Delhi High Court
M/S.Flowmore Private Limited vs National Thermal Power Corporation on 21 October, 2009
Author: Valmiki J.Mehta
Bench: Valmiki J.Mehta
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S. (OS) No. 3022A/1996
21st October, 2009.
M/S.FLOWMORE PRIVATE LIMITED ...Petitioner/Claimant
Through: Mr. Kailash Vasdev, Senior
Advocate with Mr. Sanjay K.
Shandilaya, Advocate, Mr.
Aggarwal, Advocate and Ms. Ekta
Mehta, Advocate.
VERSUS
NATIONAL THERMAL POWER CORPORATION ....Respondent
Through: Mr. J.C. Seth, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not? yes
3. Whether the judgment should be reported in the Digest? yes
% JUDGMENT (ORAL)
I.A. No. 4430/1997
1. I.A. No. 4430/1997 in Suit No. 3022A/1996 are the objections under Sections 30 and 33 of the Arbitration Act, 1940, filed by the objector M/s. National Thermal Power Corporation Limited (NTPC). The objections are with respect to the Award dated 19.11.1996 of the Arbitration Tribunal comprising of three members, namely, Sh. P.P. C.S(OS)No.3022A/1996 Page 1 Dharwadkar, FIE Presiding Arbitrator, Justice Rajender Sachar, Retd. Chief Justice, Delhi High Court and Justice Avadh Behari Rohatgi, Retd. Judge of this Court. There are two Awards, a majority Award and a minority Award. The majority Award is of Sh. P.P. Dharwadkar and Justice Avadh Behari Rohatgi (Retd.) and the minority Award is of Justice Rajender Sachar (Retd.).
2. The disputes which arose between the parties pertain to the tender called for by the objector for design, manufacture, supply of pumps with erection, testing and commissioning of circulating water pumps (CW pumps) for the project of the objector at Ramagundam in the State of Andhra Pradesh. The non-objector (hereafter "Flowmore") submitted its offer on 29.7.1979 and it was accepted by NTPC by issuing a Letter of Intent on 18.1.1980. Flowmore under the contract was to supply 7 CW pumps along with electric motors as also some spare parts. Flowmore was also to undertake installation of the pumps at site. The total value of the contract was Rs. 1,15,02,900/- for supply of the equipment, spares and erection. It may be noted that the contract was for supply of Stainless Steel C.S(OS)No.3022A/1996 Page 2 Impellers (S.S. Impellers). The S.S. impellers were to be purchased by Flowmore from M/s. Peerless Pumps Inc. U.S.A. M/s. Peerless Pumps failed to supply the S.S. Impellers and NTPC therefore agreed to purchase indigenously manufactured S.S. Impellers. Flowmore started manufacturing pumps with indigenous technology approved by NTPC. The sum and substance of the matter is that Flowmore could not supply pumps with S.S. Impellers and it could only supply pumps with bronze impellers which was agreed by NTPC. A total of 5 pumps were supplied by Flowmore to NTPC of which one was with cast iron impellers and 4 with bronze impellers. NTPC in the meanwhile on account of default of Flowmore in supplying the pumps purchased 3 CW pumps with bronze impellers from Johnston Pumps Limited, Calcutta.
3. The two charts showing the supply of pumps by Flowmore and by Johnston Pumps are as under:
"DETAILS OF C.W. PUMPS SUPPLIED BY M/s. FLOWMORE Scheduled date Actual dates of of completion completion of of Trial Trial Operation C.S(OS)No.3022A/1996 Page 3 Operation as conducted by per contract claimant
i) First CW Pump 1.7.82 20.4.84
ii) Second CW 1.7.82 16.6.84 Pump
iii) Third CW Pump 1.7.82 7.11.84
iv) Fourth CW 1.12.82 22.2.86 Pump
v) Fifth CW Pump 1.12.82 2.12.87
vi) Sixth & Seventh 1.4.83 Order cancelled CW Pumps on 1.10.1987.
Contract amended on 29.9.1988.
DETAILS OF C.W. PUMPS SUPPLIED BY M/s. Johnston to NTPC Date of LOA Schedule Actual date Date of date of of Despatch receipt at Despatch site 1st Pump 15.7.82 4.11.82 30.9.82 29.11.82 2nd Pump 15.7.82 4.11.82 31.5.83 8.9.83 3rd Pump 29.2.84 30.4.84 30.4.84 18.6.84"
4. Flowmore therefore supplied 5 pumps and 5 motors for which NTPC made payments from time to time but did not make the C.S(OS)No.3022A/1996 Page 4 payment of the last instalment being the 10% balance amount of the price. Before the remaining 6th and 7th pumps could be supplied by Flowmore, NTPC vide its letters dated 1.10.1987 and 29.9.1988 deleted the supply of the 6th and 7th pumps from the scope of the supply under the contract. Flowmore submitted its bills amounting to Rs. 24.23 lakhs on account of the balance price of 10% and other bills for supplies made and work done. Since Flowmore had a balance of Rs. 2,89,730/- in their hands out of the initial advance paid to them by the NTPC they adjusted this balance and asked for balance amount payment of Rs. 21,63,105/-. Since NTPC did not pay, Flowmore issued a legal notice dated 27.2.1990 demanding the said amount.
Finally arbitration clause in the contract was invoked and whereas Flowmore appointed Justice Avadh Behari Rohatgi, a retired Judge of this Court, NTPC appointed Justice Rajender Sachar, Retd. Chief Justice of this Court as their Arbitrator. The third Arbitrator was appointed by the Institution of Engineers who was an Engineer by profession but who unfortunately died during the pendency of the arbitration proceedings and he came to be substituted by Sh. P.P. C.S(OS)No.3022A/1996 Page 5 Dharwadkar, who was the former Chairman and Managing Director of National Building Construction Corporation.
5. The major disputes and differences which arose between the parties can be basically summarized under the following broad heads:
(i) Claim of Flowmore for the balance price payable.
(ii) Refund claim with respect to the bank guarantees encashed by NTPC.
(iii)The claim of NTPC for liquidated damages.
(iv) Respective claims of the parties for interest.
6. Keeping in view the legal position with respect to the scope of challenge to an Award under Section 30 and 33 of the Arbitration Act, 1940, I have heard the parties at length on different dates. It is settled law now that the Court cannot go into the reasonableness of the reasons of the Arbitrator. Meaning thereby, if the view of the Arbitrator is one plausible view, then, the Court will not interfere merely because it is of another view. It is also necessary that the view of the arbitrators has to be either illegal or violative of the contractual C.S(OS)No.3022A/1996 Page 6 provisions or so perverse that it calls for interference by the Court hearing objections to the Award.
7. A reading of the majority Award shows that the following conclusions have been arrived at by the Arbitrators:
a) Flowmore has been held entitled to the payment of the balance price of 10% i.e. Rs. 21,63,105/-,
b) NTPC was held disentitled to its claim for risk and purchase costs with respect to three pumps purchased from Johnston Pumps Limited.
c) NTPC has been further held disentitled to its claim for liquidated damages.
d) Flowmore has been further entitled to the bank guarantee amounts which were encashed by NTPC in as much as the counter claims including of liquidated damages of NTPC were dismissed.
e) Certain other issues and claims have also been considered in the Award such as whether the necessary tests as required under the contract were performed or not performed, whether NTPC is entitled to its claim towards interests on certain advances, whether the disputes C.S(OS)No.3022A/1996 Page 7 which arose only during the pendency of the arbitration proceedings and not before can be looked into at all or not, and so on.
8. I will now take up each of the major issues one by one to examine whether the award can be faulted with.
9. The first and the major issue which has been decided by the majority award is that Flowmore has been held entitled to its claim for balance price of 10%, namely, an amount of Rs. 21,63,105/-. The Arbitrators have held that since the contract has been performed and NTPC has received the pumps and with respect to which pumps there are absolutely no complaints and grievances, consequently it has been held that there is no reason why the contractor/ Flowmore should not be entitled to its claim of the balance price. In this regard the Arbitrators have dealt with this matter extensively from pages 31 to 37 of the Award and the important findings are that as per contractual clause 6.1.1, one of the pumps shall be selected for the prototype performance test at the manufacturer's works to determine the power consumption and its capacity on which a finding of fact is arrived at that the same was done. Clause 6.2.1 deals with the performance test.
C.S(OS)No.3022A/1996 Page 8 Such tests are required to indicate freedom from vibration and ensure satisfactory parallel operation. This test was to be done not by Flowmore but by the owner/NTPC and for which Flowmore only had to give assistance. There are findings of facts in the Award that no complaints have been at all shown with regard to either vibration or unsatisfactory parallel operation. In fact the Arbitrators note that there is a positive statement of NTPC's own witnesses which shows that the Flowmore pumps were giving satisfactory service since 1984, 1986 and 1987 when the five pumps were supplied. The witness also admits that tests were carried out as contemplated in the contract. Obviously thus there can be nothing which remains. At this stage, it is also relevant to note that the clause 14.3 which deals with performance guarantee tests specifically provided for the conduct of the test at site by the owner and not by Flowmore. The requisite performance tests as required under the contract have been done by Flowmore and this has been found as a matter of fact, thus there is no scope for interference under Sections 30 and 33 of the Arbitration Act, 1940. The Arbitrators have after considering the abovesaid facts have held that how can the owner/NTPC in view of such findings refuse to C.S(OS)No.3022A/1996 Page 9 make the payment of the balance of 10% value of the contract. The Arbitrators have held that the owner can reject the equipment if it fails to meet the guaranteed requirements( and NTPC did not reject) but it cannot say "I will accept and retain the equipment and not pay". The Arbitrators have referred to and drawn rationale from the various provisions of the Sale of Goods Act,1930 as also various other judgments showing that option was available with NTPC either to accept the goods or reject the same. Admittedly, the goods having not been rejected by the NTPC, consequently, there is no reason why the payment of price should not be made to Flowmore because more so because no damages have been alleged or have been caused to NTPC with respect to the goods in question. NTPC never wrote to Flowmore that they will reject the pumps or that the pumps supplied are defective. The majority Award notes that Flowmore's product was the best bargain in the market as tenders received from Johnston and Voltas and such other persons for the pumps with bronze impellers were in fact of a higher price. Accordingly, no fault can be found with the reasons given by the Arbitrators in entitling and awarding the claim of balance payment of the price to Flowmore.
C.S(OS)No.3022A/1996 Page 10 While dealing with this issue, I may also note that the Arbitrators at page 60 have granted to NTPC a sum of Rs.2,30,910/- as unadjusted advance lying with Flowmore. However, when one comes to the final portion of the award at page 65, the Arbitrators by an inadvertent mistake have omitted this aspect. Therefore NTPC is entitled to this amount and consequently from a sum of Rs.21,63,105 being the balance price payable by NTPC to Flowmore an amount of Rs.2,30,910 will stand adjusted and the amount of Rs.21,63,105/- will stand reduced.
10. That takes us to the claims as made by the NTPC with respect to costs of certain spares as also the risk and purchase costs incurred by NTPC for the three pumps which were purchased from M/s. Johnston.
11. As regards the issue of claim of loss suffered on account of risk and purchase, the Arbitrators have noted that before risk and purchase costs can be granted to a person who is aggrieved and against a person in breach it is necessary that what is purchased should be the same item as what was contracted for and not otherwise. In this case, the admitted position is that the contract in question was for S.S. C.S(OS)No.3022A/1996 Page 11 impellers and admittedly what was purchased from Johnston Pumps Ltd, were not S.S. Impellers but bronze impellers. That being the position the Arbitrators have held that this amounted to unilateral novation of the contract qua the impellers and thus the risk and purchase cost of a different item cannot be fastened upon Flowmore under Section 73 of the Contract Act, 1872. To this, I may add if there is a novation of the contract by purchase of substituted items then it was imperative for NTPC to give a similar offer to Flowmore because it is quite clear that Flowmore was ready to supply pumps with bronze impellers as were supplied by the Johnston and in fact NTPC received four pumps with bronze impellers from Flowmore itself amending the original contract which was for S.S. Impellers. Admittedly, this was not done in the present case and NTPC simply went ahead in purchasing pumps from M/s. Johnston containing bronze impellers without giving this offer to Flowmore. During the course of hearing, I asked the counsel for the objector to point out any correspondence by which Flowmore was put to notice that it is entitled to supply bronze impellers instead of S.S. impellers and which were being procured at a higher cost by NTPC. The counsel for the C.S(OS)No.3022A/1996 Page 12 objector could not point out any correspondence to this effect and in fact conceded that no such specific letter is on the record. The Arbitrators have accordingly on this aspect of risk and purchase cost held that this counter claim with respect to risk and purchase cost is not justified. In this regard the following important and systematic conclusions have been crisply referred to by the Arbitrators in the majority award and which are as under:
"The upshot of the above discussion is that the alleged risk purchase is not binding on Flowmore. The position can be summarised as follows:
i) The descriptive statement of SSI in Annexure-II is a contractual term.
ii) The important descriptive words regarding SSI were in the specification, and that speci-fication had to be complied with by NTPC if they wanted to make a risk purchase at the cost of Flowmore.
iii) It was an express term of the contract that the goods had to be in conformity with the description in order to give rise to a liability of Flowmore.
iv) The descriptive words of contractual obligation, namely, the condition of Stainless Steel Impellers had to be complied with.
v) If the goods did not correspond with the description and specification Flowmore did not incur any liability because NTPC was guilty of breach of condition of the contract in buying pumps from Johnston of different specifications.
vi) The condition of the contract imposed had to be strictly performed. If a condition is not performed the buyer has the right to reject.
C.S(OS)No.3022A/1996 Page 13
vii) If NTPC had a right to reject the goods with bronze impellers if
preferred by Flowmore to them they cannot accept the bronze impellers from Johnston and make Flowmore liable.
ix) The future goods which were to be manufactured by Flowmore had to conform to the condition laid down in the contract. The term of SSI is a condition and strict compliance was required, failing which the buyer was entitled to reject. The duty of the seller is very strict indeed. The liability is that in non-conformity with the contract description and of an express term of the contract there is a breach of contract.
x) If the seller fails to supply goods of the contractual description he will be guilty of breach of contract.
In the present case the goods purchased from Johnston did not accord with their description as given in the contract of Flowmore and the purchase from Johnston did not conform with the express term of the contract.
The purchase from Johnston does not bind Flowmore as the purchase did not conform with the description. It was a case of non conformity. The pumps purchased are non-compliant pumps.
Contract with Flowmore was of seven pumps. They supplied 5 pumps. NTPC claims extra cost of 3 pumps. Flowmore is not liable even for two pumps. We were surprised at counsel's pertinacity when he sought to justify NTPC's claim for 3 pumps.
We, therefore, hold that the claim of NTPC of alleged risk purchase for the amount of Rs.14,03,581/- is not tenable and is therefore rejected."
12. The aforementioned conclusions are given at the end of a detailed discussion by the Arbitrators which commences from page 20 ending with page 27 of the award. I thus do not find any fault whatsoever with the reasons or the conclusions of the Arbitrators in C.S(OS)No.3022A/1996 Page 14 this behalf. Surely, a person against whom a claim of damages on account of risk and cost purchase is sought to be imposed is entitled in case of an alteration in the contracted goods to have notice that it could have supplied the alternative goods and which admittedly was not done in this case. In fact, as stated by me while discussing the first issue that even the pumps which were accepted from Flowmore by NTPC were themselves pumps with bronze impellers because they were the best deal in the market and far more competitive to the prices than those as offered by Johnston and Voltas.
13. It has been canvassed by Mr. J.C.Seth, counsel for NTPC that NTPC was entitled to claim of the cost of the spares which Flowmore had to supply to NTPC under the contract. This claim with regard to spares has been dealt with by the Arbitrators at pages 38 and 39 of the award. The Arbitrators have in the majority award while dealing with this issue at pages 38 and 39 have clearly found as a matter of fact that since NTPC refused to pay Flowmore any amount for the spares therefore there is no question of supplying these spares. In fact Flowmore informed NTPC that it was always ready and willing to C.S(OS)No.3022A/1996 Page 15 supply the spares, if NTPC was ready to make the payment. NTPC, as has been found, was not ready to make the payment and consequently, the Arbitrators have rightly come to the finding that NTPC is not entitled to the cost of the spares. Obviously, in this case, it is not a case where cost of the spares had already been paid by NTPC to Flowmore. If that be so, it is not understood how the majority award of the arbitrators can at all be faulted.
14. That takes me to the issue with regard to whether NTPC was entitled to its claim of liquidated damages. The facts of the case clearly demonstrate that Flowmore was in fact guilty of breach of contract and delay in performance of the contract. This is quite clear as I have already set out the chart in the earlier portion of this judgment and in which chart the dates of completion as per the contract and the actual later dates of completion are mentioned. Accordingly, there is no doubt that liquidated damages in a case like this are payable without proof of actual loss. I am supported in this regard by the judgment of the Supreme Court in the case of ONGC C.S(OS)No.3022A/1996 Page 16 Vs. Saw Pipes Limited 2003(5)SCC705. The relevant paras of the judgment in ONGC's case are as under:
"46. From the aforesaid sections, it can be held that when a contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss which naturally arises in the usual course of things from such breach. These sections further contemplate that if parties knew when they made the contract that a particular loss is likely to result from such breach, they can agree for payment of such compensation. In such a case, there may not be any necessity of leading evidence for proving damages, unless the court arrives at the conclusion that no loss is likely to occur because of such breach. Further, in case where the court arrives at the conclusion that the term contemplating damages is by way of penalty, the court may grant reasonable compensation not exceeding the amount so named in the contract on proof of damages. However, when the terms of the contract are clear and unambiguous then its meaning is to be gathered only from the words used therein. In a case where agreement is executed by experts in the field, it would be difficult to hold that the intention of the parties was different from the language used therein. In such a case, it is for the party who contends that stipulated amount is not reasonable compensation, to prove the same.
66. In Maula Bux case19 the Court has specifically held that it is true that in every case of breach of contract the person aggrieved by the breach is not required to prove actual loss or damage suffered by him before he can claim a decree and the court is competent to award reasonable compensation in a case of breach even if no actual damage is proved to have been suffered in consequence of the breach of contract. The Court has also specifically held that in case of breach of some contracts it may be impossible for the court to assess compensation arising from breach.
67. Take for illustration construction of a road or a bridge. If there is delay in completing the construction of road or bridge within the stipulated time, then it would be difficult to prove how much loss is suffered by the society/State. Similarly, in the present case, delay took place in deployment of rigs and on that basis actual production of gas from platform B-121 had to be changed. It is undoubtedly true that the witness has stated that redeployment plan was made C.S(OS)No.3022A/1996 Page 17 keeping in mind several constraints including shortage of casing pipes. The Arbitral Tribunal, therefore, took into consideration the aforesaid statement volunteered by the witness that shortage of casing pipes was only one of the several reasons and not the only reason which led to change in deployment of plan or redeployment of rigs Trident II platform B-121. In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach thereof. In such a situation, if the parties have pre-estimated such loss after clear understanding, it would be totally unjustified to arrive at the conclusion that the party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of Sections 73 and 74 of the Indian Contract Act. There was nothing on record that compensation contemplated by the parties was in any way unreasonable. It has been specifically mentioned that it was an agreed genuine pre-estimate of damages duly agreed by the parties. It was also mentioned that the liquidated damages are not by way of penalty. It was also provided in the contract that such damages are to be recovered by the purchaser from the bills for payment of the cost of material submitted by the contractor. No evidence is led by the claimant to establish that the stipulated condition was by way of penalty or the compensation contemplated was, in any way, unreasonable. There was no reason for the Tribunal not to rely upon the clear and unambiguous terms of agreement stipulating pre- estimate damages because of delay in supply of goods. Further, while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages."
15. A reference to these paras clearly show that in certain contracts it is impossible to prove the damages/losses which are suffered on account of breach of contract because of the delay in performance. In such contracts it has been held that liquidated damages can be imposed and the aggrieved party is entitled to claim such liquidated C.S(OS)No.3022A/1996 Page 18 damages under Section 74 of the Contract Act, 1872. In the present case, the Arbitrators have denied NTPC the entitlement to liquidated damages, and in my opinion by a very strange reasoning of such claim being time barred. Arbitrators have held that the claim with respect to liquidated damages would arise from the date of supply of an individual pump, and, this finding of the Arbitrator is very surprising to say the least, because in one part of the award while holding the issue of limitation in favour of Flowmore, the Arbitrators have held that it is a single indivisible contract and limitation for the claim of Flowmore will commence only when the contract is completed, but for denying this claim of liquidated damages to NTPC, it has been held that the entitlement of the claim and cause of action for commencement of limitation will begin in a phased manner on different dates of the supply of individual equipments being the individual CW pumps. Surely, this finding cannot be supported because it cannot stand with the finding on a similar issue with regard to limitation qua the claims of Flowmore. This unreasonableness is surely perverse calling for interference by this Court under Sections 30 and 33 of the Act, because clearly the Arbitrators have mis-conducted C.S(OS)No.3022A/1996 Page 19 themselves and the arbitration proceedings. I, therefore, hold that NTPC was in fact entitled to an amount of Rs.5,39,100/- on account of liquidated damages claimed by it.
16. One issue which has been strenuously canvassed by Mr. J.C. Seth, counsel for the objector is that NTPC ought to have been awarded the difference in the cost of the cast iron impeller and S.S. impeller. The counsel for the objector has referred to me para 57 of the counter claim as also Annexure-42 where the calculations in this behalf are given. During the course of arguments, I put it to Mr. Seth to substantiate before me the calculations as contained in Annexure-42 to decide if such claim can be awarded to NTPC. However, except for the self serving averments made in the affidavit by way of evidence filed on behalf of the NTPC no credible evidence for payment of these amounts to a third party has been shown to me. Accordingly, there is no substance with respect to this objection which is rejected.
17. One other argument which has been pressed on behalf of the objector was that the Arbitrators have wrongly reduced the claim of NTPC from a figure of Rs.76,27,631/- to Rs.34,85,572/-. This aspect C.S(OS)No.3022A/1996 Page 20 has been dealt with by the Arbitrators in the award at page Nos. 18 and 19 of the Award. The Arbitrators have referred to the correspondence and the letters emanating from NTPC which shows that no such claim was made at any time before the arbitration proceedings commenced and therefore the Arbitrator have held NTPC disentitled to such an additional claim. Assuming for the sake of arguments, that the Arbitrators are wrong in not allowing expansion of the claims because the claim may have escaped the attention when the letter dated 15.3.1990 was written, even then I find that this difference of claim basically pertains to the claim towards entitlement for risk and purchase cost and cost of spares and so on and since I have already disallowed the basic and broad head of the risk and purchase cost and the cost of spares, therefore, once the NTPC is held disentitled to whatever amount claimed in these particular heads then even if the claim of NTPC is taken for a larger amount it shall make no difference as this head of claim has been rejected.
18. I may note for the sake of completeness that Mr. J.C.Seth canvassed that the amounts which have been encashed from bank C.S(OS)No.3022A/1996 Page 21 guarantee have been wrongly directed by the arbitrators to be paid to Flowmore. This objection is merely stated to be rejected because at best the amounts kept by encashing bank guarantees are ultimately towards the net amount which is due from one party to the other under the contract and once no claims are found due to NTPC, except the claims allowed above, surely the amounts which were encashed by NTPC with respect to the bank guarantees have been rightly held repayable by the Arbitrators to Flowmore.
19. Various other small issues with respect to alleged interest on account of advance payment and so on have been generally sought to have been canvassed on behalf of NTPC but, I am not burdening this judgment with discussion on the same because at the end of the day, what has to be seen is that the contract is performed by both the parties at different stages whether with respect to supply and with respect to payments, and that at the end of the day, minor inequities with regard to any interest on advance payment or delay in payment for supplies made cuts both ways, because it is also the case where payments would have been due to Flowmore much earlier than was C.S(OS)No.3022A/1996 Page 22 claimed by it and for the period for which it did not get the payment, it ought to have got interest. There are therefore, various aspects on which while hearing objections under Sections 30 and 33 of the Act, this court is not bound to deal with such matters which would have almost an insignificant effect on the final award passed by the Arbitrators. Accordingly, I do not consider it necessary to refer to various minor arguments repeatedly raised by Mr. Seth in this behalf because I do not consider them worthy of any acceptance whatsoever.
20. That finally takes me to the issue with regard to the interest to be awarded with respect to the claims of both the parties pursuant to the award and as modified by the present judgment. One way is that I can award the respective claims with rate of interest on such claims to either of the parties. Another way is that I can arrive at the net figure which is due from one to another, and which in this case will be from NTPC to Flowmore and therefore in the final analysis there is reduction of the total net claims which have been awarded in the award in favour of the Flowmore and against NTPC. I am doing the latter in that by the total of the two amounts under the heads of C.S(OS)No.3022A/1996 Page 23 namely of liquidated damages of Rs.5,39,100/- and the figure of Rs.2,30,910/-, I am reducing from the total amount which is awarded to Flowmore and against the NTPC. Net effect thus is that Flowmore is thus entitled to Rs.13,93,095/- from NTPC besides also the amount of bank guarantees of Rs.19,35,826/-.
The issue however is what should be the rate of interest which should be awarded . I find from the recent catena of judgments of the Supreme Court that it has directed the courts to keep in view the changed economic scenario and the consistent fall in the rates of interests, whereby the courts should be alive to the fact that the higher interest regime which was earlier permissible should no longer be adhered to. In this behalf, I must refer to the following judgments of the Supreme Court namely Rajendra Construction Co. Vs. Maharashtra Housing & Area Development Authority & ors.2005 (6) 678, McDermott International Inc. Vs. Burn Standard Co. Ltd.& ors 2006 (11) SCC 181, Rajasthan State Road Transport Corpn. Vs. Indag Rubber Ltd. (2006) 7 SCC 700 and Krishna Bhagya Jala Nigam Ltd. Vs. G.Harischandra, 2007 (2) SCC 720 which emphasise that lower rate of interest has to be granted, more so if the proceedings are pending for a long period of C.S(OS)No.3022A/1996 Page 24 time. Being bound by the ratio of the Supreme Court in the aforesaid judgments, I accordingly, award a uniform rate of 9% per annum to Flowmore and against NTPC with respect to the net amount which is granted to Flowmore and as against NTPC as granted by the award and till actual payment. I may note that this benefit which is granted to NTPC will give to NTPC a substantial relief quantified to a huge amount because at a point of time when the contract was to be performed from 1982 to 1987 the rates of interest were running as high as 18% and 24% and that too by Nationalised Banks. Further, in these years the rate of interest, was not a simple rate but was in fact compoundable quarterly. This being the position, reduction of rate of interest to 9% and that too at a simple rate, NTPC in my opinion undoubtedly gets substantial benefit.
21. That takes me to the issue of the costs to be awarded with regard to the present proceedings. Section 35 and Order XX-A of the Code of Civil Procedure, 1908, mandates that costs must follow the event. Now the Supreme Court in the case of Salem Advocate Bar Association Vs. Union of India 2005 (6) SCC 344 in para 37 has held C.S(OS)No.3022A/1996 Page 25 that it is high time that actual costs are awarded with respect to legal proceedings. I have had an occasion to recently consider this aspect in a judgment titled as ORIENTAL INSURANCE COMPANY LTD.vs. AMIRA FOODS (INDIA) LTD. numbered as OMP 319/2003 decided on 14th October,2009 and where following another single Judges judgment of this court (Madan B.Lokur, J) in Austin Nichols & Co. Vs. Arvind Behl 2006 (32) PTC 133., I have awarded actual costs. For the purpose of determining costs, I have also noted the value of claims involved and more importantly, the paying capacity of both the companies involved in the present case. I have also noted that for the imposition of costs, the objections that have been basically dismissed, however, certain objections have also been upheld and substantial relief of reduction in rate of interest is granted to the objector. Accordingly, working out a reasonable basis I feel that the non- objector/Flowmore should file in this court an affidavit with respect to the costs incurred by it for these present legal proceedings supported by the certificates from the advocates that they have received such costs for these proceedings under Section 30 and 33. This affidavit of the authorised signatory of Flowmore along with certificate of the C.S(OS)No.3022A/1996 Page 26 counsel be filed within a period of four weeks from today and 75% of such amount (not 100%) would be the costs of these proceedings which are awarded in favour of Flowmore and against the NTPC.
22. With these observations, the objection petition stands disposed of and the award dated 19.11.1996 is made rule of the court, subject to the modifications thereto as regards the reduced amount awarded to Flowmore being Rs.13,93,095/- plus Rs.19,35,826/- and interest being reduced to 9% per annum simple till actual payment of amounts as decreed.
C.S.(OS) No.3022A/1996 In view of the above order passed in I.A.No.4430/1997, the present suit stands disposed of.
VALMIKI J.MEHTA, J
October 21, 2009
Dkg/Ne
C.S(OS)No.3022A/1996 Page 27