State of Rajasthan - Subsection

Section 14(2) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016

(2)A long term open access customer, who has not availed open access rights for at least 12 (twelve) years, shall pay an amount equal to 66% of the transmission and wheeling charges, as applicable on the date on which the application for relinquishment of the open access right is made, for the stranded transmission and/or distribution capacity for the period falling short of 12 (twelve) years of open access rights subject to a maximum period of three years.Provided that such an open access customer shall submit an application to the Nodal Agency at least 1 (one) year prior to the date from which such customer desires to relinquish the open access rights.Provided further that in case such an open access customer submits an application for relinquishment of long term open access rights at any time at a notice period of less than one year, then such open access customer shall pay an amount equal to 66% of the transmission and wheeling charges, as applicable on the date from which the open access right is relinquished, for the period falling short of a notice period of one (1) year, in addition to 66% of the transmission and wheeling charges, as applicable on the date on which the application for relinquishment of the open access right is made, for the stranded transmission and/or distribution capacity for the period falling short of 12 (twelve) years of open access rights subject to a maximum period of three years.