Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Gujarat High Court

Ashish Construction Company vs General Manager, on 27 April, 2018

Author: M.R. Shah

Bench: M.R. Shah

C/IAAP/1/2018                                                                ORDER



    IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
                R/PETN. UNDER ARBITRATION ACT NO.  1 of 2018
=============================================
                      ASHISH CONSTRUCTION COMPANY
                                  Versus
                            GENERAL MANAGER,
=============================================
Appearance:
MR ARPIT P PATEL(5497) for the PETITIONER(s) No. 1
MR RAVI KARNAVAT(1650) for the RESPONDENT(s) No. 1,2,3
=============================================
    CORAM: HONOURABLE MR.JUSTICE M.R. SHAH
 
                               Date : 27/04/2018
 
                                  ORAL ORDER

[1.0] An   objection   is   raised   by   Shri   Karnavat,   learned   Advocate  appearing on behalf of the respondents that in view of the special  conditions of contract more particularly clause 37.3 which would  have an overriding effect over the general conditions of contract  upon   which  the  petitioner  has  relied  upon   and  has  requested  to  refer   the   dispute   to   arbitration   and   as   the   dispute   between   the  parties is for the value above 20% of the value of the contract, such  claim / dispute which is of the value more than 20% of the value of  the   contract,   provision   of   clauses   63   and   64   and   other   relevant  clauses of general conditions of contract will not be the remedy for  settlement   of   such   disputes   and   therefore,   the   dispute   is   not  required to be referred to arbitration. One another object which is  raised by Shri Karnavat, learned Advocate appearing on behalf of  the   respondents   that   even   otherwise   as   per   the   terms   and  conditions of the contract the Officer of the Railway shall be the  Arbitrator   to   resolve   the   dispute   between   the   parties   and/or   to  adjudicate the dispute between the parties. 

[2.0] To the aforesaid, Shri Patel, learned Advocate appearing on  Page 1 of 4 C/IAAP/1/2018 ORDER behalf of the petitioner has vehemently submitted that as such the  respondent   Authorities   have   served   their   objection   to   refer   the  dispute   between   the   parties   to   arbitration   and   infact   they   never  raised any objection invoking clause 37.3 of the special conditions  of the contract. It is submitted that therefore in view of section 4 of  the Arbitration Act, the objection raised on behalf of the respondent  is required to be overruled. 

[3.0] Now,   so   far   as   the   objection   raised   on   behalf   of   the  respondent Authorities that even as per the terms and conditions of  the contract, in case of any dispute between the parties, the dispute  is required to be referred to the Arbitrator who shall be the Officer  of the Railway Authorities is concerned, it is submitted that as per  section   12(5)   of   the   Arbitration   Act,   1996   as   amended   vide   Act  No.3 of 2016, such an officer shall be ineligible to be appointed as  an Arbitrator. It is submitted that in the present case as such the  respondent Authorities asked the undertaking from the petitioner  for   waiver   of   section   12(5)   of   the   Arbitration   Act,   however   the  petitioner   had   not   given   such   undertaking   and   had   insisted   for  section 12(5) of the Arbitration Act. Therefore, it is requested to  dispose   of   the  objection   to  the  Arbitrator   by  appointing  the  sole  Arbitrator. 

[4.0] Heard learned Advocates appearing for respective parties on  the objection raised by Shri Karnavat, learned Advocate appearing  on behalf of the respondent Authorities raised against referring the  dispute to arbitration. 

[4.1] Now, so far as the objection raised by the respondent Railway  Authorities   invoking   Clause   37.3   of   the   special   conditions   of  contract is concerned, at the outset it is required to be noted that  Page 2 of 4 C/IAAP/1/2018 ORDER after   the   petitioner   served   a   notice   under   Section   21   of   the  Arbitration   Act,   1996   invoking   arbitration,   the   respondent  Authority did not raise any objection invoking Clause 37.3 of the  special   conditions   of   the   contract.   On   the   contrary   vide  communications   dated   16.10.2017   and   03.01.2018   asked   an  undertaking and called upon the petitioner to submit an agreement  as   per   Annexure­XII,   towards   waiver   under   Section   12(5)   and  section 31­A(5) of the Arbitration Act, 1996 to the effect that the  applicant   waives   section   12(5)   of   the   Arbitration   Act,   1996   by  which   the   Officers   of   Railway   Authorities   can   be   said   to   be  ineligible   to   become   an   Arbitrator.   As   such,   such   insistence   /  agreement   on   the   part   of   the   Railway   Authorities   is   absolutely  uncalled   for.   Be   that   as   it   may,   even   the   petitioner   did   not  specifically   stated   that   he   is   not   agreeable   to   waiver   of   section  12(5) of the Arbitration Act, 1996. As observed herein above, as  such   no   other   objections   were   raised   more   particularly   invoking  Clause 37.3 of special conditions of contract and did not raise any  objection that the dispute is not arbitrable, in view of Clause 37.3  of   the   special   conditions   of   the   contract.   Therefore,   considering  section 4 of the Arbitration Act, 1996, it can be said that there is a  waiver   of   the   objection   on   the   part   of   the   respondent   Railway  Authorities. 

[4.2] Now,   so   far   as   the   submission   on   behalf   of   the   Railway  Authorities that as per the contract only the Officers of the Railway  Authorities is required to act as Arbitrator is concerned, in view of  section 12(5) of the Arbitration Act, 1996, same is not sustainable.  Section 12(5) of the Arbitration Act, 1996 as amended by Act No.3  of 2016 provides that notwithstanding any prior agreement to the  contrary, any person whose relationship, with the parties or counsel  or   the   subject­matter   of   the   dispute,   fails   under   any   of   the  Page 3 of 4 C/IAAP/1/2018 ORDER categories specified in the Seventh Schedule shall be ineligible to  be   appointed   as   an   arbitrator.   However,   the   parties   may,  subsequent   to   disputes   having   arisen   between   them,   waive   the  applicability   of   sub­section   (5)   of   section   12   by   an   express  agreement in writing, which in the present case the petitioner has  not agreed to waive. Under the circumstances, section 12(5) of the  Arbitration   Act,   1996   shall   be   applicable   and   the   Officer   of   the  Railway   Authorities   shall   be   ineligible   to   be   appointed   as   an  Arbitrator. 

[5.0] For the reasons stated above, the objection raised on behalf of  the   Railway   Authorities   against   referring   the   dispute   to   the  arbitration is hereby over­ruled. Now, the dispute is required to be  referred to the Arbitrator. 

Stand over to 04.05.2018.

(M.R. SHAH, J.)  Ajay** Page 4 of 4