Jharkhand High Court

Jagdish Prasad vs The Central Bureau Of Investigation A C B ... on 29 June, 2017

Author: Anant Bijay Singh

Bench: Anant Bijay Singh

                                         1

      IN THE HIGH COURT OF JHARKHAND AT RANCHI                      
                    A.B. A. No. 1057 of 2017     
Jagdish Prasad                              ...... Petitioner
                      Versus 
The C.B.I (A.C.B.) through Superintendent of Police,  Ranchi......         Opposite Party
                                 with
                       A.B. A. No. 1008 of 2017            
Sanjay Kumar Singh                                      ...... Petitioner
                         Versus 
The State of Jharkhand through C.B.I                            ...... Opposite Party
                              with
                    A.B. A. No. 1012 of 2017                 
Anil Kumar Singh                                                ...... Petitioner
                         Versus 
The State of Jharkhand through C.B.I                            ...... Opposite Party

                            ­­­­­­­­­
CORAM:  HON'BLE MR. JUSTICE ANANT BIJAY SINGH
                            ­­­­­­­­­
For the Petitioners: Mr. Abhishek Sinha, Advocate
                     Mr. Kumar Harsh, Advocate
                    (in A.B.A. No.1057 of 2017)
                    Mr. Rohit Ranjan Sinha, Advocate
                    Mr. Mohit Mani Kishore, Advocate
                    (in A.B.A. No. 1008 of 2017)
                    Mr. Indrajit Sinha, Advocate
                    (in A.B.A. No. 1012 of 2017)
For the C.B.I          : Mr. Kailash Prasad Deo, Advocate

C.A.V. On: 21/06/2017                            Pronounced on 29/06/2017


      Since all the three anticipatory bail applications arise out of one and the 

same case hence they are taken up together and disposed of by common order.

      The   petitioners   are   apprehending   their   arrest   in   connection   with   R.C­

11(A)/2014­R for the offence registered under sections 120B420468 and 471 

of the Indian Penal Code and under section 13(2) read with Section 13(1(d) of 

the Prevention of Corruption Act, 1988 pending in the court of Shri B.K. Tiwary, 

Special Judge, C.B. I(A.C.B), Ranchi. 

      The case of prospection, in short, is that one S.K. Khare, Superintendent of 

Police/HOB, C.B.I, AC.B, Ranchi got information from reliable source that one 

Shri Darlando Thanmi Khathing, the then Vice Chancellor, Central University of 

Jharkhand  (CUJ), Ranchi Jharkhand, Narendra Lal  Garg, OSD (Project, Central 

University of Jharkhand, Ranchi, Sanjay Kumar Singh, the then Civil Engineer, 
                                               2

Central     University   of   Jharkhand,   Ranchi,   Abhay   Nindkan   Tigga,   then   then 

Electrical   Engineer,   Central   University   of   Jharkhand,   Ranchi     entered   into   a 

criminal conspiracy with the proprietors/Directors/ Partners of 12 private firms, 

viz, M/s Rock Drill India, Ranchi, M/s Sadanand Gupta, Ranchi, M/s Park Sarva 

Mangala   Project,  Ranchi,  M/s  J.C.  Enterprises,  Ranchi,  M/s  Raj   construction, 

Garhwa, M/s Mourya Heritage Inn Pvt. Ltd, Ranchi and others during the period 

2010 to 2014 and committed the offences of cheating and criminal misconduct 

and in pursuance thereof, cheated the Central University of Jharkhand, Ranchi 

by causing to it a wrongful loss of Rs. 7,11,89,770/­(approx) and corresponding 

wrongful gain to themselves, in the matter of award of construction works of 

different buildings for the permanent campus of Central University of Jharkhand 

by abusing their  official position and awarding the works at  exorbitant rates to 

the said firms. It is further alleged that  the above mentioned public servants of 

Central University of Jharkhand entered into conspiracy with 12 firms awarded 

the work of construction of different   buildings to the said firms at exorbitant 

rats and fraudulently  made payment of Rs. 93,94,77,420/­ to them and cheated 

the Central University of Jharkhand to the tune of Rs. 7,11,89,776/­ as a result 

of   fraudulent   payment   made   to   those   firms.   Thus,   Central   University   of 

Jharkhand,   Ranchi   was   put   to   a   wrongful   loss   of   Rs.   7,11,89,776/­   and 

corresponding wrongful gain was made by the   accused firms. On the basis of 

these allegations, the instant case has been lodged.

       A.B.A. No. 1057 of 2017

       Learned counsel  appearing on behalf of the petitioner­Jagdish Prasad has 

submitted that  the Bharat Dirlling & Foundation Treatment Pvt. Ltd is a Private 

Ltd.   Company   and   registered   under   the   Companies   Act,   1856   in   which   the 

petitioner   is   one   of   the   Director   of   the   said   company.     Further,   it   has   been 

submitted   that   C.B.I  after   completion   of   investigation   submitted   charge­sheet 
                                              3

vide Charge­sheet No. 13/16 dated 30.11.2016. It has also been submitted that 

it was specifically mentioned in the said notice inviting tender that there is four 

categories for  empanelment which are as follows:

Sl. No.       Group                 Nature of work        Estimated Value E.M
1             A                     Civil/Internal  Above 25 Crores 5 lacs
                                    Electrification/
                                    H.A.V.C/Service
                                    s
2             B                     Civil/Internal  10 Crores to 25  3.5 Lacs
                                    Electrification/ crores
                                    H.A.V.C/Service
                                    s
3             C                     Civil/Internal  5 Crores to 10             2.5 Lacs
                                    Electrification/ Crores
                                    H.A.V.C/Service
                                    s
4             D                     Civil/Internal  3 Crores to 5              1 Lac
                                    Electrification/ Crores
                                    H.A.V.C/Service
                                    s  


It   has   also   been   submitted   that   as   per   the   said   notice   inviting   tender,   the 

petitioner's company had applied for empanelment in Group­C vide his letter 

dated 15.11.2011 and also deposited the Earnest money through demand draft 

being   No.   955305   dated   15.11.2011   in   favour   of   Central   University   of 

Jharkhand.   It   is   further   submitted   that   as     per   the   direction   of   the   Central 

University   of   Jharkhand   vide   his   letter   dated   21.01.2012,   the   petitioner's 

company submitted its  quotation i.e. Annexure 1, as per the rate based on DSR 

2007 for civil and electrical and the said company had quoted 58% above of the 

DSR ,2007. The learned counsel for the petitioner referred to Annexure 9 and 

9/1 and has submitted that after negotiation, the petitioner's company did the 

construction   work   54%   above   of   DSR,   2007   but   at   the   relevant   time, 

Government of India issued the office memorandum dated 28.12.2011 to which 

the Government has approved rate for Ranchi is 158 ie. Above 58% of the DSR 

2007 as well as during the period of contract agreement, the Government of 
                                              4

India, vide its letter dated 03.07.2012 issued fresh guideline and hike in the 

construction rate i.e. 174 above of DSR ­2007. It is further submitted that after 

negotiation vide letter dated 12.03.2013, the Central University of Jharkhand 

has sent offer to the petitioner's company to do a work under the Group­C at the 

rate of 54% above over DSR 2007 for civil and internal electrification works duly 

approved by the competent authority. Further, it has been submitted that as per 

the allegation made against him that due to the act of the petitioner, the Central 

University of Jharkhand has suffered wrongful loss of Rs. 43,52,503/­ but as a 

matter   of   fact,   the   Central   University   of   Jharkhand   is   a   defaulter   of   the 

petitioner for not paying the lawful claim of the petitioner for the construction 

work   done   by   him   for   an   amount   of   Rs.   11,24,93,106/­   as   such   due   to   the 

meanness of  the  Central  University of  Jharkhand,  the  petitioner   has suffered 

heavy loss.  A supplementary affidavit has been filed on behalf of the petitioner 

bringing on record the final form.  It is further submitted that investigation in 

this case is complete and final form has been submitted, the petitioner has never 

been arrested during investigation and cooperated with the investigation and 

Trial  will  take  some  time. Considering all  these facts, the  petitioner deserves 

privilege of anticipatory bail.

        On  the   other   hand  learned   standing   counsel   for   the   C.B.I   opposed   the 

prayer for anticipatory bail and filed counter­affidavit. Referring to para 14 & 15 

of   the   counter­affidavit,   learned     standing   counsel   has   submitted   that   under 

Group­C, M/s Raj Construction, M/S Mourya Heritage, M/S J.C. Enterprises and 

M/s Bharat Drilling & Foundation Treatment Pvt. Ltd wer L­1 after post tender 

negotiation who quoted 54% above DSR­2007. Further, it has been submitted 

that under Group­D, M/s B.P. Construction was L­1 who quoted 49% DSR 2007. 

So, considering the aforesaid facts, the petitioner does not deserve anticipatory 

bail.
                                              5

A.B.A. No. 1008 of 2017

       Learned   counsel     appearing   on   behalf   of   the   petitioner   ­Sanjay   Kumar 

Singh has submitted that at the relevant time the petitioner was posted as Civil 

Engineer, C.U and now he has been retired. Further, it has been submitted that 

the   petitioner   has   got   his   family   and   property   within   the   jurisdiction   of   the 

Hon'ble   Court.   Further,   it   has   been   submitted   that   allegation   against   the 

petitioner is that he participated in preparation of the comparative chart for the 

empanelment   of   contractors   and   he   prepared   the   measurement   books   and 

countersigned the bills, so far as the first allegation is concerned,  the same was 

only a ministerial act on part of the petitioner and his role was only to prepare a 

chart based upon the date available from the records of the so­called tender. 

The allegation of conspiracy behind the petitioner so doing his task is baseless 

and without any material, secondly this allegation would equally apply upon 

Shri   A.N.   Tigga,   the   then   Electrical   Engineer,   C.U..   So   far   as   the   second 

allegation   is   concerned,   namely   preparation   of   measurement   book   and 

countersigning the bills, it is patently erroneous to fasten any criminality upon 

the petitioner. Further, it has been submitted that the petitioner should not be 

treated as public servant. There is no allegation against the petitioner having 

made any misrepresentation so as to constitutie deception within the meaning of 

Section 420 I.P.C. There is no allegation of dishonestly or fraudulently including 

anyone.  It is further submitted that investigation in this case is complete and 

final form has been submitted, the petitioner has never been arrested during 

investigation   and   Trial   will   take   some   time.   Considering   all   these   facts,   the 

petitioner deserves privilege of anticipatory bail.

       On the other hand, learned   standing counsel for the C.B.I opposes the 

prayer   for   anticipatory   bail   and     filed   counter­affidavit   and   referring   to   the 

various paras of the counter­affidavit, counsel for the C.B.I has submitted that 
                                             6

the   petitioner   is   signatory   to   the   comparative   chart   prepared   by   for 

empanelment of Group A contractors in which CP.WD was deliberately excluded 

on the false ground that it charges 27.5% of the capital value of the work as 

agency charge because of which the cost of the project would increase by 25% 

and further CU would have no role to play. So, considering the aforesaid facts, 

the petitioner does not deserve the privilege of anticipatory bail.

A.B.A. NO. 1012 of 2017

       Learned counsel  appearing on behalf of the petitioner ­Anil Kumar Singh 

has submitted that   the petitioner has been falsely implicated in this case. The 

petitioner   was   served   with   a   notice   on   23.09.2015   to   appears   before   the 

Investigating   Authority,   after   receiving   notice,   the   petitioner   appeared   at   the 

office   of   the   Superintendent   of   Police,   C.B.I   Ranchi   on   25.09.2015   and   fully 

cooperated with the Investigating Officer. it has been submitted that C.B.I after 

completion of investigation submitted charge­sheet. It has also been submitted 

that as per the notice inviting tender specifically mentions that   there is four 

categories for empanelment of contractor/builder which are as follows:

Sl. No.       Group                Nature of work       Estimated Value E.M
1             A                    Civil/Internal  Above 25 Crores 5 lacs
                                   Electrification/
                                   H.A.V.C/Service
                                   s
2             B                    Civil/Internal  10 Crores to 25  3.5 Lacs
                                   Electrification/ crores
                                   H.A.V.C/Service
                                   s
3             C                    Civil/Internal  5 Crores to 10            2.5 Lacs
                                   Electrification/ Crores
                                   H.A.V.C/Service
                                   s
4             D                    Civil/Internal  3 Crores to 5             1 Lac
                                   Electrification/ Crores
                                   H.A.V.C/Service
                                   s  


 The learned counsel for the petitioner has submitted that after negotiation vide 
                                              7

letter dated 07.02.2012, the Central University of Jharkhand has sent offer to 

the petitioner's firm to do a work under the Group 'C' at the rate of 54% above 

over DSR 2007 for civil and internal electrification works duly approved by the 

competent   authority   of   such   work.   Further,   it   has   been   submitted   that   on 

22.11.2013

 a certificate was given by Central University of Jharkhand wherein it  was certified that work done by M/s Raj Construction was found satisfactory and  about 70% work was found to be completed and further it was observed that the  remaining   work   is   under   progress.    Further,  it   has   been   submitted   that     the  petitioner's company has sent letter dated 30.11/2014 to the Vice­Chancellor,  Central   University   of   Jharkhand   for   payment   of   5th   R/A   (Pre­final)   bill  amounting to Rs. 2.75, but the same has not been paid by the said University till  date.  It has also been submitted that after negotiation, the petitioner's firm did  the   construction   work   54%   above   of   DSR   2007,   but   at   that   relevant     time,  Government of India issued the office memorandum dated 28.12.2011 in which  the Government has approved rate for Ranchi is 158 ie above 58% of the PAR of   DSR 2007.  It has also been submitted that as per allegation,  the petitioner has  obtained   the   work   5%   above   of   the   L1   rate,   as   such,   Central   University   of  Jharkhand has suffered wronglful loss of Rs. 17,09,155/­. As a matter of fact,  contractor of Group 'D' has given a negotiated rate of 49% above of DSR 2007  and the  contractors of  Group  'D' are  empowered to do a  work from RS. 3­5  crore, but the petitioner's company has been empanelled under Group C and he  is empowered to do a construction work from Rs. 5­10 crore.   Both categories  are different and work was also to be done on different design and drawing. So,  it cannot be said that both the categories were having the same work to be done.  It is also implied by the Notice Inviting Tender that Group "C' has to do work  upto Rs. 5­10 crore and Group 'D' has to do work from R. 3­5 crore. It is further  submitted that investigation in this case is complete and final form has been  8 submitted, cognizance has been taken, the petitioner has never been arrested  during investigation and Trial will take some time. Considering all these facts,  the petitioner deserves privilege of anticipatory bail.

On  the   other   hand  learned   standing   counsel   for   the   C.B.I   opposed   the  prayer for anticipatory bail and filed counter­affidavit. Referring to various paras  of   the   counter­affidavit   affidavit,   learned   standing   counsel   for   the   C.B.I   has  submitted that the petitioner does not deserve privilege of anticipatory bail.

Having heard the learned counsel for the parties and after going through  the records, final form, material collected by the C.B.I against the petitioners  and also the fact that final form has been submitted in this case, cognizance has  been taken, trial will take some time, during investigation these petitioners co­ operated  in   the  investigation  and   they   were   never  arrested   by   the  I.O,  I   am  inclined to admit the petitioners on anticipatory bail. Accordingly, they above  named   petitioners   are   directed   to   surrender   in   the   Court   below   within   four  weeks from the date of this order and in the event of their arrest or surrender  the Court below shall enlarge the above named petitioners on bail on furnishing  bail bond of Rs. 15,000/­ (Rupees fifteen thousand)each, with two sureties of  the like amount each to the satisfaction of the court of Sri B.K. Tiwary, learned  Special   Judge,   C.B.I   (A.C.B.),   Ranchi   in   connection   with   R.C­11(A)/2014­R,  subject to conditions as laid down under Section 438(2) of the Cr.P.C and also  subject to further condition  that one of the  bailors must be local  resident of  Ranchi district. Petitioners shall fully cooperate with the CBI and also appear  physically on each and every date before the trial court till framing of charge. If  they want exemption from appearance, they will inform the CBI in advance and  after taking necessary permission from Trial Court, they may be exempted from  personal appearance. The petitioners shall not try to influence the prosecution  witnesses   during   trial.   The   petitioners   shall   deposit   their   pass   port   (if   any)  9 before the trial court.

Let a copy of this order be communicated to the concerned trial court and  a copy of this order be handed over to the learned standing counsel for the C.B.I.                            (Anant Bijay Singh, J.) Satyarthi/­