Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 0]

Chattisgarh High Court

M/S Surendra Singh Kalra vs The General Manager, South East Central ... on 4 August, 2017

Author: Sanjay K. Agrawal

Bench: Sanjay K. Agrawal

                                                   Arb. Application No.36/2015

                                  Page 1 of 8

                                                                       NAFR

             HIGH COURT OF CHHATTISGARH, BILASPUR

                     Arbitration Application No.36 of 2015

M/s Surendra Singh Kalra, aged 45 years, S/o Shri Balwant Singh Kalra,
Railway Contractor, R/o A-507, Harsh Ashiyana, Green Park Colony,
Near Maharana Pratap Chowk, Bilaspur, Tahsil and Distt. Bilaspur (C.G.)
                                                           ---- Applicant

                                   Versus

The General Manager, South East Central Railway, Bilaspur, Distt.
Bilaspur (C.G.)
                                               ---- Non-applicant

For Applicant:            Mr. Somnath Verma, Advocate.
For Non-applicant:        Mr. Abhishek Sinha & Ms. S. Harshita, Advocates.

                 Hon'ble Shri Justice Sanjay K. Agrawal

                               Order On Board

04/08/2017

   1. This is an application filed seeking appointment of arbitrator on the

      strength of arbitration clause contained in the contract agreement

      dated 24-4-2008. The applicant entered into contract agreement

      for execution of earth-work in between Ch 600 m to 2500 m to

      4500 m to 4900 m and construction of ROB Br.No. 4A at Ch 1393

      (2x6.0x7.0 m RCC Box), diversion of road of N.H.7 and

      construction of level crossing Goomty and provision of lifting barrier

      and minor bridge No. 4 at Ch. 2020 (1x3.0x1.45 m) RCC Box

      between section BUQ-GRC on detour alignment in connection with

      Gondia-Jabalpur gauge conversion project. The approximate value

      of contract is ₹ 4,93,83,736/- and the completion period was 18

      months from the date of acceptance.             The agreement was

      executed on 7-11-2007 bearing No.191/ROB/No.4A/Min Br.No.4/

      BUQ-GRG/CEC/SECR/11.            The work was finally measured in
                                               Arb. Application No.36/2015

                            Page 2 of 8

  presence of the contractor and final bill was submitted by the

  contractor which was paid on 21-8-2014. Thereafter, the applicant

  raised claim on 4-4-2013 and issued notice on 15-4-2015 stating

  inter alia that there is price variation for additional work which he

  has executed and sought appointment of arbitrator on 15-4-2015

  which was replied by the Railways stating that clause 43(2)

  provides for no claim and once no claim certificate is issued by the

  contractor, he shall be debarred from disputing the correctness of

  the items covered by no claim certificate. Clause 63 excludes the

  remedy of arbitration in a case where no claim certificate has been

  given by the contractor and therefore no arbitrator can be

  appointed. Thereafter, the applicant has filed this application on

  17-8-2015 for appointment of arbitrator to which reply has been

  filed stating that since no claim certificate has been issued by the

  contractor and such claims are excepted matters not within the

  purview of dispute resolution by arbitration, that will debar him from

  making claim for appointment of arbitrator as such, no arbitral

  dispute exists between the parties which requires reference of

  dispute to the Arbitral Tribunal and the application deserves to be

  rejected.

2. Learned counsel for the applicant submits that no claim was issued

  by the applicant under duress and coercion and not voluntarily. No

  claim was issued under compulsion on the pressure exerted by the

  non-applicant Railways that unless such certificate is issued, final

  payment would not be disbursed, therefore to meet the financial

  liability and to overcome the hardship, no claim certificate has been
                                                   Arb. Application No.36/2015

                                Page 3 of 8

      issued and it will not come in the way for appointment of arbitrator

      and intervention by the court and as such, the application deserves

      to be allowed.

    3. Learned counsel for the non-applicant Railways would submit that

      there is no arbitral dispute exists in view of no claim certificate

      signed by the applicant under his own signature willingly and

      without protest or demur as such, this will be an explicit matter

      under clause 43 (2) of the contract agreement and arbitration is not

      the remedy and the matter cannot be referred to arbitration under

      the Arbitration and Conciliation Act, 1996.         Even thereafter,

      performance guarantee and security deposit were released in

      favour of the applicant which he did not object and willingly

      accepted. He placed reliance upon the decisions of the Supreme

      Court in the matters of National Insurance Company Limited v.

      Boghara Polyfab Private Limited1 and New India Assurance

      Company Limited v. Genus Power Infrastructure Limited 2.

    4. I have heard learned counsel appearing for the parties, considered

      their rival submissions made herein-above and also gone through

      the record with utmost circumspection.

    5. The question for consideration would be whether accord and

      satisfaction in the present case upon acceptance of entire money

      and issuance of 'No Claim Certificate' was not voluntary and

      whether the applicant was subjected to duress or coercion and as

      such, he can validly invoke the jurisdiction of this Court under

      Section 11 (6) of the Act of 1996 for appointment of arbitrator.

1   (2009) 1 SCC 267
2   (2015) 2 SCC 424
                                               Arb. Application No.36/2015

                            Page 4 of 8

6. Law on this point is very much well settled. In Boghara Polyfab

  Private Limited (supra), the Supreme Court has held that the party

  pleading duress or coercion in issuance of No Claim Certificate is

  required to establish the same. It was held as under:-

        "25. We may next examine some related and
        incidental issues.     Firstly, we may refer to the
        consequences of discharge of a contract. When a
        contract has been fully performed, there is a discharge
        of the contract by performance, and the contract comes
        to an end. In regard to such a discharged contract,
        nothing remains - neither any right to seek
        performance nor any obligation to perform. In short,
        there cannot be any dispute. Consequently, there
        cannot obviously be reference to arbitration of any
        dispute arising from a discharged contract. Whether
        the contract has been discharged by performance or
        not is a mixed question of fact and law, and if there is a
        dispute in regard to that question, that is arbitrable.
        But there is an exception. Where both parties to a
        contract confirm in writing that the contract has been
        fully and finally discharged by performance of all
        obligations and there are no outstanding claims or
        disputes, courts will not refer any subsequent claim or
        dispute to arbitration. Similarly, where one of the
        parties to the contract issues a full and final discharge
        voucher (or no due certificate as the case may be)
        confirming that he has received the payment in full and
        final satisfaction of all claims, and he has no
        outstanding claim, that amounts to discharge of the
        contract by acceptance of performance and the party
        issuing the discharge voucher/certificate cannot
        thereafter make any fresh claim or revive any settled
        claim. Nor can he seek reference to arbitration in
        respect of any claim.

        26. When we refer to a discharge of contract by an
        agreement signed by both parties or by execution of a
        full and final discharge voucher/receipt by one of the
        parties, we refer to an agreement or discharge voucher
        which is validly and voluntarily executed. If the party
        who has executed the discharge agreement or
        discharge voucher, alleges that the execution of such
        discharge agreement or voucher was on account of
        fraud/coercion/undue influence practiced by the other
        party and is able to establish the same, then obviously
        the discharge of the contract by such agreement/
        voucher is rendered void and cannot be acted upon.
                                                     Arb. Application No.36/2015

                                  Page 5 of 8

             Consequently, any dispute raised by such party would
             be arbitrable."
    7. In the matter of Union of India and others v. Master

      Construction Company3, the Supreme Court has held that bald

      plea of fraud, coercion, duress or undue influence is not enough

      and the party who sets up such a plea must prima facie establish

      the same by placing material before the Chief Justice/his

      designate. It was observed as under:-

             "18. In our opinion, there is no rule of the absolute
             kind. In a case where the claimant contends that a
             discharge voucher or no-claim certificate has been
             obtained by fraud, coercion, duress or undue influence
             and the other side contests the correctness thereof, the
             Chief Justice/his designate must look into this aspect to
             find out at least, prima facie, whether or not the dispute
             is bona fide and genuine. Where the dispute raised by
             the claimant with regard to validity of the discharge
             voucher or no-claim certificate or settlement
             agreement, prima facie, appears to be lacking in
             credibility, there may not be necessity to refer the
             dispute for arbitration at all."

             19. It cannot be overlooked that the cost of
             arbitration is quite huge - most of the time, it runs in six
             and seven figures. It may not be proper to burden a
             party, who contends that the dispute is not arbitrable
             on account of discharge of contract, with huge cost of
             arbitration merely because plea of fraud, coercion,
             duress or undue influence has been taken by the
             claimant. A bald plea of fraud, coercion, duress or
             undue influence is not enough and the party who sets
             up such plea must prima facie establish the same by
             placing material before the Chief Justice/his designate.
             If the Chief Justice/his designate finds some merit in
             the allegation of fraud, coercion, duress or undue
             influence, he may decide the same or leave it to be
             decided by the Arbitral Tribunal. On the other hand, if
             such plea is found to be an after-thought, make-believe
             or lacking in credibility, the matter must be set at rest
             then and there.

             22. The above certificates leave no manner of doubt
             that upon receipt of the payment, there has been full
             and final settlement of the contractor's claim under the

3   (2011) 12 SCC 349
                                                Arb. Application No.36/2015

                              Page 6 of 8

         contract. That the payment of final bill was made to the
         contractor on 19-6-2000 is not in dispute. After receipt
         of the payment on 19-6-2000, no grievance was raised
         or lodged by the contractor immediately.               The
         concerned authority, thereafter, released the bank
         guarantee in the sum of Rs. 21,00,000/- on 12-7-2000.
         It was then that on that day itself, the contractor lodged
         further claims."

8. Recently, in Genus Power Infrastructure Limited (supra), Their

   Lordships again emphasized the need for material to be placed

   before the Chief Justice/his designate establishing the plea of

   coercion or duress and held as under:-

         "10. In our considered view, the plea raised by the
         respondent is bereft of any details and particulars, and

cannot be anything but a bald assertion. Given the fact that there was no protest or demur raised around the time or soon after the letter of subrogation was signed, that the notice dated 31.03.2011 itself was nearly after three weeks and that the financial condition of the respondent was not so precarious that it was left with no alternative but to accept the terms as suggested, we are of the firm view that the discharge in the present case and signing of letter of subrogation were not because of exercise of any undue influence. Such discharge and signing of letter of subrogation was voluntary and free from any coercion or undue influence. In the circumstances, we hold that upon execution of the letter of subrogation, there was full and final settlement of the claim. Since our answer to the question, whether there was really accord and satisfaction, is in the affirmative, in our view no arbitrable dispute existed so as to exercise power under section 11 of the Act. The High Court was not therefore justified in exercising power under Section 11 of the Act."

9. The question for consideration would be whether the applicant has been able to establish the plea of coercion and duress in issuance of No Claim Certificate.

10. The applicant issued no claim certificate under his own signature which states as under: -

NO CLAIM CERTIFICATE Arb. Application No.36/2015 Page 7 of 8 Certified that I have no claim against the work executed by me from date of commencement i.e. dt. 10-6-2010 till vide CC-11 & Final.
C.A.No.191/ROB/No.4A/Min Br.No.4/BUQ-GRG/CEC/ SECR/11 Name of work : Execution of earth work in between ch 600m to 2500m and 4500m to 4900m and construction of ROB Br. No.4A at Ch 1393 (2 x 6.0 x 7.0 m RCC Box) diversion of road of N.H.7 and construction of level crossing Goomty and lifting construcrossing Goomty and provision of lifting barrier and Minor bridge No.4 at Ch 2020 (1x3x1.45m) RCC Box between section BUQ-GRG on detour alignment in connection with Gondia-Jabalpur gauge conversion project.

11. Not only this, thereafter, performance guarantee was released in favour of the applicant on 6-5-2014 and security deposit was also released on 9-10-2014 and on that basis, rights and obligations under the contract stand discharged and the contractual obligations came to an end. The application for appointment of arbitrator was filed on 17-8-2015 in which it has been stated in paragraph 2 that certificate was obtained under threat of non-preparation of final bill and non-payment, but it has not been substantiated by filing any material on record.

12. The applicant's conduct in issuing no claim certificate under his own seal and signature on his letter-pad and even after the issuance of no claim certificate, obtaining performance guarantee on 6-5-2014 and release of security deposit on 9-10-2014 would show that the plea of duress taken by the applicant is not sincere and it is only in order to overcome the difficulty in getting such a claim.

13. In my considered opinion, the applicant has failed to establish the plea that 'No Claim Certificate' has been signed under duress or Arb. Application No.36/2015 Page 8 of 8 coercion. No material has been brought on record to establish such plea. No details and particulars have been given and no protest or demur was made by the applicant at the time when 'No Claim Certificate' was signed on 31-5-2012 or soon after the letter was signed on 31-5-2012. Even after when the notice of this application was served to the non-applicant, no such plea was taken in the application. Such a plea of duress is absolutely lacking in this entire application and material filed by the applicant. Therefore, in my view the issue is not arbitral in view of clause 43 (2) of the general conditions of contract. Thus, I am of the opinion that the satisfaction accorded by the applicant by accepting final bill and issuing no claim, was voluntary and not under duress or coercion. It was full and final satisfaction of claim and therefore no arbitral dispute exists in order to exercise the power under Section 11(6) of the Arbitration and Conciliation Act, 1996 following the principles of law laid down by the Supreme Court in Boghara Polyfab Private Limited (supra), Master Construction Company's case (supra) and Genus Power Infrastructure Limited (supra).

14. Accordingly, the arbitration application for appointment of arbitrator deserves to be is hereby dismissed leaving the parties to bear their own cost(s). However, this will not bar the applicant for resolution/ adjudication of dispute in accordance with law.

Sd/-

(Sanjay K. Agrawal) Judge Soma