Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

Delhi District Court

M/S. Aadhar Stumbh vs National Building Construction ... on 21 August, 2018

      IN THE COURT OF MS. SHUNALI GUPTA, ADJ­06, SOUTH DISTRICT,
                  SAKET COURT COMPLEX, NEW DELHI


CS No.: 121/18
CSDJ No.207222/16
CNR No. DLST01­000343­2012

In the matter of:

M/s. Aadhar Stumbh
IInd Floor, Plot No.2, Anand Plaza,
Local Shopping Centre,
Sainik Vihar, Pitampura,
New Delhi­110034.
                                                                                .......Plaintiff

                                                     Versus

National Building Construction Corporation Ltd.
Integrated Office Complex,
Lodhi Road, New Delhi­110003.
                                                                            .......Defendant
 
Date of Institution                                           :    31.08.2012
Date reserved for judgment                                    :    20.08.2018
Date of pronouncement of judgment                             :    21.08.2018

                             Suit for Recovery of Rs.19,99,999/­.

J U D G M E N T: 

1.

  The brief facts of the case as culled out from the pleadings of the parties are summarized as under: 

1.1 Plaintiff company registered under the Companies Act, 1956 is engaged in   the   business   of   civil   consultancy,   engineering   and   building construction work. The suit has been filed by Sh. Amit Mittal - one of the CS DJ No.7222/16     Page No.1/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

Principal officers of the company and duly authorized in this regard vide Board Resolution dated 21.07.2012 passed by the Board of the Directors of the plaintiff company.

1.2 Defendant Corporation is engaged in civil construction and consultancy services   and   also   undertakes   construction   work   for   and   on   behalf   of various   Central   and   State   Agencies.   The   defendant   Corporation   also sub­contracts various civil and construction work to the contractors for and on behalf of its clients.

1.3 It   is   stated   that   the   plaintiff   company   was   awarded   the   work   of construction, retrofitting and renovation works at MRD Pavilion, Pragati Maidan, New Delhi by the defendant vide letter dated 29.06.2007. The stipulated  date   of commencement of  work  as  per the   agreement  was 09.07.2007 and the stipulated date of completion was 15.02.2008. As per   the   letter,   the   sum   contracted   for   the   work   was   Rs.3,64,93,526/­. However,   due   to   delays   attributable   to   the   defendant,   instead   of 15.02.2008   the   work   was   completed   on   01.03.2008   after   which   the physical possession of the constructed building was taken over by the MRD.

1.4 The   defendant,   without   any   notice   to   the   plaintiff,   made   number   of deductions   from   running   account   and   final   bill   prepared   by   the department, details whereof are as under:­ CS DJ No.7222/16     Page No.2/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

(i)  Claim   No.1:   As   per   Clause   4.2.4,   the   letter   of   Intent   envisaged deduction of DVAT @3% from the plaintiff's running account bills and final   bill.   The   department  has  withheld   additional   DVAT  @2%   without any  reason,  authority  and   right  from  running   account  bills  detailed   as under:
From 4th running Account Bill : Rs.3,23,874/­ From 5th and pre­final Bill : Rs.1,58,390/­ ­­­­­­­­­­­­­­­­­­­   Rs.4,82,264/­ ­­­­­­­­­­­­­­­­­­­
(ii)  Claim   No.2:   The   department   has   deducted/withheld   the   following amounts, as mentioned below, under the 'Miscellaneous' head:
         From 1st running Account Bill               : Rs.     9,950/­
         From 2nd running Account Bill               : Rs.     5,500/­
         From 3rd running Account Bill               : Rs.   31,328/­
         From 4th running Account Bill               : Rs.   37,080/­
         From 5th running Account Bill               : Rs.   19,016/­
         From 6th and final Bill                     : Rs.   66,370/­
                                                     ­­­­­­­­­­­­­­­­­­­
                                                       Rs.1,69,244/­
                                                     ­­­­­­­­­­­­­­­­­­­

(iii)  Claim   No.3  :   The   department   had   deducted/withheld   a   sum   of Rs.70,000/­  from  1st  running  account   bill   on  account   of  submission   of material testing, etc.
(iv) Claim No.4 : The work was completed by the plaintiff on 01.03.2008.

As   such,   the   defect   liability   period   expired   on   14.05.2008   and immediately thereafter, the plaintiff was entitled to the refund of the entire Security   Deposit   as   per   clause   74   of   the   Agreement.   However,   the defendant has not refunded the same and the plaintiff is entitled to the said amount.

CS DJ No.7222/16     Page No.3/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

(v) Claim No.5 : There are part payments amounting to Rs.11,50,000/­, to   be   released   to   the   plaintiff   by   the   department,   from   the   final   bill measured and prepared by the department.

Thus,   a   total   amount   of   Rs.24,06,787/­   is   due   and   payable   by   the defendant   which   includes   Rs.18,01,488/­   on   account   of   the   aforesaid claims and Rs.6,05,299/­ on account of interest accrued thereon @12% per annum from the date of expiry of the defect liability period till the date of the filing of the suit i.e. till 31.08.2012. 

1.5 Since   the   defendant   failed   to   pay   the   said   amount   despite   repeated requests   and   reminders,   a   legal   notice   dated   05.07.2011   was   served upon   the   defendant   calling   upon  the   defendant   company  to   remit   the aforesaid   amount.   Despite   service   of   the   legal   notice,   the   defendant failed to release the payment. Hence,  the present suit. However, to bring the suit within the jurisdiction of this court, only a sum of Rs.19,99,999/­ along with pendentelite and future interest @12% per annum has been claimed.

2. Written   statement   has   been   filed   by   the   defendant   denying   the   claim made by the plaintiff. It is stated that the deductions of various amounts have been done by the defendant as per the terms & conditions of the contract and for which the plaintiff had given his consent at the time of entering   into   the   agreement.   The   running   bills   and   final   bills   were prepared, measured and submitted by the plaintiff itself and the plaintiff CS DJ No.7222/16     Page No.4/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

has accepted the final bill vide their letter dated 10.08.2009. Hence, the claim made by the plaintiff does not exist.

As regards claim no.1  i.e. deduction of money on account of DVAT is concerned,   it   is   stated   that   as   per   clause   4.2.4   of   the   contract,   the plaintiff was required to be registered under the composite scheme but the   plaintiff   failed   to   submit   the   documentary   evidence   on   time   and therefore,   necessary   deductions   have   been   made   from   the   plaintiff's running bills.

As regards claim no.2, the justification for deductions made in the bill, is mentioned herein below:

(a) 1st RA Bill Rs.9,950.00 Mobile   Phone   charges,   Computer repair,   purchase   of   diesel   for   vehicle provided by contractor
(b) 2nd RA Bill Rs.5,500.00 Salary of Driver
(c) 3rd RA Bill Rs.31,328.00 Salary of Driver, Hire charges of SCV
(d) 4th RA Bill Rs.37,030.00 Printing   &   Stationery,   Mobile   phone charges, Diesel for Vehicle
(e) 5th RA Bill Rs.19,016.00 Printing   &   Stationery,   Mobile   Phone charges, Computer Operator Salary
(f) 6th & Final RA Bill Rs.66,730.00 Printing   &   Stationery,   Electricity   bill charges As regards claim no.3, it is stated that the amount of Rs.70,000/­ was withheld for testing charges of building materials from 1 st RA Bill and the same   has   already   been   released   to   the   plaintiff   which   fact   has   been concealed by the plaintiff.

As regards claim no.4, it is stated that upon request of the plaintiff, the CS DJ No.7222/16     Page No.5/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

security deposit was immediately released to the plaintiff on 06.07.2010 which fact has not been correctly stated by the plaintiff. However, a sum of Rs.4,60,000/­ has been withheld from the security deposit on account of settlement of water charges vide GCC clause no.44 as the water for the   construction   purpose   was   used   by   the   plaintiff   from   the   water connection of ITPO, Pragati Maidan, New Delhi and the plaintiff is legally bound to pay the water charges as per the claim made by the ITPO, New Delhi.

Finally,  with regard to claim no.5, it is stated that the part­payment of Rs.11,50,000/­ as averred by the plaintiff, is not due as the plaintiff had accepted full & final payment from the defendant, receipt whereof is lying with the defendant.

2.1 Regarding the legal notice, it is stated that reply to the legal notice was sent to the plaintiff wherein proper explanation was given and which was accepted by the plaintiff as full & final settlement. Rest all the contrary averments made in the plaint have been denied and dismissal of the suit has been sought.

3. Replication has been filed by the plaintiff reiterating the averments made in   the   plaint   and   denying   the  contrary  averments   made   in  the   written statement filed by the defendant.

4. Upon completion of the pleadings, on 17.03.2015 the following issues CS DJ No.7222/16     Page No.6/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

were framed:

1. Whether   the   plaintiff   has   filed   the   present   suit   without   any cause of action as alleged in preliminary objection no.1 in the WS? OPD
2. Whether the plaintiff is entitled to suit amount as claimed for?
OPP
3. Whether the plaintiff is entitled to interest, if so, at what rate and for which period? OPP
4. Relief.
5. In support of its case, the plaintiff has examined only  one witness  i.e. PW­1   Sh.   Amit   Mittal   -   Authorized   Representative   of   plaintiff company. In lieu of his examination­in­chief he has deposed by way of affidavit  Ex.PW1/A, wherein he has reiterated the  case set forth in the plaint and has relied upon the following documents:
i. Ex.PW1/1 - Certified copy of Board Resolution dated 21.07.2012. ii. Ex.PW1/2   (OSR)  -   Copy   of   Memorandum   and   Articles   of Association.
iii. Ex.PW1/4 (Colly) - Copy of letter dated 29.06.2007. iv. Ex.PW1/5 - Copy of letter dated 17.12.2008. v. Ex.PW1/6 - Copy of letter dated 28.02.2008. vi. Ex.PW1/7 - Copy of letter dated 10.08.2009. vii. Ex.PW1/8 - Copy of letter dated 19.05.2011. viii. Ex.PW1/9 - Copy of legal notice.
6. In defence evidence, the defendant has examined only one witness i.e. CS DJ No.7222/16     Page No.7/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

DW­1 Sh. Jagmohan Singh - Additional General Manager (Engg.) in defendant company. In lieu of his examination­in­chief he has deposed by way of affidavit  Ex.DW1/A, wherein he has reiterated the  case set forth in the plaint.

Both PW­1 and DW­1 were duly cross­examined by the opposite side.

7. Final arguments addressed by Ld. Counsel Sh. Amit Punj for the plaintiff and Ld. Counsel Sh. Kundan Kumar for the defendant have been heard. Record has been carefully perused.

8. Discussion on Issues:

ISSUE No.1  : Whether the plaintiff has filed the present suit without any cause of action as alleged in preliminary objection no.1 in the WS?
and ISSUE No.2  :  Whether the plaintiff is entitled to suit amount as claimed for?
and ISSUE No.3 : Whether the plaintiff is entitled to interest, if so, at what rate and for which period?

9. All the issues are taken up together as they are connected, based on the same evidence and hence, a common discussion shall suffice. 9.1 In brief, the case of the plaintiff is that their company was awarded the tender   for   construction,   retrofitting,   etc.   of   MRD   Pavilion   at   Pragati Maidan and terms whereof were contained in the Letter of Intent dated 29.06.2007  Ex.PW1/4.   The   work   was   duly   completed   on   01.03.2008 CS DJ No.7222/16     Page No.8/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

pursuant   whereto   the   physical   possession   of   the   constructed   building was taken over by MRD. However, the defendant did not clear in totality the bills raised by the plaintiff company towards the work done. In fact, certain illegal deductions were made and certain amounts from the said bills were withheld by the defendant details whereof have already been specified   in   the   plaint.   Hence,   withholding   of   the   said   amount   and deductions made being illegal - defendant is bound to release the entire payment.

9.2 On   the   other   hand,   the   case   of   the   defendant   is   that   the   deductions made by the company from the bills, were on account of DVAT as the plaintiff   company   had   failed   to   submit   the   documentary   evidence regarding registration under the composite scheme. Further, as regards the   withholding   of   the   amount   from   the   security   deposit,   the   same   is stated to be on account of settlement of water charges which the plaintiff is legally bound to pay to the ITPO as per the claim made by them. It has been   submitted   by   Ld.   Counsel   for   the   defendant   that   they   have   no objection in releasing the amount of the final bill if the plaintiff company approaches them and settles the dispute with regard to the electricity and water charges.

9.3 Thus,   precisely   the   claims   of   the   plaintiff   company   can   be   broadly categorized under two heads:­ CS DJ No.7222/16     Page No.9/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

(i) on account of illegal deductions made from the bills

(ii) on account of amount withheld from the final bill and security deposit. 9.4 Now, at the outset, I may note that the defendant in its written statement has stated that the plaintiff had accepted the final bill vide their letter dated 10.08.2009. The said letter is an admitted one as it has been filed by the plaintiff and has been proved on record by them as  Ex.PW1/7. Thus,   before   adverting   further,   it   becomes   imperative   to   consider   the said letter. For clarity on further discussion, the contents of the said letter are extracted and reproduced hereunder:

".....We hereby certify and undertake that  there are no  dues, disputes or  payments pending with NBCC for above cited work other   than   the   final   bill   gross   amount   of   Rs.97,237.00.   The gross value of the work done is Rs.2,44,57,023.00. The over all measurements and amounts upto the final bill of above cited work have been accepted by us full and final. We also certify and undertake that we shall not have any claim against above cited work from NBCC or Owner. We also certify and undertake that we have no dispute with any of   our   vendors   or   labour/petty   contractor   and   statutory departments.
We are certifying and undertaking above without any duress....."

(underlining mine) 9.5 Now, admittedly the plaintiff had concluded the work on 01.03.2008. The running bills obviously must have been raised during the continuance of the   work   and   the   final   bill   would   have   been   raised   at   the   time   of CS DJ No.7222/16     Page No.10/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

conclusion of the work or immediately thereafter. This letter  Ex.PW1/7 (reproduced hereinabove) was written by the plaintiff on 10.08.2009 i.e. after more than a year from the date of completion of work and raising the bills. Thus, had there been any grievance of the plaintiff regarding deductions made from the bills under any head/ expense/ tax(s), etc., the same would have been raised by the plaintiff in the said letter. In fact, vide the said letter, the acceptance by the plaintiff of the measurements and amounts upto the final bill as full & final, by itself rules out any such plea which the plaintiff is now harping upon or agitating in the plaint. 9.6 Also   the   argument   now   sought   to   be   raised   that   the   said   letter   was written under pressure, has no weight or substance at all as firstly the plaintiff in the said letter has categorically stated that the undertaking is without any duress and secondly and more importantly, till the time of evidence, it has never been the case of the plaintiff that the said letter was written under duress. Even in the legal notice given by the plaintiff to the defendant with respect to the claim for money  Ex.PW1/9, which is dated 05.07.2011 i.e. written almost two years after the letter Ex.PW1/7 or in the plaint, it is nowhere even whispered that the letter  Ex.PW1/7 was got written forcibly and under duress. Thus, I can certainly say that this argument is absolutely a bald & a superfluous argument taken at the stage   of   evidence   in   order   to   wriggle   out   of   the   undertaking   and CS DJ No.7222/16     Page No.11/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

certification given by the plaintiff through the letter Ex.PW1/7. 9.7 Thus, in so far as the claims with regard to the deductions made from the bills, in view of the undertaking given in letter Ex.PW1/7, the said claims no more exist.

9.8 Delving further with regard to the amount withheld from the final amount and the security deposit, admittedly the amount of Rs.97,237/­ is still due from the final bill. The same is clearly stated in letter  Ex.PW1/7. Also, DW­1  during   cross­examination   has   categorically   admitted   that   the defendant has withheld the said sum from the final bill on account of non­ settlement of water and electricity charges.

9.9 Further,   regarding   security   deposit   there   is   a   clear   admission   in   the written statement that a sum of Rs.4,60,000/­ has been withheld by them from the security deposit for the settlement of water charges as the water for  the   construction   purpose   was   used   by  the   plaintiff   from  the   water connection of ITPO, Pragati Maidan and the plaintiff is legally duty bound to pay the water charges as per the claims made by the ITPO. DW­1 was also  cross­examined  on  this  aspect wherein  he  has admitted  that the defendant has not released the complete security deposit to the plaintiff. DW­1  further   deposed   that   the   defendant   had   received   a   letter   from ITPO, Pragati Maidan to the effect that the plaintiff has not deposited the electricity   &   water   charges   and   in   this   regard   some   amount   was CS DJ No.7222/16     Page No.12/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.

deducted by ITPO from NBCC/defendant. On being cross­examined with regard to there being any document on record issued by ITPO to NBCC, DW­1  deposed that there is no document on record showing that any letter   was   issued   by   ITPO   to   NBCC   or   deducting   any   amount   from NBCC. Though the work pertained to year 2008, not even a single letter has been filed on record till date by the defendant to show any demand having been raised by the ITPO on account of alleged water or electricity consumption by the plaintiff during the construction work nor there is any letter/communication by the defendant to the plaintiff claiming/fixing upon them   any   liability   for   the   amount   due   towards   the   water   or   electricity charges.   Thus,   there   is   nothing   on   record,   whatsoever,   to   show   that ITPO   had   ever   raised   any   demand   from   the   defendant   for electricity/water charges on account of construction work. 9.10 That   being   so,   the   defendant   has   failed   to   show   the   reason   for withholding the said amount from the security deposit till date. Thus, the said amount being arbitrarily withheld from the bills raised by the plaintiff towards the work executed by their company - the defendant is clearly under liability to pay the same.

Issues accordingly are decided in favour of the plaintiff.

10. Relief:

In view of my discussion on aforesaid issues, the suit of the plaintiff is CS DJ No.7222/16     Page No.13/ 14 M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.
decreed in the following terms:­
(i)  the defendant is liable to pay to the plaintiff cumulatively a sum of Rs.5,57,237/­   which   consists   of   Rs.97,237/­   towards   the   final   bill   and Rs.4,60,000/­ towards the security deposit.
(ii) Further, plaintiff is also held entitled to interest @10% per annum on the amount of Rs.5,57,237/­ from the date of filing of the suit till its recovery.
(iii) Costs of the suit is also awarded.
Decree sheet be prepared accordingly and  file be consigned to Record Room after necessary compliance.
Announced in the Open Court                                                 (Shunali Gupta)
Dated: 21.08.2018                                                   Addl. District Judge­(06)
                                                Digitally signed
                                                by SHUNALI
                                                                   South Distt. Saket Courts,
                                SHUNALI         GUPTA                          New Delhi.
                                                Date:
                                GUPTA           2018.08.21
                                                16:06:16
                                                +0530




CS DJ No.7222/16                                                                         Page No.14/ 14
M/s. Aadhar Stumbh Township Pvt. Ltd. v. NBCC Ltd.