Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 0]

Jharkhand High Court

Amrit Coal Carriers Through Its Partner ... vs Eastern Coalfields Limited Through Its ... on 28 November, 2014

Author: D.N. Patel

Bench: D.N. Patel

    IN THE HIGH COURT OF JHARKHAND AT RANCHI
          Arbitration Application No. 12 of 2013
                             ­­­­­
    Amrit Coal Carriers             ....  ......    Applicant  
                       Versus
    Eastern Coalfields Limited & others .....  ...  Respondents   
                       ­­­­­
    CORAM:  HON'BLE MR. JUSTICE D.N. PATEL    
  For the Applicant     : M/s Amit Kumar Das, Arbind Kumar, Advocates
  For the Respondents: Mr. Rajesh Lala, Advocate    
                                       ­­­­­­­­­
  09/Dated: 28th November, 2014

1. Counsel for the applicant submitted that an agreement was entered into  between the parties on 05.07.2007 for transportation of coal which is to be  supplied by Eastern Coalfields Limited. Without making coal available it was  expected by the Eastern Coalfields Limited that this applicant should lift certain  minimum   quantity   of   coal   and   therefore,   penalty   was   imposed   upon   the  Eastern Coalfields Limited and sizeable amount has been deducted from the  amount   legally   payable   to   the   applicant.   This   is   an   illegal   deduction   by  respondent no.1. Huge amount has been deducted by respondent no.1 which is  to be returned to this applicant because unless the coal is available there is no  question   of   transportation   of   the   same   whatsoever   arises.   For   this   dispute  which has been arisen a letter was written to the Engineer­Incharge by this  applicant   dated   6th   July,   2011   and   reminder   was   also   given   to   the   said  authority again on 27th May, 2013 and instead of denying any other things on  merits   the   answer   was   given   by   respondent   no.1   whereas,   the   request   was  made by the applicant to refer the matter to an Arbitrator. No reply has been  given by respondent no.1 that there is no existence of the arbitration clause.  Further counsel for the applicant is relying upon clause 12 of the agreement  dated 5th July, 2007 especially General Terms and Conditions (G.T.C,.) which  is annexed with Section­1 Instructions to Bidders, which is Annexure­1 to the  memo of this application. 

2. Counsel for the  applicant is also relied upon  the  guidelines especially  clause­2, which are issued in the form of Office Memorandum dated 14th May,  2008   issued   by   the   Government   of   India,   Ministry   of   Heavy   Industries   and  Public Enterprises, Department of Public Enterprises, which are at Annexure­3  to   the   memo   of   this   arbitration   application.   Upon   conjoint   reading   of   this  clause­12   of   the   agreement   and   clause­2   of   the   Office   Memorandum  (Annexure­3),   it   is   submitted   by   the   counsel   for   the   applicant   that   the  Arbitrator  may  kindly  be  appointed  for  resolving  the  disputes  between the   2. parties and thus, the applicant is ready if this court is appointing any retired  Hon'ble Judge of this Court as an Arbitrator. 

3. I have heard counsel for the respondents, who has submitted that there  is no arbitration clause in the agreement and the Office Memorandum is of  subsequent date then that of an agreement and the order of the settlement of  the dispute has been provided in the settlement of disputes clause itself and  hence, this application may not be entertained by this Court. 

4. Having heard counsels for both the sides and looking to the facts and  circumstances of the case and the agreement between the parties, it appears  that:­

(i) this   applicant   is   a   Contractor,   who   was   assigned   the   work   of  transporting   the   coal  which   was  made  available   by   Eastern  Coalfields  Limited.   There   is   a   dispute   about   the   penalty   already   levied   by   the  Eastern Coalfields Limited from the applicant for non lifting the coal of a  targeted quantity and the applicant submits that there was no availability  of the targeted coal at all.

(ii) On   06.07.2011,   a   letter   was   written   by   this   applicant   to   the  Engineer­incharge to resolve the dispute and again reminder was given  on  27th  May,  2013   for   referring  the  dispute   to  the  Arbitrator.  It   was  never   replied   by   the   respondents   that   there   is   no   existence   of   the  arbitration clause at all on the contrary, the reply was given on merits of  the claim of the applicant. 

(iii) For the ready reference clause no. 12 of the agreement reads as  under:­           "12. Settlement of disputes:

It   is   incumbent   upon   the   contractor   to   avoid   litigation   and   disputes   during   the   course   of   execution.   However,  if   such   disputes   take  place   between the contractor and the department, effort shall be made first to   settle the disputes at the company level. 
The   contractor   should   make   request   in   writing   to   the   Engineer­In­ charge for settlement of such dispute/claims within 30(thirty)days of   arising of the cause of dispute/claim failing which no disputes/claims of   the   contractor   shall   be   entertained   by   the   company.  If   difference   persists, the settlement of the dispute/claim with Govt Agencies shall be   dealt   with   as   per   the   Guidelines   issued   by   the   Ministry   of   Finance,   Government of India in this regard. In case of parties other than Govt   Agencies the redressal of the dispute may be sought in the Court of law."
 
                                                                           (Emphasis Supplied)   This   clause   is   to   be   read   with   Office   memorandum   dated   14th  May, 2008 which is at Annexure­3. Clause 1 and Clause 2 read as under: 
    3.    
 "Disputes between government departments and Central Public Sector   Enterprises   (CPSEs)   are   settled   through   the   Permanent   Machinery   of   Arbitration   (PMA),   which   does   not   fall   within   the   purview   of   any   arbitration   law.   The   other   mechanism   is   the   Committee   on   Disputes   (CoD),   which   ensures   that   no   litigation   between   departments/CPSEs   reaches   a   court   or   tribunal   without   clearance   by   the   CoD.   The   CoD   mechanism has been put in place in pursuance of the direction of the   Supreme Court in case of ONGC vs. Collector of Central Excise (1992   Supp.(2) SCC 432 and 1995 Supp.(4) SCC 541).

2. The   mechanism   of   PMA   or   CoD   does   not   deal   with   a   dispute   between a private party on the one hand and a government department   or CPSE on the other. For such cases arbitration is resorted to under the   Arbitration and Conciliation Act, 1996. It has come to the notice of the   government that arbitration in such cases is taking a long time. Such   delays give an adverse message to investors. Instead of expediting dispute   resolution, arbitration results in delay. Therefore, it has been decided to   develop a suitable monitoring mechanism for arbitration cases in which   Government or one of its CPSEs is a party." 

                                                                              (Emphasis Supplied) 

(iv) In view of this Office Memorandum dated 14th May, 2008 though  it is subsequent in point of time than the date of agreement which is  dated 5th July, 2007, nonetheless Office Memorandum dated 14th May,  2008 is applicable to the dispute which are arisen out of the agreement  dated   5th   July,   2007   and   therefore,   paragraph­2   of   the   Office  Memorandum is applicable to the disputes raised by the  applicant for  which he has already written letter dated 6th July, 2011 and 27th May,  2013. Hence, it cannot be said that there is no clause of arbitration at all.  Moreover, as per Section 7(4)(c) of the Arbitration and Conciliation Act,  1996   when   the   statement   of   claim   is   raised   by   the   applicant   for  settlement   of   the   disputes   the   answer   is   given   on   merits   by   the  respondents, but, it has been never stated by the respondents that there  is no arbitration clause at all.  

5. As a  cumulative  effect  of  the  aforesaid facts and  reasons, the  dispute  between the parties as referred in the memo of this arbitration application is  hereby, referred to an Arbitrator.  

6. I   therefore,  appoint   retired   Hon'ble   Mr.   Justice   D.G.R.   Patnaik   as   an  Arbitrator   to   resolve   the   disputes   between   the   parties   as   stated   in   the  Arbitration Application. 

7. Learned   Arbitrator   is   requested   to   decide   the   disputes   between   the  parties   and   pass   an   award   as   early   as   possible   and   practicable,   preferably  within   a   period   of   six   months   from   the   date   of   commencement   of   the   4. arbitration proceeding. Both the parties shall cooperate the hearing before the  learned Arbitrator and they shall not ask for any unnecessary adjournment.

8.  Registrar   General   of   this   Court   is   directed   to   supply   a   copy   of   the  arbitration application alongwith annexures and affidavits as well as the order  passed by this Court to retired Hon'ble Mr. Justice D.G.R. Patnaik, who shall  resolve the disputes between the parties.   

9. This arbitration application is allowed and disposed of.   

         (D.N. Patel, J.) VK/