Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Calcutta High Court (Appellete Side)

Meghdoot Ghosh vs The State Of West Bengal & Ors on 17 December, 2018

                                 1


                     W.P. No. 1172 (W) of 2018
                IN THE HIGH COURT AT CALCUTTA
                  Constitutional Writ Jurisdiction
                           Appellate Side
                         Meghdoot Ghosh
                                Vs.
                  The State of West Bengal & Ors.

For the Petitioner          : Mr. Joy Saha, Sr. Advocate
                              Mr. Avishek Guha, Advocate
                             Ms. Rimi Aich, Advocate

For the State               : Mr. Samrat Sen, Sr. Advocate
                              Ms. Amrita Panja Moulick

Hearing concluded on        : December 11, 2018

Judgment on                 : December 17, 2018

DEBANGSU BASAK, J.:-

       The petitioner has assailed the rejection of his technical

bid.


       Learned Senior Advocate appearing for the petitioner has

submitted that, not only the rejection of the technical bid of

the petitioner was incorrect, but also, the tender evaluation

process was not in accordance with the terms and conditions

of the tender. The petitioner participated in the notice inviting

e-tender issued by the Irrigation and Waterways Directorate

for special repair of drainage channel of Nalipara at Barakar

under Asansol Municipal Corporation. The prequalification
                                    2


work   credential   requirement         of   the    tender     requires   a

participant to have undertaken major item as described in

protection work (Type A) of the tender conditions of a value of

Rs. 38.23 lakhs for an individual and Rs. 76.45 lakhs for

consortium/ joint venture. According to him, the petitioner

undertook protection work (Type A) as described in the tender

conditions at least in two projects of value far in excess of

Rs. 38.23 lakhs. Learned Senior Advocate appearing for the

petitioner has referred to, the documents submitted by the

petitioner in the tender process. He has submitted that, the

authorities   wrongfully     and       illegally   did   not    take   into

consideration at least three items of work in one of the

projects executed by the petitioner, and at least two items of

work in the other project. The non considered items of work by

themselves qualified the value prescribed in the tender

process, let alone the entirety of the value of the work

undertaken by the petitioner, in such projects. Therefore,

according to him, the rejection of the technical bid by the

authorities was incorrect.
                                3


     Referring to the general terms and conditions of the

tender process, he has submitted that, the tender conditions

prescribed the schedule of important dates of the e-tenders.

Under such schedule, the authorities are required to provide

clear four working days between the date of the opening of the

technical bid and the opening of the financial bid for disposal

of complaints and obtaining of decision from appellate

authority. In the present case, such schedule was not adhered

to. Non-adherence with such schedule caused immense

prejudice to the petitioner as the petitioner could not approach

the appellate authority to urge his complaints. He has drawn

the attention of the Court to the tender summary report

appearing at page 101 of the writ petition and has submitted

that, the technical bid was claimed to be opened on January

5, 2018 which was later updated on January 11, 2018. The

financial bid was opened on January 11, 2018 itself.

Therefore, four clear days were not provided between the

opening of the technical bid and the financial bid. In such

circumstances, the rejection of the technical bid of the
                                    4


petitioner should be held to be bad. The petitioner held to be

qualified in the tender process.


     Learned Assistant Additional Advocate General appearing

for the State has submitted that, the technical bid of the

petitioner was evaluated in accordance with the tender

conditions. There are no infirmities or irregularities in such

evaluation process warranting an interference by a Writ Court.

He has relied upon 2016 Volume 16 Supreme Court Cases

page 818 (Afcons Infrastructure Limited v. Nagpur Metro

Rail Corporation Limited & Anr.) and has submitted that,

the Courts should be slow in interfering with the decision

making process in accepting or rejecting a bid. In the present

case, the decision making process does not suffer from any

mala fides. It has not been substantiated that, the decision

was intended to favour someone. It has also not been

substantiated that, the decision is arbitrary or irrational or

such that no responsible authority acting reasonably and in

accordance with law could have reached such a decision.


     Learned Assistant Additional Advocate General has

referred to the terms and conditions of the e-tender, and
                                   5


submitted that, it is open to the employer to interpret the

tender conditions in a particular way. The Tender Evaluation

Committee had considered the documents submitted by the

petitioner and arrived at a finding that, the petitioner was not

qualified. Such a decision cannot be said to be perverse. A

Writ Court need not sit in appeal over such decision of the

Tender Evaluation Committee.


     Referring to the terms and conditions of the e-tender,

learned Assistant Additional Advocate General has submitted

that, the petitioner did not qualify the essential criteria laid

down in the tender process. The petitioner did not have the

requisite technical qualification to have its financial bid

opened. Moreover, more than four working days were afforded

to the parties between the date of opening of the technical bid

and the financial bid as will appear from page 101 of the writ

petition   being   the   tender       summary   report.   Therefore,

according to him, no interference is called for in the present

writ petition.


     The Superintending Engineer, Irrigation and Waterways

Directorate of the State of West Bengal, floated a notice
                                    6


inviting e-tender for special repair of drainage channel of

Nalipara at Barakar under Asansol Municipal Corporation.

The relevant eligibility criteria to match the prequalification

work credential in terms of execution of similar previous work

contract prescribed in the tender process is as follows:-


          "A Prequalification (PQ) Work Credential:
     i.      Gross notional value of Completion Certificate
             (CC) of at least one 100% completed single project
             works contract (defined at clause 6) during the
             current FY and preceding five FY of similar
             nature (defined at clause 7) to the particular
             work in this e-NIT, for which the bidder intends
             to participate.
     ii.     Gross notional value of that similar work cited by
             bidder as PQ work credential calculated by
             multiplying the gross final value of the work as
             per the CC with a factor as stated under Clause
             7 I(a), should not be less than 30% of the amount
             put to tender of the work for which the bidder
             chooses to participate. (The same shall be
             minimum 60% for Consortium/JV)
     iii.    Finally, the PQ work criteria of 'similarity' will be
             established, only if summation of values of any
             one of the following conglomerate of items,
             calculated from the uploaded BOQ of the bidders
             PQ work credential and further multiplying the
             sum by the factor stated in Clause 7 III and is
             greater than the monetary value of the
             corresponding conglomerate of items shown
             below:
             a. Major Item description in brief: Protection
                work (Type A)
                                 7


           b. Rs. 38.23 Lakh & for Consortium/Joint
              Venture Rs. 76.45 Lakh"


     The general terms and conditions of the subject e-tender

requires a participant in such e-tender to submit bill of

quantities along with work order/award of contract duly

authenticated by the competent authority under technical

order. The protection work (Type A) is described in Clause

7.II.f of the general terms and conditions of the e-tender. It is

as follows:-


           "Protection work (Type A): CC blocks/cement
          concrete lining / toe walls / boulders of all kind,
          dry brick pitching / brick block pitching / loose
          boulder apron / crated boulder dumping,
          boulder/blocks in PP rope-gabions/ brick bat
          dumping for sausage or aprons or under water,
          scour hole depth filling by boulders / brick bats in
          geo-bags, sand/earth filled geo-bags, laying of
          inverted filters below pitching by conventional
          brick bats / jhama bags or geo-jute or geo-
          synthetics, including supply, carriage and laying
          at site etc complete."



     Clause 14.3 of the General Conditions of the e-tender

requires the Tender Evaluation Committee to evaluate the

technical bids. It requires the Tender Evaluation Committee to
                                  8


scrutinise the bids and upload the technical bid opening

summary sheet within a minimum of two working days with

reasons for preliminary rejection and a preliminary list of

eligible bidders/contractors whose technical proposals have

been considered for uploading in the web portal. Clause 14.4

of the general conditions permits an aggrieved bidder to seek

clarification/redressal/review from the Tender Evaluation

Committee within 24 hours of the uploading of the tender bid

opening summary sheet. Clause 14.5 of the general terms and

conditions of the e-tender allows opening and evaluation of

financial bid. It allows the Tender Evaluation Committee to

accept the tender if it finds it acceptable.


     The petitioner had participated in the subject e-tender. It

had submitted its bids electronically. The Tender Evaluation

Committee had opened the technical bid of the petitioner on

January 5, 2018 as appearing from the tender summary

report at page 101 of the writ petition. The technical bids were

scrutinised and the result of such scrutiny was updated on

January 11, 2018.
                                    9


     It is the contention of the petitioner that, two of the

earlier works executed by the petitioner brings the petitioner

within the technical qualification as laid down in the subject

tender conditions. The tender documents submitted by the

petitioner   were    evaluated     by   the   Tender   Evaluation

Committee. According to the petitioner, three bill of quantities

items in one of the works and two of the bill of quantity items

in the other work should have been taken into consideration

by the Tender Evaluation Committee. Not having done so, the

Tender Evaluation Committee erred in evaluating the technical

bid of the petitioner correctly.


     Afcons Infrastructure Limited (supra) has held that,

the decision making process in accepting or rejecting a bid

should not be interfered with unless, it is substantiated that,

the decision making process suffers from mala fides or is

intended to favour someone or is arbitrary or irrational or

such that no reasonable authority acting reasonably in

accordance with law could have reached such decision. A

perversity of the decision making process can be enquired

into. A decision which is merely faulty or erroneous or
                                 10


incorrect should not be a ground for a Court to interfere. A

Constitutional Court is expected the exercise restraint in

interfering with administrative decision and ought not to

substitute its view for that of the administrative authority.


     The fact that, a different view can be taken on the self-

same material, is not a valid ground for interference for a

Constitutional Court with an administrative decision, unless,

it is substantiated that, the decision is tainted with fraud or

mala fide or the decision is so erroneous that, no reasonable

authority could have arrived at such a conclusion.


     In the facts of the present case, the Tender Evaluation

Committee evaluated the tender documents and did not take

into consideration three of the bill of quantity items in one of

the works executed by the petitioner and two bill of quantity

items in the other. At best, the Tender Evaluation Committee

can be said to have erred in not taking into consideration such

bill of quantities. There is no material placed on record to

suggest that, the impugned decision was taken in order to

favour someone or suffers from mala fides. It is the contention

of the petitioner that, the petitioner had quoted the rate which
                                  11


was 20% less than the initial quote of the private respondent.

Moreover, the authorities accepted the bid of the private respondent after a discount of 2%. Ultimately, the exchequer suffered 18% less for not having accepted the bid of the petitioner. That by itself, will not attribute mala fides in the decision making process nor can the decision arrived at by the Technical Evaluation Committee be said to be taken for the purpose of benefitting the private respondent. The fact that the financial bid of the petitioner was less than 20% of the rate quoted by the private respondent was not known to the Technical Evaluation Committee as the financial bid of the petitioner was not opened while considering the financial bid of the private respondent. Moreover, the petitioner had time since January 5, 2018 when, the technical bid opening summary was uploaded till January 11, 2018 when the financial bid was opened, for the petitioner to question the decision of the Technical Evaluation Committee in not considering the petitioner as technically qualified. Nothing is placed on record to suggest that, the petitioner attempted to do so within such time period.

12

In such circumstances, I find no reason to interfere. W.P. No. 1172 (W) of 2018 is dismissed. No order as to costs.

Urgent certified website copies of this order, if applied for, be made available to the parties upon compliance of the requisite formalities.

[DEBANGSU BASAK, J.]