Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

Rajasthan High Court - Jodhpur

State Of Rajasthan vs M/S. Manda Developers And Builders Pvt. ... on 8 August, 2025

Author: Vinit Kumar Mathur

Bench: Vinit Kumar Mathur

[2025:RJ-JD:35429-DB]

      HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                       JODHPUR
                   D.B. Spl. Appl. Writ No. 181/2019
1. The State Of Rajasthan, Through The Chief Secretary, Water
Resources Department, Jaipur.
2.Chief Auditor General (Cag), Government Of Rajasthan, Jaipur.
3.The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rswrp), Water Resource Department, Jaipur.
4.The     Chief   Engineer,        Irrigation      (North),         Water   Resources
Division, Hanumangarh.
5.The Executive Engineer, Water Resources, South Division,
Sriganganagar.
                                                                       ----Petitioners
                                        Versus
M/s. Gsco Infrastructure Pvt. Ltd., A Private Limited Company
Situated At Sco- 67, Sector 20-C, Chandigarh (U.t).
                                                                      ----Respondent
                   D.B. Spl. Appl. Writ No. 334/2019
1. State Of Rajasthan, Through The Chief Secretary, Department
Of Water Resources, Jaipur, Rajasthan.
2. The Chief Auditor General (Cag), Government Of Rajasthan,
Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rwsrp), Department Of Water Resources, Jaipur.
4. The Chief Engineer, Irrigation Zone Jodhpur, Jodhpur.
5. The Executive Engineer, Jawai Canal, Irrigation Division,
Sumerpur, Pali (Raj.).
                                                                       ----Petitioners
                                        Versus
M/s. Manda Developers And Builders Pvt Ltd., Shiv Shakti Vihar,
Opposite 220Kv Power House, Jaipur Road, Bikaner Through Its
Power Of Attorney Holder Er. Hardayal Singh S/o Shri Kripa Singh
General Manager (Technical) Of The Company.
                                                                      ----Respondent
                   D.B. Spl. Appl. Writ No. 463/2019
1. State Of Rajasthan, Through The Chief Secretary, Department
Of Water Resources, Jaipur, Rajasthan.
2. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rwsrp), Department Of Water Resources, Jaipur.
3. The Superintending Engineer, Water Resource Circle, Pali


                        (Downloaded on 12/08/2025 at 09:45:17 PM)
 [2025:RJ-JD:35429-DB]                  (2 of 13)                             [SAW-181/2019]


(Raj.).
4. The Additional Chief Engineer, Water Resources Division,
Jodhpur (Raj.).
                                                                           ----Petitioners
                                        Versus
M/s.      Rameshwarlal         Manaram,            Through          Its    Partner    Sh.
Rameshwarlal S/o Sh. Manaram, R/o Sarvodaya Basti, Bikaner.
                                                                          ----Respondent
                   D.B. Spl. Appl. Writ No. 501/2019
1. State Of Rajasthan, Through The Chief Secretary, Department
Of Water Resources, Jaipur, Rajasthan.
2. The Chief Auditor General (Cag), Government Of Rajasthan,
Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rwsrp), Development Of Rajasthan, Jaipur.
4. The Additional Chief Engineer, Irrigation Zone Jodhpur,
Jodhpur.
5. The Executive Engineer, Water Resource Division, Pali (Raj.).
                                                                           ----Petitioners
                                        Versus
M/s. Manda Developers And Builders Pvt. Ltd., Shiv Shakti Vihar,
Opposite 220Kv Power House, Jaipur Road, Bikaner Through Its
Power Of Attorney Holder Er. Hardayal Singh S/o Shri Kripa Singh
General Manager (Technical) Of The Company.
                                                                          ----Respondent
                   D.B. Spl. Appl. Writ No. 565/2019
1. State Of Rajasthan, Through The Chief Secretary, Department
Of Water Resources, Jaipur, Rajasthan.
2. The Chief Auditor General (Cag), Government Of Rajasthan,
Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rwsrp), Department Of Water Resources, Jaipur.
4. The Chief Engineer, Water Resource Zone Jodhpur, Jodhpur.
5. The Executive Engineer, Jawai Canal, Irrigation Division, Sirohi
(Raj.)
                                                                           ----Petitioners
                                        Versus
M/s. Gopala Ram Pema Ram, Village And Post Karmisar, Ward


                        (Downloaded on 12/08/2025 at 09:45:17 PM)
 [2025:RJ-JD:35429-DB]                  (3 of 13)                       [SAW-181/2019]


No. 2, Bikaner (Raj.) Through Its Proprietor, Pema Ram S/o Pana
Ram by caste Jat, aged about 53 years, R/o.Karmisar Ward No.6,
Bikaner (Rajasthan).
                                                                    ----Respondent
                   D.B. Spl. Appl. Writ No. 819/2019
1. State Of Rajasthan, Through The Chief Secretary, Department
Of Water Resources, Jaipur, Rajasthan.
2. The Chief Auditor General (Cag), Government Of Rajasthan,
Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rwsrp), Department Of Water Resources, Jaipur.
4. The Chief Engineer, Irrigation Zone, Jodhpur, Jodhpur (Raj.).
5. The Executive Engineer, Water Resource Division, Sirohi (Raj.)
                                                                     ----Petitioners
                                        Versus
M/s. Manda Developers And Builders Pvt. Ltd., Shiv Shakti Vihar,
Opposite 220Kv Power House, Jaipur Road, Bikaner Through Its
Power Of Attorney Holder Er. Hardayal Singh S/o Shri Kripa Singh
General Manager (Technical) Of The Company.
                                                                    ----Respondent
                   D.B. Spl. Appl. Writ No. 943/2019
1. State Of Rajasthan, Through The Secretary, Water Resources
Department, Jaipur.
2. Accountant General (Ag), Rajasthan Government Of India,
Jaipur.
3. The Chief Engineer, Water Resource Department, Rajasthan
Jaipur.
4. The Chief Engineer, Water Resources, North Zone,
Hanumangarh.
5. The Executive Engineer, Water Resources Divsion-I,
Hanumangarh.
                                                                     ----Petitioners
                                        Versus
Bhullar Constructions Pvt. Ltd., A Register Company Situated At
1534, , Sector 18D, Chandigarh (Ut).
                                                                    ----Respondent
                   D.B. Spl. Appl. Writ No. 986/2019
1. State Of Rajasthan, Through The Chief Secretary, Water


                        (Downloaded on 12/08/2025 at 09:45:17 PM)
 [2025:RJ-JD:35429-DB]                  (4 of 13)                       [SAW-181/2019]


Resources Department, Jaipur.
2. Chief Auditor General (Cag), Government Of Rajasthan, Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rswrp), Water Resource Department, Jaipur.
4. The Chief Engineer, Irrigation (North), Water Resources,
Hanumangarh.
5. The Executive Engineer, Gaggar Flood Control And Drainage
Division- Hanumangarh.
                                                                     ----Petitioners
                                        Versus
M/s. Amar Nath Aggarwal Construction Pvt. Ltd., A Private
Limited Company Situated At 3038-A, Guru Kanshi Marg,
Bhatinda (Punjab).
                                                                    ----Respondent
                  D.B. Spl. Appl. Writ No. 1104/2019
1. State Of Rajasthan, Through The Chief Secretary, Water
Resources Department, Jaipur.
2. Chief Auditor General (Cag), Government Of Rajasthan, Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring,
Project (Rswrp), Water Resource Department, Jaipur.
4. The Chief Engineer, Irrigation (North), Water Resources
Division, Hanumangarh.
5. The Executive Engineer, Water Resources, Division-Ii,
Hanumangarh.
                                                                     ----Petitioners
                                        Versus
M/s. Subhash Chander And Co., A Partnership Firm Situated At
129 P, Sector 15, Part Ist Gurgaon (Haryana)
                                                                    ----Respondent
                  D.B. Spl. Appl. Writ No. 1249/2019
1. State Of Rajasthan, Through The Chief Secretary, Water
Resources Department, Jaipur.
2. Chief Auditor General (Cag), Government Of Rajasthan, Jaipur.
3. The Chief Engineer, Rajasthan Water Sector Restructuring
Project (Rswrp), Water Resource Department, Jaipur.
4. The Chief Engineer, Irrigation (North), Water Resources
Division, Hanumangarh.
5. The Executive Engineer, Water Resourced, South Division,
Sriganganagar.


                        (Downloaded on 12/08/2025 at 09:45:17 PM)
     [2025:RJ-JD:35429-DB]                  (5 of 13)                        [SAW-181/2019]


                                                                          ----Petitioners
                                            Versus
    M/s. Gsco Infrastructure Pvt. Ltd., A Private Limited Company
    Situated At Sco-67, Sector 20-C, Chandigarh (U.t).
                                                                        ----Respondent
                      D.B. Spl. Appl. Writ No. 1275/2019
    1. State Of Rajasthan, Through The Chief Secretary, Water
    Resources Department, Jaipur.
    2. Chief Auditor General (Cag), Government Of Rajasthan, Jaipur.
    3. The Chief Engineer, Rajasthan Water Sector Restructuring
    Project (Rswrp), Water Resource Department, Jaipur.
    4. The Chief Engineer, Irrigation (North), Water Resources
    Division, Hanumangarh.
    5. The Executive Engineer, Water Resources, South Division,
    Sriganganagar.
                                                                           ----Petitioner
                                            Versus
    M/s. Gsco Infrastructure Pvt. Ltd., A Private Limited Company
    Situated At Sco-67, Sector 20-C, Chandigarh (U.t.).


                                                                        ----Respondents


    For Petitioner(s)             :     Mr. Sajjan Singh Rathore, AAG
    For Respondent(s)             :     Mr. Vinay Kothari
                                        Mr. Bhavyadeep Singh
                                        Mr. Ayush Gyoyal
                                        Mr. Gaurav Ranka for
                                        Mr. Muktesh Maheshwari
                                        Mr. Sunil Joshi



            HON'BLE MR. JUSTICE VINIT KUMAR MATHUR

HON'BLE MR. JUSTICE ANUROOP SINGHI Order REPORTABLE : 08/08/2025

1. The delay in filing the appeals is condoned. Accordingly, the applications for condonation of delay are allowed. (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (6 of 13) [SAW-181/2019]

2. With the consent of learned counsel for the parties, the matter is taken up today itself and heard finally at this stage.

3. The present batch of special appeals arise out of common judgment dated 14.09.2018 passed by learned Single Judge in batch of writ petitions, therefore, they are being decided by this common judgment.

4. Briefly noted the facts in the present appeals are that the respondents herein are registered firms/companies enlisted as contractors with the Irrigation Department, Government of Rajasthan. They were awarded various contracts under the Rajasthan Water Sector Restructuring Project (RWSRP), which were sponsored by the International Development Association and funded by the International Bank for Reconstruction and Development--collectively referred to as "The World Bank". The Central Government had issued two notifications--Customs Notification No. 108/1995 dated 28.08.1995 and Excise Notification No. 85/1999 dated 06.07.1999--granting exemption from excise duty for goods falling under the Schedule to the Central Excise Tariff Act, 1985, when imported into India for execution of projects financed by the United Nations or any other international organization. As per the conditions contained in the bid documents, to avail such exemption, contractors were required to obtain an excise exemption certificate from the Executive Head of the Project Implementing Authority, countersigned by the Principal Secretary or Secretary of the Finance Department of the concerned State Government, verifying that the goods were required for execution of the approved project. The respondent firms submitted declarations and supporting documents in the (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (7 of 13) [SAW-181/2019] prescribed format, indicating the list of goods such as cement, diesel, mechanical compactors, trucks, etc., for which the exemption was sought. Upon due verification, exemption certificates were issued by the competent authority and duly countersigned by the Finance Secretary. The respondents availed excise duty exemption on the basis of these certificates, including in particular for cement. After the completion of the work by the respondents, they received letters dated 05.03.2013 and other similar communications from the concerned Executive Engineer, informing that the exemption availed on cement was irregular and proposing recovery of the excise amount. The ground for such recovery was that cement, being an indigenous good manufactured by an Indian company, did not qualify as an "imported" good as contemplated under the relevant notifications. It was also alleged that the exemption certificate had been obtained belatedly, contrary to Clause 13.3 of the Instructions to Bidders (ITB), which required submission of the certificate at the bid stage. Subsequently, audit objections were raised by the Comptroller and Auditor General of India (CAG), pointing out irregularities in the issuance of such exemption certificates to the respondents. Acting on these objections, the department initiated recovery proceedings against the respondents for the excise duty benefit allegedly availed irregularly. The respondents challenged the said recovery proceedings as well as the audit objections by filing writ petitions before the learned Single Judge of the High Court. It is pertinent to note that the CAG, despite being a necessary party, neither appeared before the Writ Court nor filed any reply. The learned Single Judge, vide judgment dated (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (8 of 13) [SAW-181/2019] 14.09.2018, allowed the writ petitions and quashed the recovery orders primarily on the ground that no opportunity of hearing had been afforded to the respondents before initiating recovery, and further, that no action had been taken against the government officials who had issued and countersigned the exemption certificates. Hence, the present appeals have been filed.

5. Learned counsel for the appellants vehemently submitted that the Central Government had issued two notifications dated 28.08.1995 and 06.07.1999 exempting excise duty payable on the goods falling under the Schedule prescribed under the Central Excise Tariff Act, 1985 particularly to those goods which are imported into India for execution of projects financed by the United Nation or an International Organization and, therefore, the respondents were under an obligation to get the exemption in- conformity with those notifications only. He further submits that as per the bid document, the contractor was required to submit the exemption certificate at the time of submission of the bid document, however, the same was not submitted on 14.02.2003 and the certificate was filed after a period of five months i.e. on 19.07.2003, therefore, the same was in violation of clause 13.3 of the Instructions to Bidders (hereinafter referred to as 'ITB'). Since the exemption has been obtained by the respondents in contravention of the conditions of ITB, therefore, the same has been erroneously granted to them. Learned counsel further submits that as per the Notification issued by the Union of India, the benefit of exemption could have been availed only on the goods which were imported, however, in the present case, the exemption has been granted on Cement, which is not permissible (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (9 of 13) [SAW-181/2019] in the Notification issued by the Central Government on the ground that Cement is not an imported goods as the same has been manufactured by an Indian Company. Learned counsel further submits that the recoveries have been effected on account of wrongly issued exemption certificates, therefore, there is no illegality. Learned counsel for the appellants has relied upon the judgment of Hon'ble Supreme Court in case of State of Gujrat Vs. Arcelor Mittal Nippon Steel India Ltd. (2022) 6 SCC 459, wherein, it was held that all the terms and conditions contained in the exemption Notification shall prevail, and the person claiming the exemption must fulfill and satisfy all the eligibility criteria mentioned in the exemption Notification. He submits that since the conditions mentioned in the exemption Notification has not been fulfilled by the respondents, therefore, the recovery orders have rightly been issued. Learned counsel has further relied upon judgment of Hon'ble Supreme Court in the case of Commissioner of Custom (Import) Mumbai vs. Dilip Kumar and Company, (2018) 9 SCC 1, wherein, it was held that the interpretation of the Taxation Statute must be strict, and in case of any ambiguity, the benefit of such ambiguity must be strictly interpreted in favour of revenue/state. On the strength of these arguments, he submits that learned Single Judge has not considered the matter in correct perspective and has wrongly allowed the writ petition. He, therefore, prays that the present appeals may be allowed and the order dated 14.09.2018 may be quashed and set aside.

6. Per contra, learned counsel for the respondents, while supporting the judgment dated 14.09.2018, submits that the learned Single Judge has correctly taken into consideration all the (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (10 of 13) [SAW-181/2019] relevant factors and has rightly come to this conclusion that the exemption granted to the respondents is perfectly justified and the same falls in conformity with the Notification dated 108/95-CE, Dated 28.08.1995. Learned counsel submits that the respondents were entitled to get exemption of all the goods falling under the Central Excise and Tariff Act, if the same was supplied to the United Nations or an International organization for their official use or supplied to the projects financed by the United nations or an international organization and approved by the Government of India. Learned counsel submits that all the three conditions mentioned in the Notification have been fulfilled as the work undertaken by the respondents was financed by the international organization, the goods were falling under the category of exemption and the same was approved by the Government of India. Learned counsel further submits that the exemption, which has been granted to them and utilized by them, cannot be unilaterally recovered as the benefit of the same has been utilized by the appellants and has been passed to the other stakeholders while executing the contract in hand. Learned counsel for the respondents submits that the recovery notices have been issued, without giving an opportunity of hearing to the respondents in utter violations of principles of natural justice. To buttress his contentions, learned counsel for the respondents has relied upon the judgments rendered by Hon'ble Supreme Court in case of Pondicherry State Cooperative Consumer Federation Ltd. vs. Union Territory of Pondicherry, (2007) 10 VST 630, Birla Jute & Industries vs. State of M.P. & Anr, (2000) 5 Superme Court Cases 271 and a judgment passed by Division (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (11 of 13) [SAW-181/2019] Bench of this Court in D.B. Civil Writ Petition No.3234/1998, (Commissioner, Commercial Taxes, Rajasthan & Anr. vs. Rajasthan Taxation Tribunal, Jodhpur & Ors)., decided on 12.11.2013. He, therefore, prays that the special appeals preferred by the appellants may be dismissed.

7. We have considered the submissions made at the Bar and gone through the relevant record of the case including the impugned order dated 14.09.2018.

8. At the very outset, we note that the learned Single Judge has considered the matter threadbare and has rightly come to the conclusion that as per the CAG Note, the recovery proceedings have been initiated. It is noted that the exemption certificates were issued by the competent authorities of the respondents Department after duly satisfying themselves that the case of the respondents fall within the four corner of the Notification dated 28.08.1995. It is also noted that the respondents, while undertaking the work financed by the international organization, are using the goods falling under the Schedule of the Central Excise and Tariff Act, 1985 under the category of exempted goods as the same has been approved by the Government of India. Therefore, no illegality has been committed by the respondents for getting the exemption of the same. We also note that the undisputed facts, narrated above, show that the work executed by the respondents was financed by an international organization and that the goods used for the purpose of undertaking the work was Cement and the same was falling within the category of exempted goods, and the list of the same was approved by the Government of India. Thus, in our opinion, the parameters (Downloaded on 12/08/2025 at 09:45:17 PM) [2025:RJ-JD:35429-DB] (12 of 13) [SAW-181/2019] mentioned in the Notification dated 28.08.1995 have been fulfilled by the respondents for availing the exemption on the use of Cement in the project financed by the international organization and, therefore, they have rightly been granted the exemption certificate on the basis of which they have obtained the exemptions.

9. The argument of learned counsel for the appellants that there is delay in filing the exemption certificate will not defeat the purpose for which the same has been issued.

10. It is also noted that before issuing the recovery notices to the respondents, no opportunity of hearing was granted to them and on a pointed query raised by the Court to the learned counsel for the appellants, he fairly admits that before issuing the order of recovery, no opportunity of hearing was granted.

11. In the considered opinion of this Court, even the recovery order was issued in gross and utter violation of principle of natural justice, therefore, the same is also not sustainable. Hence, the same was liable to be quashed and set aside.

12. We are of the view that the judgments relied upon by the appellants in case of State of Gujrat Vs. Arcelor Mittal Nippon Steel India Ltd (supra) is having no applicability in the present case as the respondents are fulfilling and satisfying all the eligible conditions for exemption made in the Notification dated 28.08.1995.

13. Further, the judgment replied upon by the appellants in case of Commissioner of Custom (Import) Mumbai vs. Dilip Kumar and Company(supra) is also having no application in the present set of facts discussed hereinabove.

(Downloaded on 12/08/2025 at 09:45:17 PM)

[2025:RJ-JD:35429-DB] (13 of 13) [SAW-181/2019]

14. In the considered opinion of this Court, no interference is warranted in the judgment of the learned Single Bench, whereby, the writ petitions have been allowed.

15. Accordingly, the special appeals fail and the same are dismissed.

16. The stay applications and other pending applications, if any, also stand disposed of.

                                   (ANUROOP SINGHI),J                               (VINIT KUMAR MATHUR),J
                                    68-SanjayS/-




                                                           (Downloaded on 12/08/2025 at 09:45:17 PM)




Powered by TCPDF (www.tcpdf.org)