State of Maharashtra - Subsection

Section 45(5) in The Maharashtra Regional and Town Planning Act, 1966

(5)If the Planning Authority does not communicate its decision whether to grant or refuse permission to the applicant within sixty days from the date of receipt of his application, or within sixty days from the date of receipt of reply from the applicant in respect of any requisition made by the Planning Authority, whichever is later, such permission shall be deemed to have been granted to the applicant on the date immediately following the date of expiry of sixty days:[Provided that, the development proposal, for which the permission was applied for, is strictly in conformity with the requirements of all the relevant. Development Control Regulations framed under this Act or bye-laws or regulations framed in this behalf under any law for the time being in force and the same in no way violates either the provisions of any draft or final plan or proposals published by means of notice, submitted for sanction under this Act:Provided further that, any development carried out in pursuance of such deemed permission which is in contravention of the provisions of the first proviso, shall be deemed to be an unauthorised development for the purposes of sections 52 to 57.] [These proviso were added by Maharashtra 10 of 1994, Section 6(a).]