Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Entire Act]

Union of India - Section

Section 49 in Joint Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2019

49. Operation and Maintenance Expenses.

- 49.1 The normative O&M expenses for the first year of the Control Period, i.e., FY 2019-20 shall be 5% of the capital cost for first year.
49.2The normative O&M expenses for subsequent years shall be derived in accordance with the escalation mechanism specified at Regulation 20.3.