consumption  site  at  66  kV  voltage  level  and  above. 

The wheeling of electricity generated from the Wind Power Generators, to  the  desired  location(s)  within  the  State,  shall  be  allowed  on  payment  of  transmission  charges  and  transmission  losses  applicable  to  normal  Open  Access Consumer. 

(b) Wheeling of power to consumption site below 66 kV Voltage level. 

    Page 34 of 37 

Appeal No. 52 0f 2010 

(i) The wheeling of electricity generated from the Wind Power Generators, to  the  desired  location(s)  within  the  State,  shall  be  allowed  on  payment  of  transmission  charges,  applicable  to  normal  open  Access  Consumer  and  transmission  and  wheeling  losses  @  10%  of  the  energy  fed  to  the  grid.   The above loss is to be shared between the transmission and distribution  licensee in the ratio of 4:6.  This provision shall be applicable to the Wind  Energy  Generators  who  are  having  more  than  one  Wind  Energy  Generators. 

(ii) The  wheeling  of  electricity  generated  by  smaller  investors,  having  one  Wind  Energy  Generator  in  the  State,  to  the  desired  location(s),  shall  be  allowed  on  payment  of  transmission  charges,  applicable  to  normal  open  access  consumer,  and  transmission  and  wheeling  losses  @  7%  of  the  energy  fed  to  the  grid.    The  above  losses  are  to  be  shared  between  the  transmission and distribution licensee in the ratio of 4:3."    

65.  From  perusal  of  the  above  new  Regulations,    it  becomes  clear  that  State  Commission  had  adopted  the  provisions  of  amendment  to  2007  Policy  with  slight modification in relation to sharing of losses between transmission and  distribution  licensees.  These  Regulations  came  into  force  11th  August  2009.    Para 9 of the Regulations dealing with applicability is reproduced below: 

"9.  Applicability of the Order:
As  already  clarified  in  para  2.2.  above,  this  Order  shall  come  into  force  from 11th August, 2009.  The tariff fixed in the Order shall be applicable to  all  the  wind  energy  generators  commissioned  on  or  after  11th  August,      Page 35 of 37  Appeal No. 52 0f 2010  2009.  The existing contracts and agreements between the wind energy  generators  (Wind  Energy  Generators)  and  distribution  licensees  signed  upto 10th August will continue to remain in force as per the PPA signed  by the parties." (emphasis supplied) 

66.  As  per  above,  only  existing  PPAs  signed  between  energy  generators  and  distribution licensees would continue to remain in force. Wheeling charges as  determined  in  this  Order  would  be  applicable  on  Wind  Energy  Generators  commissioned  only  after  11th  August  2010.  Wind  Energy  Generators  commissioned and connected to grid prior to this date shall be governed by  Government  of  Gujarat's  Wind  Power  Policy  2007  and  State  Commission's  existing  Regulations  on  Renewable  Sources,    2006.    Undoubtedly  Wind  Energy  Generators  of  Appellant  were  commissioned  and  connected  to  grid  prior  to  11th  August  2009.  These  were  to  be  covered  under  State  Government's  Wind  Policy  2007  and  State  Commission's  earlier  regulations  and  accordingly Appellant  is  liable  to  pay  wheeling charges  at  4%  of  energy  injected (in kind) as all inclusive Transmission and wheeling charges. 

67.  Summary of our findings  I. There  was  no  restriction  on  number  of  captive  locations  per  Wind  Energy  Generator in Government of Gujarat's Wind Power Policy 2007. GETCO (R‐

2)  had  delayed  the  signing  of  wheeling  agreement  to  wheel  power  from  appellant's Wind Energy Generators to desired locations. 

II. Appellant's Wind Energy Generator's were commissioned and connected to  grid prior to 7.1.2009. 

    Page 36 of 37 

Appeal No. 52 0f 2010  III. In  view  of  intentional  delay  by  GETCO  to  wheeling  agreement,  Appellant  has  right  to  raise  the  issue  despite  his  conditional  acceptance  vide  letter  dated 12.3.2009. 

IV. State  Commission  ought  to  have  taken  into  account  the  Government  of  Gujarat's letter dated 6.11.2008 clarifying the number of captive  locations  and decided the case accordingly. 

V. After enactment of Electricity Act 2003, State Commission is sole authority  to  specify  wheeling  charges.  Government  of  Gujarat  had  no  power  to  change the wheeling charges specified by State Commission vide its Order  no  2  of  2006  dated  10.8.2006.  Enhancement  of  wheeling  charges  in  amendment  to  2007  Policy  vide  Government  Resolution  dated  7.1.2009  is  void abnitio. 

68.  The matter is disposed off accordingly. Appeal is allowed with no Orders as to  costs.  

69.  Pronounced in the open court today the 8th March, 2011    (V J Talwar)          (Justice M Karpaga Vinayagam)  Technical Member           Chairperson    INDEX : REPORTABLE/NON‐REPORTABLE  np        Page 37 of 37