Section 5(6) in Bihar Electricity Regulatory Commission (Levy and Collection of Fees and Charges by SLDC) Regulations, 2006

(6)Disputes arising out of billing of SLDC Charges shall be, as far as possible, settled by mutual negotiations. If the disputes are not resolved through mutual negotiations within ninety (90) days, the matter shall be referred to the Commission through a petition by either of the parties. The decision of the Commission shall be binding on both the parties.