Section 31 in Kolkata Municipal Corporation Building Rules, 2009

31. Delay in issue of Completion Certificate.

(1)In case where within a period of thirty days of the receipt of the notice of completion, duly completed in all respects, the Municipal Commissioner fails to issue a Completion Certificate or communicate his refusal, the applicant may in accordance with the provisions of section 403 make a representation in writing to the Mayor.
(2)The Mayor shall, after such enquiry as he may think fit, and after giving the applicant an opportunity of being heard, direct the Municipal Commissioner to issue the certificate or communicate refusal of the same to the applicant within a period of thirty days from the date of receipt of the representation to the Mayor.