Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 0]

Orissa High Court

M/S. Sainik Mining & Allied Services Ltd ... vs Mahanadi Coal Fields Ltd. & Others ... on 11 March, 2010

Equivalent citations: AIR 2010 (NOC) 683 (ORI.)

Author: I.M.Quddusi

Bench: I.M.Quddusi

                                    W.P.(C) NO.5203 OF 2009

          In the matter of an application under Articles 226 and 227 of the
          Constitution of India.

          M/s. Sainik Mining & Allied Services Ltd & another .......                     Petitioners.

                                                       Versus.

          Mahanadi Coal Fields ltd. & others                  ...........                  Opp.parties


                         For petitioners       :       M/s. Ashok Mohanty,
                                                            Pradeep Kumar Mohapatra &
                                                            M. Mishra.


                         For opp. parties      :       M/s. Rakesh Sharma, S.R.Singh
                                                            Samanta, P.R. Patnaik and
                                                            B. Binay.
                                                            (for opposite party nos.1 & 3)


          PRESENT

                 THE HON'BLE SHRI ACTING CHIEF JUSTICE I.M.QUDDUSI
                                       AND
                        THE HON'BLE SHRI JUSTICE B.K.NAYAK

          --------------------------------------------------------------------------------------
          Date of hearing : 03.11.2009 :               Date of judgment: 11.03.2010


B.K.NAYAK, J.

In this writ application, the petitioner-company challenges the letter dated 02.03.2009 under Annexure-1 issued by opposite party no.2, General Manager (Technical Co-ordination), Mahanadi Coalfields Limited (in short 'M.C.L.') threatening to initiate action towards cancellation of contract, forfeiture of earnest money and taking up the contract work at petitioner's risk and cost. The further prayer is to direct 2 the opposite parties to release petitioners' all previous dues concerning different earlier works

2. The case of the petitioner is that the opposite parties, Mahanadi Coalfields Limited and its functionaries issued notice dated 26.3.2008 under Annexure-2 inviting tender under Ref. No.MCL/SBP/ GM(TC)/NIT-477/2008/2008 for the work Extraction and Transfer of Coal/Coal measure strata by deploying "Surface Miners" on hiring basis at Kulda OCP, Basundhara- Garjanbahal Area of M.C.L. In pursuance of the notice the petitioner participated in the tender process and having been found qualified in both technical and price bids, the said work was awarded in its favour and acceptance of petitioner's bid was communicated by the opposite parties in their letter dated 31.10.2008 under Annexure-3. The petitioner company issued letter dated 12.11.2008 acknowledging receipt of opposite parties' letter under Annexue-3. The opposite parties also issued work order dated 04.11.2008 vide Annexure-5. In the work order the opposite parties acknowledged receipt of the earnest money of Rs.7,55,600/- deposited by the petitioner and also asked the petitioner to deposit a further sum of Rs.25,35,732/-, since as per the terms of the bid, the contractor was to deposit performance security @ 5% of annualised value of contract vide letter dated 03.12.2008. In their letter under Annexure-6, the opposite parties further instructed the petitioner for submission of the aforesaid performance security amount at M.C.L. Headquarters in the form of Demand Draft. The petitioner was also further reminded in the said letter 3 to submit other documents like Indemnity Bond, Insurance, updated R.C. Books and fitness certificate of the fleet for execution of agreement.

It is the further case of the petitioner that the petitioner- company had executed various works under M.C.L. earlier since 1998 for which a sum of about Rs.15.00 crores (roughly) was due to the petitioner from the opposite parties, which the latter have not yet released, for which the petitioner-company could not furnish the performance security of Rs.25,35,732/- in connection with the present contract because of its financial stringency. The petitioner, therefore, in its letter dated 13.12.2008 under Annexure-8 requested the opposite parties for 15 days time beyond 15.12.2008 for maintenance and repair of machine/equipments before starting execution of the work. On receipt of the aforesaid letter, the opposite parties requested the petitioner vide their letter dated 17.12.2008 under Annexure-9 to start the work latest by 26.12.2008 and also to fulfil the formalities like submission of security deposit and the required papers concerning execution of agreement. The petitioner-company having expressed their helplessness in arranging finances intimated vide letter dated 19.1.2009 under Annexure-12 that they were not in a position to take the contract work. In reply, the opposite parties in their letter dated 20.1.2009 (Annexure-13) requested the petitioner to start the work within 15 days failing which action would be taken for forfeiture of earnest money as per Clause No.6.1 of General Terms and Conditions of the bid document. Thereafter, the petitioner- company having failed to start the work, the opposite parties issued the 4 impugned letter dated 02.03.2009 (Annexure-1) requesting the petitioner to start the work within 15 days of the issue of the said letter, failing which M.C.L. would be compelled to initiate action towards cancellation of contract, forfeiture of earnest money deposited and taking up of the work at the risk and cost of the petitioner-company.

3. It is urged by the petitioner that the opposite parties having held up substantial amount of money of the petitioner-company in connection with other works done by them previously, the company was not in a position to arrange finances to start the present work in question and, therefore, M.C.L's notice under Annexure-1 threatening to cancel the contract and to forfeit earnest money and take up the work at the risk and cost of the petitioner is unreasonable, unjust and illegal. It is the further submission that all the formalities with regard to execution of agreement having not been completed, the contract had not reached finality and the person aggrieved (opposite parties) cannot claim risk and cost whimsically.

4. The opposite parties filed a counter affidavit in reply stating that the petitioner was issued with L.O.I. and the same was accepted by the petitioner and further work order was also issued in favour of the petitioner, which amounts to awarding of the contract in favour of the petitioner, and the agreement is a mere formality as the agreement consists of the N.I.T. including its terms and conditions, LOI and the work order with all its terms and conditions. It is stated that the contentions of the petitioner-company being contrary to the conditions mentioned in 5 the Notice Inviting Tender (NIT) they are not sustainable. It is also stated that Clause-3.3 (a) of Instructions to Bidders in the tender notice, stipulates that to qualify for award of the contract, evidence of possessing adequate working capital (at least 20% of the annualised value of this work) inclusive of access to lines of credit and availability of other financial resources to meet the requirement, and that being aware of this condition, the petitioner submitted certificate regarding adequate working capital along with the tender, which was taken into account at the time of scrutinising the technical bid as well as the financial bid by the M.C.L. authorities and the petitioner being the L-1, work order was issued in its favour. It is further stated that the petitioner having already informed in its letter dated 19.1.2009 (Annexure-12) that it would not take up the work, it was not open to the petitioner to challenge the notice of cancellation of the contract under Anexure-1. The opposite parties have every right to act on the basis of the conditions provided in the instruction to bidders, general terms and conditions, special terms and conditions as per Annexure-2 for the failure of the petitioner to execute the work. It is further stated in the counter affidavit that the writ petition has become infructuous inasmuch as the opposite parties have already cancelled the contract/work order vide office order dated 09.04.2009 as per Annexure-A. Their further plea is that after cancellation the work was retendered in which the petitioner has participated.

5. The questions that fall for consideration are whether there was a valid contract between the parties in absence of a written 6 agreement and whether the opposite parties were legally entitled to issue the impugned notice of cancellation of the contract and forfeiture of earnest money etc., under Annexure-1.

6. Admittedly, the notice inviting tender contains detailed procedure and terms and conditions with regard to tender process including award of the contract. The petitioner-company having been found qualified in the technical as well as price bids, its bid was accepted and it was issued with work order on the terms and conditions including the special terms and conditions which are part of the tender notice and were agreed to by the petitioner when it made the offer by way of submission of tender and by the opposite parties when they accepted the bid of the petitioner and issued work order in its favour. Clause-29 of "Instruction to Bidders" provides for notification of the award and formation of the contract. Clause-29.2 specifically stipulates that the notification of the award will constitute the formation of the contract, subject only to the furnishing of a performance security/security deposit in accordance with Clause-30. It is thus clear that by way of acceptance of the bid of the petitioner and the issuance of work order by the opposite parties the contract was formed and execution of a written agreement was a mere formality and was not a condition precedent for the formation of the contract.

Clause-2(i) of the 'Special Terms and Conditions of tender' inter alia stipulates that for delay in starting the work after 45 days of receipt of L.O.I, the management shall get the work executed at the L-1 7 contractor's cost and risk for the daily average quantity and the difference in the rate shall be recovered from the L-1 tenderers SD/other payments due of the tenderer with M.C.L.

7. In view of the aforesaid conditions and stipulations, the opposite parties were well within their right to issue notice of cancellation of the contract and the work order and to forfeit the earnest money and to take up the work otherwise at the risk and cost of the petitioner, since admittedly despite being given several extensions of time the petitioner could not start the work and, on the contrary, expressed inability to execute the work. The action of the opposite parties in issuing the notice under Annexure-1, therefore, cannot be termed as unreasonable or unjust.

8. It is the further undisputed fact, as revealed from the counter affidavit and the documents annexed thereto that the contract/work order has already been cancelled on 09.04.2009 under Annexure-A and the said cancellation order has not been challenged by the petitioner. It is the further undisputed fact that after cancellation of the contract, the process of retender of the work has been initiated by the opposite parties and the petitioner has already participated in the said retender process, which only goes to show that the petitioner has no grievance about the cancellation of the work order issued in its favour.

9. So far as the relief of issuing directions to the opposite parties to release all previous dues concerning different works executed by the petitioner earlier, the details of which have been set out in paragraph-8 of 8 the writ petition, is concerned, the same cannot be worked out in this writ petition in as much as the petitioner can take recourse to the modes of settlement as agreed upon between the parties under the respective contracts.

10. For the foregoing reasons, we find no merit in this writ petition, which is accordingly dismissed without any order for costs.