Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 21, Cited by 0]

Delhi District Court

Delhi Development Authority vs Pandit Munsi Ram & Associates (P) Ltd on 16 October, 2017

                                                                                      Page   1    of  20


        IN THE COURT OF DR. NEERA BHARIHOKE, ADJ­01 (SOUTH), 
                      SAKET COURTS, NEW DELHI

ARBT no.84/17

Delhi Development Authority 
Executive Engineer SWD2
Vasant Kunj, New Delhi
                                                                             .............Petitioner

Versus


Pandit Munsi Ram & Associates (P) Ltd.
B­27, Sarvodya Enclave
New Delhi­110017

                                                                          ............Respondent

O R D E R:

1. Vide this order, I shall dispose of petition filed under Sec.34 of Arbitration & Conciliation Act for setting aside the arbitral Award dated 20.10.2010.
2. The   grounds   for   filing   the   present   petition   are   that   the   Ld.   Arbitrator passed the award for a sum of Rs.3,39,928.32 under the claim no.9 for the loss of profitability/turnover due to prolongation of the contract and has legally misconducted in awarding the said claim on percentage basis whereas the Ld. Arbitrator has not considered the cost of the work done including the cost of material which is amounting to Rs.35,03,360/­ which ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 
Page   2    of  20

has   not   been   deducted   by   the   Ld.   Arbitrator   hence   the   claimant   has nowhere claimed the loss of profitability.

2.1 Petitioner has further submitted that the claimant had not filed actual   loss   being   suffered   by   him.   Even   no   documentary   evidence   to show the loss of profit in the statement of account has been filed and still Ld. Arbitrator had granted 8% loss of profit to the work which includes cost of material which is against the provisions of law and public policy of India and the Ld. Arbitrator has legally misconducted on this account.  2.2 Petitioner   has   further   submitted   that   the   present   claim   is against Section 73 of Contract Act as the loss of profit is shown indirect damage for which claimant has to prove his case which the claimant has failed to do and also the claimant had nowhere pleaded that he suffered loss and has not placed any document to show that he had any other contract  during  the  said  period  and  could  have  utilized  this amount in other contract, hence the present claim is liable to be set aside.  2.3 Petitioner has further submitted that the claim is false, frivolous and baseless as the claimant/respondent has not stated as to when it is deducted   to   mitigate   the   loss   and   the   present   claim   is   hypothecated, ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   3    of  20

erroneous and illegal without any evidence placed on record and also the Ld. Arbitrator had not considered the clause 10 & 13 of General Condition no.1   of   Specification   and   Conditions   and   in   view   of   this   clause,   the claimant is not entitled to any loss/compensation and hence the claim is liable to be set aside. 

2.4 The petitioner has further submitted that the Ld. Arbitrator has not considered the cost of material as Rs.35,03,360/­. Without prejudice to earlier submissions thus the cost of the material has to be reduced from   the   cost   and   also   the   Ld.   Arbitrator   has   not   considered   that   the excess   period   is   required   for   the   execution   of   the   work   beyond   the tendered amount and hence the period so calculated is also correct and excess   work   done   is   for   Rs.42,17,031   beyond   tendered   amount   of Rs.96,94,048/­ total work comes to Rs.1,39,11,079 and hence the award is liable to be set aside as the claimant is not entitled to any amount.

3. Detailed reply has been filed on behalf of respondent in which respondent has submitted that the Objection petition filed under Section 34 of the Arbitration & Conciliation Act, 1996 are in the nature of an appeal against the award passed by Learned Arbitrator and the grounds of objections ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   4    of  20

are   totally   outside   the   parameters   of   Section   34   of   the   Arbitration   & Conciliation Act, 1996. The Objections are in the nature of appeal and are liable to be outrightly rejected.

4. Respondent   has   relied   on   law   laid   down   in   the   case   of  Ispat Engineering & Foundry Works, B.S. City, Bokaro Vs. Steel Authority of   India,   B.S.   City   Bokaro,   (2001)   3   SCR   1190  where   the   Hon'ble Supreme Court has held as under:­ "4. Needless to record that there exists a long catena of cases through which the law seems to be rather well settled that the re­ appraisal of evidence by the court is not permissible. This court in one of its latest decisions (Arosan Enterprise Ltd. Vs. Union of India & Anr. AIR 1999 SC 3804) upon consideration of decision in  Champsey Bhara & Co. Vs. Jiraj Ballow Spg. & Wvg. Co. Ltd. (AIR 1923 PC 66 1923 AC 480), Union of dina V. Bugno Steel Furniture  (P) Ltd. (1967) 1SCR 324, N. Chellappan V. Seev., Kerala SEB & Anr. (1975) 1 SCR 811, M/s. Sudarsan Trading Co. V. Government of Kerala and Anr.(1989) 1 SCR 665; State of Rajasthan V. Puri Construction Co. Ltd. & Anr. (1994) 6 SCC 485 as also in Olyphus Superstructures (P) Ltd. V. Meena Vijay Khetan & Ors. (1999) 3 SCR 490  has stated that re­appraisal of evidence by the court is not permissible and as a matter of fact exercise of power to re­appraise the evidence ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   5    of  20

is unknown to a proceeding under Section 30 of the Arbitration Act.   This   Court   in  Arosan   Enterprise   (supra)  categorically stated that in the event of there being no reason in the award question of interference of the court would not raise at all. In the event however, there are reasons, interference would still be not available   unless  of  course,  there  exist  a   total   perversity  in   the award or the judgment is based on a wrong proposition of law. This court went on to record that in the event, however two views are possible on question of law, the court would not be justified in interfering   with   the   award   of   the   Arbitrator   if   the   view   taken recourse to is a possible view. The observations of Lord Dunedin in  Champsey Bhara (supra)  stands accepted and adopted by this court in Bungo Steel Furniture (supra) to the effect that the court had no jurisdiction to investigate into the merits of the case or to examine the documentary and oral evidence in the record for the purposes of finding out whether or not the arbitrator has committed an error of law. The court as a matter of fact cannot substitute its own evaluation and come to the conclusion that the Arbitrator had acted contrary to the bargain between the parties."

5.  Respondent has averred that the petitioner has failed to point out any illegality or perversity in the Award. Respondent has also referred to case of State of U.P. Vs. Applied Construction, (2003) 7 SCC 396, where it was observed that "Once it is found that the view of the Arbitrator is a ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   6    of  20

plausible one, the court will refrain itself from interfering." It is a settled law that it is not for a court to interfere with an award merely on the basis that   the   court   would   come   to   a  different   conclusion   on   the   basis   of material available before the arbitrator. Respondent has also contended that referring to the judgment of Hon'ble Supreme Court in the case of Food   Corporation   of   India   Vs.   Joginderpal,   Mohinderpal   &   Anr. (1989)   2   SCC   347­   Gujrat   Water   Supply   and   Sewerage   Board   Vs. Unique   Erectors   (Gujrat)   (P)   Ltd.   And   Anr,   AIR   1989   SC   173.  The Division Bench of this Hon'ble Court in FAO (OS) 147/2002  decided on 12.08.2011 observed as under:­ "In fact, it has been observed in a catena of judgments by the Supreme Court that in the absence of an award being absurd, reasonableness is not the matter to be considered by the court as appeasement of evidence by an arbitrator is not ordinarily a matter for the court. 

6. Respondent   has   denied   the   submissions   made   in   the   reply   and   has submitted   that   the   petitioner   has   failed   to   point   out   mistake   in   the calculation   based   on   Hudson   Formula   before   the   Ld.   Arbitrator. Respondent has also contended that the respondent was not required to ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   7    of  20

show any actual loss and produce documentary evidence to show the loss of profit and the arbitrator is entitled to make his assessment. The Ld. Arbitrator is competent to adopt any method to determine the actual amount of loss, as has been done in the present case. Further claimant is entitled to damages under Section 73 of the Contract Act and has rightly been awarded Rs.3,39,928.32 by the Ld. Arbitrator. In any event it is an admitted   fact   a   work   stipulated   for   12   months   was   completed   in   28 months.   It   is   also   an   admitted   fact   that   it   was   petitioner   who   was responsible for delay and the consequence thereof. It is also an admitted fact that contractor is bound to suffer losses if a work stipulated for 12 months prolonged by 15 more months. Therefore the Ld. Arbitrator is well within its jurisdiction to assess the loss. The respondent has prayed for dismissal of the present petition.

7. Arguments Heard. Record perused.

8. The petitioner is aggrieved by the allowing of claim number 9 by learned arbitrator in the impugned award dated 20.10.2010.

9. The respondent had raised claim of ₹ 3, 39, 928.32 on account of loss of profitability/turnover   due   to   prolongation   of   the   contract   under   claim ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   8    of  20

number   9.   In   support   of   this   claim,   respondent   had   submitted   that immediately after expiry of stipulated date of completion, the respondent had informed the petitioner through letter dated 12.05.1991 that the work had   delayed   due   to   non­fulfillment   of   obligation   on   the   part   of   the petitioner and the respondent is going to charge 40% above the quoted rates   for   the   work   done   after   stipulated   date   of   completion.   The respondent has submitted that the said notice is nothing but notice under Section   55   of   the   Indian   Contract   Act   and   the   said   notice   was   never replied by the petitioner implying that it was accepted by the petitioner. The  respondent  had   submitted   before   Learned   Arbitrator  that  the   said 40% was informed taking into consideration that the said 40% will cater to loss on account of profitability/turnover for the prolonged period, loss due to underutilization of men, material and T&P etc. and increase in market rates of building materials and labour. The respondent had also relied on section 44 AD of Income Tax Act as well as submitted calculation sheet based   on   the   formula   specified   in   Hudson's   Building   and   Engineering Contracts.

10. The petitioner on the other hand had submitted that no such notice as contemplated   by  section   55   of   the   Contract   Act   was  served   upon   the ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   9    of  20

petitioner by the respondent and in any case the respondent having been paid extra amount of wages of the labour and increase in price of material under   clause   10   CC   of   the   contract   and   going   by   the   clause   1   of Additional Specifications and Conditions, the respondent is not entitled to have any reimbursement in respect of salaries paid to the staff more so when   the   respondent   has   not   substantiated   the   claim   by   placing   any cogent material in the shape of account books or other documents on record to show that he had to incur extra expenditure on salary etc.

11. Learned   Arbitrator  has  observed  that  completion   of  work  was  delayed due to non­fulfillment of obligation on the part of petitioner and that the petitioner   had   extended   the   period   for   completion   on   the   conditions notified by the respondent vide its letter dated 12 5 1991 wherein it was stated that:

"The   above   work   was   awarded   to   us   with   date   of   start   as 26.01.1990 stipulated to be completed on 25.04.1991. As per the award letter the  scope  of work was  construction  of 288  Janta  houses at the estimated cost of ₹ 96,94,047.
Even after various hindrances, not attributable to us, we have completed approximately same amount of work allotted to us within the ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 
Page   10    of  20
stipulated period. However, it is pointed out here that a lot of further work is to be carried out at site to complete the allotted 288 houses.
As our stipulated time for completing the project is over and as we  have completed the  same quantum of work allotted to  us on  time therefore our responsibility as per the contract stands discharged.
However, we being the prudent contractors are interested to complete all the 288 houses allotted to us but on following conditions:
1.Extension of time without levy of compensation be given to us in accordance with the balance quantum of work.
2.You   also   know   that   in   last   few   months   rates   of   building materials and labour have risen sharply and the escalation under section 10 CC is not enough to compensate for this rise in the market. Therefore, we will be charging 40% above our quoted rates for the balance work to be done."

12. Learned   arbitrator   deemed   it   to   be   a   notice   under   section   55   of   the Contract Act and further observed that the claim could not have been rejected on the sole ground that no notice as envisaged by section 55 of the   Contract   Act   was   given   by   the   contractor   to   the   DDA.   Learned arbitrator   proceeded   to   say   that   the   calculation   submitted   by   the respondent is based on the formula specified in Hudson's Building and Engineering   Contracts   which   has   been   approved   by   Apex   Court   in ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   11    of  20

various High Courts as the valid basis. The claim is also stated to be based on the provisions of section 44 AD of the Income Tax Act which provides the method of calculating contractor's profit at the rate of 8% of the work executed by him.

13. Learned arbitrator despite noticing the submission of the petitioner that claimant has not substantiated its claim by placing any cogent material in the shape of account books or other documents on record showing that he had to incur extra expenditure on salary etc. still held that respondent is entitled to this claim because there cannot be denial of the position that completion of work was delayed due to non­fulfillment of its obligation on the part of the petitioner - DDA and that is why they extended the period for completion on the conditions notified by the claimant vide its letter dated 12.05.19 91.

It   was   also   observed   that  "There   cannot   be   denial   of   the position that due to prolongation of the contract, the claimant must have suffered loss in his turnover/profitability because he was unable to utilize his   resources   for   any   other   work   which   he   could   have   undertaken   to execute   during   the   extended   period.   It   is   true   that   claimant   has   not produced   his   account   books   in   order   to   show   the   actual   loss   of profitability/turnover due to prolonged nation of contract. Even then he ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   12    of  20

has worked out his claim based on Hudson formula which is stated in the following terms:

contract   head   office   overhead   and   profit   percentage   into contract sum/contract period X period of delay This   formula   has   been   upheld   by   the   Apex   Court   in   the decision   of  McDermott   International   Inc   versus   Bernard   Standard Company Ltd and Others 2006 (2) Arb. LR (SC) and allowed the claim of the respondent."

14. Thus it is clear that the claim of the respondent was allowed in absence of respondent leading any evidence and in the absence of respondent producing its account books.

15. The respondent has submitted that under section 34 of Arbitration and Conciliation Act, this court cannot reappraise the evidence as been held in   catena   of   judgments   that   under   section   34   of   Arbitration   and Conciliation   Act   grounds   of   objections   have   to   be   decided   within   the parameters of section 34 of Arbitration and Conciliation Act. However in the   present   case,   the   impugned   sum   awarded   by   the   claimant/ respondent while allowing claim number 9 is not based on any evidence rather it has been allowed despite arbitrator specifically noticing that the ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   13    of  20

respondent has led no evidence to substantiate its claim under the said head.   It   is   pertinent   to   note   that   Learned   Arbitrator   had   specifically disallowed   the   sum   claimed   by   the   respondent   towards   claim   for   the work done after the stipulated date of completion on account of increase in market rate as well as claim number 11 raised on the ground of loss and damages due to under utilization of men, material and T and P etc. by observing that the respondent had received the amount under Clause 10 CC of the contract.

16. The facts of the present matter are similar to the facts in the matter of Edifice   Developers   and  Projects   Engineers   Ltd   versus   M/s   Essar Projects   (India)   Ltd  where   the   Hon'ble   High   Court   of   Bombay   while deciding appeal number 11 of 2012 in Petitioner No. 313 of 2007 upheld the decision of Learned Single Judge setting aside the impugned award in   similar   set   of   facts   and   the   Hon'ble   High   Court   of   Bombay   has specifically   dealt   with   Hudson's   formula   and   the   law   laid   down   in judgment   of  Mcdermott   International   (Supra)  on   which   learned Arbitrator has relied in allowing the claim under Claim 9 raised by the respondent/claimant before him.

ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   14    of  20

17. Hon'ble High Court of Bombay observed that the appellant had claimed an amount of  ₹  1,88,15,960 towards overhead losses on the basis of Hudson's formula. Learned single judge in that case while noting that the appellant had not produced either the basis of the accounts nor lead any oral evidence in support of the claim, the arbitrator nonetheless allowed the claim on the basis of a finding that Hudson formula is adopted for quantification   of   claims   for   overhead   losses   in   India.   The   award contained the following finding:

"35(i)   the   claimants   have   claimed   a   sum   of  ₹1,88,15,9604 overhead loss on the basis of Hudson formula. The respondents have denied   the   liability   and   have   stated   that   no   evidence   of   actual   loss alleged to have been suffered by the claimant have been led so as to entitle the claimants to claim the same from the respondents. It is correct that the claimant have not produced the basis of accounts nor led any oral evidence to prove the overhead loss caused to or suffered by the claimant. However in the construction industry where the resources are mobilized   and   the   delay   is   caused   in   execution   of   work   which   is   not attributable to the contractor, overhead losses consequently caused to the contractor, the contractor becomes entitled to same on the basis of Hudson formula even in want of direct evidence to prove the same"....

18. This formula is adopted for quantification of claim for overhead losses in ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   15    of  20

India. Even in the case of  M/s Brij Paul Singh and Brothers versus State of Gujarat AIR 1994 SC 1703  on which reliance is placed by Dr Dave, learned Techno Legal Consultant for the claimant, this formula has been accepted by the Hon'ble Supreme Court for quantification of claims for overhead losses. On the basis of Hudson formula the claimants have claimed overhead losses up to 28 January 2002 amounting to  ₹ 1, 88, 15, 960."

19. The   Learned   Single   Judge   while  setting   aside   the   arbitral   award observed that­

(i) The Respondent had specifically objected to the adoption of Hudson formula noting that this was not an accepted method or measure for the quantification   of   losses   and   that   the   appellant   had   in   fact   failed   to produce any evidence in support of the claim. The Arbitral Tribunal had not dealt with the objections of the Respondent;

(ii)   The   finding   of   the   Arbitrator   that   the   Hudson's   Formula   had   been accepted by the Supreme Court in the decision in M/s Brij Paul Singh and Brothers versus State of Gujarat was incorrect. As a matter of fact the judgment of Supreme Court in M/s Brij Paul Singh's case only noted that   in   that   case   the   High   Court   had   referred   to   Hudson   Treatise   on Building   and   Engineering   Contracts   as   stating   that   in   major   contracts subject   to   a   competitive   tender,   evidence   given   in   litigation   on   many ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   16    of  20

occasions   suggests   that   the   head   office   overheads   and   profits   are between 3 to 7% of the total price of cost which is added to the tender;

(iii)   The   Arbitrator   has   purported   to   rely   on   prevalent   trade   practice though as a matter of fact the Appellant was not able to demonstrate any material placed on record to show that any such practice prevailed or was accepted in the trade;

(iv)   The   Arbitrator   had   not   considered   any   other   formula   and   had proceeded on the erroneous premises that Hudson Formula is the only formula available and which is accepted by the Supreme Court. This, it was held, was contrary to the law laid down by the Supreme Court in Mc Dermott International Inc. versus Burn Standard Company Ltd. When this finding was assailed before Hon'ble High Court of Bombay, it was observed by Hon'ble High Court of Bombay as­ "The arbitral award, ex facie, demonstrates that the Arbitrator proceeded on the basis that the Appellant had not produced either the basis of the account or any oral evidence to prove the overhead losses caused to or suffered   by   it.   Despite   that   finding,   the   arbitrator   held   that   in   the construction industry a contractor becomes entitled to overhead losses on the basis of Hudson Formula, even in the absence of direct evidence to prove such losses when resources are mobilized and delay is caused in the execution of work not attributable to the contractor. In holding this the Arbitrator relied upon the judgment of the Supreme Court in Brij Paul Singh's case (supra).

The Learned Single Judge was justified in coming to the conclusion that ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   17    of  20

the arbitrator was manifestly in error in awarding the claim for overhead losses in spite of the fact that no oral evidence was adduced on behalf of the Appellant. In Brij Paul Singh's case, the Supreme Court noted that it was not disputed that where in a work contract a party entrusted with the   work   commits   a   breach   of   the   contract,   the   contractor   would   be entitled to claim the damages for loss of profit which he expected to earn while undertaking the contract.

  The Supreme Court however noted that what must be the measure of the profit and what evidence should be tendered to sustain the claim are different matters. The judgment of the Supreme Court adverts to the fact that in that case the High Court had referred to Hudson's Treatise on Building and Engineering Contracts. Hudson states there that in major contracts subject to competitive tender on national basis, the evidence given   in   litigation   on   many   occasions   suggests   that   the   head   office overheads  and  profits are  between  3  to   7%   of the  total  price   of cost which is added to the tender. The High Court in that case had rejected the claim of the contract. The Supreme Court noted that in an identical contract   with   regard   to   another  portion   of   the   same   road   and   for   the same type of work, the High Court had accepted loss of profit at 15% of the price of the balance of work as a reasonable measure of damages if the State  is guilty of breach  of contract. It was on this basis that the Supreme Court came to the conclusion that since for the same type of work, between the same parties involving a nearby portion of the same road   a   certain   measure   of   damages   had   been   adopted   by   the   High ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   18    of  20

Court, the same measure ought to have been adopted in that case as well."

20.  It was further observed by Hon'ble High Court of Bombay that­ "Brij   Paul   Singh's   case  therefore   does   not   stipulate   as   a doctrine of law that the formula which has been prescribed in Hudson's treatise   must   invariably   be   accepted   in   all   cases   as   a   measure   of damages sustained on account of loss of overheads. On the other hand in   the   subsequent   decision   of   the   Supreme   Court   in  McDermott International (Supra)  the Supreme Court has relied upon the following observations contained in the earlier decision in M.N. Gangappa versus Atmakur Nagabhushanam Setty and Company as "In the assessment of damages, the court must consider only strict legal obligations and not the expectations, however reasonable of one contractor that the other will do something that he has assumed no obligation to do."

21. The   judgment   in  McDermott   International   (Supra)  considers   various formulae   including   Hudson   Formula,   Emdun   Formula   and   Eichleay Formula. As regards Hudson Formula, the Supreme Court has noted that although it has received judicial support in many cases it has been the subject matter of criticism principally because it adopts the head Office overhead   percentage   from  the   contract  as  a   factor  for calculating  the costs and this may bear little or no relation to the actual head office costs of the contractor." (emphasis supplied)."

ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   19    of  20

22.  In  McDermott international (supra) that it is an accepted position that different   formulae   can   be   applied   in   different   circumstances   and   the question as to whether damages should be computed by taking recourse to one or other formula, having regard to the facts and circumstances of a particular case, would fall within the domain of the arbitrator."

23.  After   recording   these   observations,   Hon'ble   High   Court   of   Bombay observed   that   In   the   case   i.e.  Edifice   Developers   and   Projects Engineers Ltd versus M/s Essar Projects (India) Ltd, no other formula other than Hudson formula has been considered in the arbitral award. In the present case the arbitrator proceeded on the basis that it was only Hudson formula which was to be applied and that even though no direct evidence had been adduced on behalf of the appellant, nonetheless the appellant would be entitled to damages measured with reference to the aforesaid   formula.   This   approach   of   the   arbitrator   is   manifestly   in   the teeth   of   the   law   laid   down   by   the   Supreme   Court   in  McDermott international. Section 28 (1) (a) requires that the arbitral tribunals shall decide   a   dispute   submitted   to   arbitration   in   accordance   with   the substantive   law   for   the   time   being   in   force   in   India.  Section   28   (3) requires the arbitral tribunal to decide in accordance with the terms of the ARBT no.84/17 DDA  Vs.  Pt. Munshi Ram Associates Pvt. Ltd. 

Page   20    of  20

contract and take into account the usages of the trade applicable to the transaction. The arbitral terminal under section 28 (2) can act as amiable compositeur   and   can   decide  ex   aequo   et   Bono  only   if   parties   have expressly authorized it to do so. Thus the Hon'ble High Court of Bombay upheld the decision of learned single judge.

24. Thus   the   impugned   award   having   been   passed   in   absence   of   any evidence by relying on Hudson's Formula and in violation of section 28 (1) (a) and section 28 (3) of Arbitration and Conciliation Act is liable to be set aside in view of aforesaid observations and the cited case law.

25. Vide   Award   dated   20.10.2017   claim   no.9   of   respondent   was   allowed, whereas   claim   no.8,   10   &   11   were   disallowed.   The   award   dated 20.10.2010 is set aside to that extent while the remaining part of award in   relation   to   claim   no.8,   10   &  11   is  affirmed.   The   present   petition   is disposed of in these terms. File be consigned to record room.




         (Announced in open
         Court on 16.10.2017)                                   (Dr. Neera Bharihoke)
                                                                ADJ­01, South District
                                                                Saket Courts, New Delhi




ARBT no.84/17
DDA 
Vs. 
Pt. Munshi Ram Associates Pvt. Ltd.