Section 24(2)(iii) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
(iii)additional RoE of 0.50% may be allowed if any element of the transmission project is completed within the specified timeline and it is certified by the Regional Power Committee/National Power Committee that commissioning of the particular element will benefit the system operation in the regional/national grid: