State of Odisha - Subsection

Section 12(1)(a) in Orissa Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulation, 2005

(a)
(i)An application for long-term access shall be submitted to the nodal agency;
(ii)The application shall contain the details, such as capacity needed, point(s) of injection, point(s) of drawal, duration of availing open access, peak load, average load and such other additional information that may be laid down by the nodal agency :