Jharkhand High Court
Dinesh Ram vs Union Of India & Ors. on 7 December, 2012
Author: Aparesh Kumar Singh
Bench: Aparesh Kumar Singh
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W. P. (C) No. 1192 of 2008
Dinesh Ram ...Petitioner
-Versus-
Union of India and others ........Respondents.
---
CORAM : HON'BLE MR. JUSTICE APARESH KUMAR SINGH
---
For the Petitioner : Ms. Ritu Kumar, Adv.
For the Respondents-U.O.I : Mr. Mokhtar Khan,ASGI
For the Respondents-BCCL : Mr. Anup Kumar Mehta, Adv.
For the Respondent No. 8 : Mr. Himanshu Kumar Mehta,Adv.
--
04/07.12.2012Heard learned counsel for the parties.
The writ petition has been preferred challenging opening of the tender no. KOL/72/RLBJC/Oxygen Self Rescuer/ADVT/200708/11 dated 23rd July, 2007 alleging noncompliance of letter dated 8th January, 2008 (Annexure7) by respondent no. 8. It is further prayed that the respondent no.3, Director General of Mines Safety, Dhanbad, may be asked as to how and under what circumstances letters dated 13th September, 2007 and 17th September, 2007, were issued granting additional approval to the respondent no.8.
In short by the said NIT, tenders were invited for supply of 'Chemical Type Self Generating Oxygen Self Rescuer 30 minute duration by the RespondentsBCCL to be used for the safety of its workers working in the mines belonging to them. The petitioner is admittedly not a tenderer in the said NIT, however, he claims to be a member of Agragani Jharkhand Colliery Mazdoor Union and is concerned with the safety of miners. The reason for assailing the tender, according to the petitioner, is that certain defects were pointed out in the aforesaid article to be supplied under the instant tender by the respondent no. 8 as per the report of the Director General of Mines Safety.
Learned counsel for the petitioner has relied upon Annexure3 letter of the D.G.M.S dated 11th September, 2007. Learned counsel for the petitioner has also relied upon Annexure6 to submit that the respondent no. 8 was required to replace all defective batches within the stipulated time of six months as per NIT, however, he has not done so.
The respondentsBCCL have appeared and filed their counter affidavit. The Director General of Mines Safety has filed a separate affidavit. The respondent no. 8 also entered appearance through counsel, but he has not filed any affidavit. As such the stand of the BCCL is that the 2 writ petition itself is not maintainable at the instance of petitioner, who is an outsider and he has no locusstandi to challenge the tender as he has not participated in the said tender. It is further submitted on behalf of the counsel for the BCCL that the advertised tender, in question, was opened following the entire process as required under the NIT and was finally approved in favour of the respondent no. 8 who is L1. It is further submitted that the project is covered by valid D.G.M.S approval, which is mandatory requirement and hence the Apparatus is safe. It is further submitted that the petitioner has relied upon a letter which is a correspondence from D.G.M.S to the firm seeking certain information which did not have any bearing on the tender processing of M/s. BCCL. It is further stated categorically at paragraph 14 that the Self Rescue Apparatus is safe having been approved by the D.G.M.S for use in the underground mines. The approval granted by D.G.M.S vide letters dated 1.8.2004 and 4.1.2005 to the respondent no. 8 for supply of Chemical Oxygen Type Self Rescuers, ModelRaksha Kawatch was valid on the date of opening of the tender. The D.G.M.S vide letter dated 11th September, 2007 (Annexure3) had withdrawn the approval but again vide letter dated 13th September, 2007 (Annexure4) had restored the approval. Therefore, the withdrawal letter becomes in operative and redundant. Both the bidders were in possession of D.G.M.S. approval and out of them the respondent no. 8 was finally selected as L1 as per the direction of the D.G.M.S. contained in letter dated 17.9.2007. The respondent no. 8 was asked by B.C.C.L to replace all 70 numbers of such Self Rescuers even though no defects were noticed. In paragraph 22, it has been categorical stated that respondent no. 8 has replaced all 70 numbers of Self Rescuers and the same have been tested at the approved Laboratory of Indian School of Mines University(ISMU), where the tests results were found satisfactory. The entire procurement has been made through tender process as per the direction of D.G.M.S. guidelines/approval and there is no delay in the supply of the same. Any delay in procurement of these items would have deprived the workers of coal mines in availing the help of life saving devise as per statutory requirement.
The respondentsD.G.M.S, in their reply, have also categorical stated at paragraph 19 that the matter for replacement of 70 pieces of 'Raksha Kavach' by respondent no. 8 were taken up by the 3 B.C.C.L and they have confirmed vide letter dated 4th March, 2008 that all 70 'Raksha Kavach' had been replaced by the respondent no. 8 Learned counsel for the respondent no. 8 also submits on their behalf that they had approval of DGMS from before and on the date of opening of the tender as well. The certain Raksha Kavach which were found to be defective were replaced within the period of supply and the entire Raksha Kavach has also been supplied within the stipulated time.
I have heard learned counsel for the parties at length and gone through the entire materials on record. The petitioner admittedly is not a participant in the NIT which has been challenged by him and is not an aggrieved person in the sense of the term having no locusstandi to challenge the tender process. Even then, the issues raised in the writ application relating to safety of 'Raksha Kavach' appears to have been adequately addressed by the respondentB.C.C.L and D.G.M.S in their reply as narrated hereinabove and the entire supply of Raksha Kavach, in question, have also been made within the stipulated time. 70 pieces of Raksha Kavach which were said to be defective have also been replaced by respondent no. 8 during the period of work order itself.
In the aforesaid facts and circumstances, therefore, I have no reason to exercise discretionary jurisdiction in the instant case. Accordingly, the writ petition is dismissed.
(Aparesh Kumar Singh, J) jk/