Section 266 in West Bengal Municipal Corporation Act, 2006

266. [ Order of demolition of building or stoppage of erection of buildings in certain cases and appeal. [Substituted by West Bengal Act No. 17 of 2016, dated 20.1.2017.]

(1)Where the erection of any building or the execution of any work has been commenced, or is being carried on, or has been completed without or contrary to the sanction referred to in section 263 or in contravention of any of the provisions of this Act or the rules and the regulations made thereunder, the Commissioner may, in addition to any other action that may be taken under this Act, make an order directing that such erection or work shall be demolished' by the person at whose instance the erection or the work has been commenced or is being carried on or has been completed within such period, not being less than five days and more than fifteen days from the date on which a copy of the order of demolition with a brief statement of the reasons therefor has been delivered to such person, as may be specified in the order:Provided that no order of demolition shall be made unless such person has been given, by means of a notice served in such manner as the Commissioner may think fit, a reasonable opportunity of showing cause why such order shall not be made:Provided further that where the erection or the execution has not been completed, the Commissioner may by the same order or by a separate order, whether made at the time of the issue of the notice under the first proviso or at any other time, direct such person to stop the erection or the execution until the expiry of the period within which an appeal against the order of demolition if made may be preferred under sub-section (3).Explanation. - In this chapter, "the person at whose instance" shall mean the owner, occupier or any other person who causes the creation of any building or execution of any work to be done, including alterations or additions if any, or does it by himself.Provided also that the Commissioner, by order, delegate his powers and functions under the first and the second proviso of this sub-section to the Special Officers, appointed by the Commissioner with the approval of the State Government on such terms and conditions as may be determined by the Corporation, and the expenses for payment of such officers shall be borne from the Municipal Fund.
(2)The Commissioner may make an order under sub-section (1), notwithstanding the fact that the assessment of such building has been made for the levy of the property tax on lands and buildings.
(3)Any person aggrieved by an order of the Commissioner made under sub-section (1) may, within thirty days from the date of the order, prefer an appeal against the order to the Municipal Building Tribunal appointed under section 295A.
(4)Where an appeal is preferred under sub-section (3) against an order made under sub-section (1), the Municipal Building Tribunal may stay the enforcement of the order on such terms, if any, and for such period, as it may think fit:Provided that where the erection of any building or the execution of any work has not been completed at the time of the order made under sub-section (1), no order staying the enforcement of the order made under that sub-section shall be made by the Municipal Building Tribunal unless a surety, sufficient in the opinion of the said Tribunal, has been given by the appellant for not proceeding with such erection or work pending the disposal of the appeal.
(5)Save as provided in this section, no court shall entertain any suit, application or other proceeding for injunction or other relief against the Commissioner to restrain him from taking any action or making any order in pursuance of the provisions of this section.
(6)Every order made by the Municipal Building Tribunal on appeal and, subject to such order, the order made by the Municipal Commissioner under sub-section (1) shall be final and conclusive.
(7)Where no appeal has been preferred against an order made by the Commissioner under sub-section (1) or where an order under that sub-section has been confirmed on appeal, whether with or without modification, the person against whom the order has been made shall comply with the order within the period specified therein, or as the case may be, within the period, if any, fixed by the Municipal Building Tribunal on appeal, and on the failure of such person to comply with the order within such period, the Commissioner may himself cause the building or the work to which the order relates to be demolished and the expenses of such demolition shall be recoverable from such person as an arrear of tax under this Act.
(8)Notwithstanding anything contained in this Chapter, if the Mayor-in- Council is of the opinion that immediate action is called for in relation to a building or a work being carried on in contravention of the provisions of this Act, it may, for reasons to be recorded in writing, cause such building or work to be demolished forthwith.]